Permanent occupancy | | | 3/10/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6804 issued 3-10-97 to the Gym Outfitter in Vista Village.
|
Permanent Occupancy | | 3/7/1997 | 3/7/1997 | | DONE |
|
|
|
|
INSP - Final | 2/26/1997 | 2/26/1997 | 2/26/1997 | P | PASS |
Jim Storey
|
|
|
02/26/97 301 - FINAL FOR C/O FNL -OK FINAL ROUTED FOR SIGN OFFS ì
|
INSP - Final | 1/9/1997 | 1/10/1997 | 1/10/1997 | A | FAIL |
Jim Storey
|
|
|
01/10/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Sprinkler Rough-in/Hydro | 11/7/1996 | 11/8/1996 | 11/8/1996 | A | PASS |
|
|
|
UG HYDRO TEST PASSED
|
INSP-Supply line flush | 11/7/1996 | 11/7/1996 | 11/7/1996 | | PASS |
|
|
|
FLUSH WITNESSED
|
INSP - Final | 1/3/1997 | 1/6/1997 | 1/6/1996 | A | PASS |
|
|
|
tested alarm checked sprinklers for obstructions
|
INSP - Framing/Rough-in | 12/8/1995 | 12/8/1995 | 12/8/1995 | P | PART |
|
|
|
12/08/95 338 - FRAMING ON STAIR WALL ok to cover all but what is involve correction calcs are to be on jobsite when recall to 301
|
INSP - Final | 11/27/1995 | 11/27/1995 | 11/27/1995 | P | PART |
Jim Storey
|
|
|
|
INSP - Final | 11/27/1995 | 11/27/1995 | 11/27/1995 | | PART |
Jim Storey
|
|
|
11/27/95 301 -
|
INSP - Final | 11/24/1995 | 11/24/1995 | 11/24/1995 | A | PART |
Jim Storey
|
|
|
11/24/95 301 - friday
|
INSP - Framing/Rough-in | 11/17/1995 | 11/20/1995 | 11/20/1995 | A | PART |
Jim Storey
|
|
|
11/20/95 301 -
|
Inspection Record Card- Bld | | | 11/17/1995 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/17/1995 | | |
|
|
|
|
Received Certificate of Value | 11/17/1995 | | 11/17/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 11/17/1995 | | PASS |
|
|
|
RECEIVED RESUBMITTALS TO RESOLVE BASEMENT PROBLEM, ATTACHED TO PLANS AND IN FILE, REVISED PERMIT VERBAGE, ISSUE
|
Permit taken to Permit Desk | | | 11/17/1995 | | PASS |
|
|
|
ISSUE
|
Plan resubmittals received | 11/17/1995 | | 11/17/1995 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/17/1995 | | PASS |
|
|
|
REVISED FILES
|
Plan Reviewer's activity | | | 11/15/1995 | | PASS |
|
|
|
PLAN REVIEW, PHONE CONVERSATION WITH ARCH, PLAN ANALYSIS, FAX CORRECTIONS TO ARCH, MARK-UP PLANS, PERMIT-PLAN INPUT, WAIT FOR REVISED CERT OF VALUE.
|
Waiting for Cert. of Value | 11/15/1995 | | 11/15/1995 | | PEND |
|
|
|
REVISED CERTIFICATE NEEDED TO COVER THE WORK IN THE BASEMENT.
|
Print Pending Permit.LaserJet4 | | | 11/15/1995 | | PASS |
|
|
|
FILES
|
Plan resubmittals received | 11/13/1995 | | 11/13/1995 | | |
|
|
|
|
Plan resubmittals requested | 11/13/1995 | | 11/13/1995 | | PEND |
|
|
|
preplan review revealed no information on two walls, stair enclosur, basement, some spaces within the units, and wall and floor/ceiling assemblies between tenants.
|
Received Certificate of Value | | | 10/24/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/17/1995 | | 10/20/1995 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 10/17/1995 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 10/12/1995 | | |
|
|
|
|