CHANGE STATUS TO (D) | | | 8/16/1996 | | DONE |
|
|
|
|
INSP - Letter of compliance | 5/24/1996 | 5/24/1996 | 5/24/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED # 11059
|
INSP - Letter of compliance | 5/24/1996 | 5/24/1996 | 5/24/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED # 11059
|
INSP - Final | 5/23/1996 | 5/24/1996 | 5/24/1996 | A | PASS |
|
|
|
05/24/96 338 - FINAL REINSPECT made ok FNL -OK FINAL
|
INSP - Final | 5/21/1996 | 5/21/1996 | 5/21/1996 | | FAIL |
|
|
|
/ / 338 - energy seal fail clean crawlspace
|
INSP - Final | 5/17/1996 | 5/20/1996 | 5/20/1996 | P | CANC |
|
|
|
05/17/96 338 - done by others
|
INSP - Framing/Rough-in | 3/15/1996 | 3/15/1996 | 3/19/1996 | P | CANC |
|
|
|
03/15/96 222 - FRAME REINSPECTION
|
INSP - Energy code compliance | 3/18/1996 | 3/18/1996 | 3/18/1996 | P | PASS |
|
|
|
03/18/96 338 - WILL CHECK THE TUB DRAIN SEAL AT THE FINAL WHENTHE CRAWL WATER
|
INSP - Framing/Rough-in | 3/18/1996 | 3/18/1996 | 3/18/1996 | P | PASS |
|
|
|
03/18/96 338 - WILL CHECK THE TUB DRAIN SEAL AT THE FINAL WHEN WATER IS CRAWL AREA
|
INSP - Framing/Rough-in | 3/14/1996 | 3/14/1996 | 3/14/1996 | P | FAIL |
|
|
|
03/14/96 338 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to insulate only
|
INSP - Framing/Rough-in | 3/13/1996 | 3/13/1996 | 3/13/1996 | P | FAIL |
|
|
|
03/13/96 338 - NO ADDRESS NO INSP
|
Issue PAID IN FULL permit | | | 11/17/1995 | | I |
|
|
|
|
Permit taken to Permit Desk | | | 11/8/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/8/1995 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/8/1995 | | |
|
|
|
|
INSP - Footings | 11/7/1995 | 11/7/1995 | 11/7/1995 | P | PASS |
Jim Storey
|
|
|
11/07/95 301 -
|
Plan Reviewer's Copy of Permit | | | 10/26/1995 | | P |
|
|
|
|
Dwelling recd. by Plan Check | | | 10/24/1995 | | |
|
|
|
|
Application received | | | 10/23/1995 | | |
|
|
|
|