Permanent Occupancy | | 11/28/1997 | 11/28/1997 | | DONE |
|
|
|
|
Permanent occupancy | | | 11/28/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #7063 issued 11-28-97 to Micron Semiconductor, Inc.
|
INSP - Final | 10/13/1997 | 10/14/1997 | 10/14/1997 | A | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL routed for sign offs and need to send co to joe card attch
|
INSP-Final Inspection | 8/21/1997 | 8/21/1997 | 8/22/1997 | P | PART |
|
|
|
building 3 fab 2 pollution abatement missing head in penthouse and north west corner over duct
|
INSP - Wall cover | 12/3/1996 | 12/3/1996 | 12/3/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - GWB -OK SHEETROCK NAILING fire wall
|
INSP - Wall cover | 12/3/1996 | 12/3/1996 | 12/3/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - GWB -OK SHEETROCK NAILING fire wall
|
INSP - Framing/Rough-in | 9/26/1996 | 9/27/1996 | 9/27/1996 | A | PASS |
Jim Storey
|
|
|
09/27/96 301 - CALL JOE DALSOGLIO - ###-####. FRAM-OK FRAMING
|
INSP - Conference | 8/2/1996 | 8/5/1996 | 8/5/1996 | | |
|
|
|
advised to schedule alarm test witnessing, advised to obtain approved sprinkler plans from contractor for this project, advised to schedule hydrostatic test witnessing for sprinklers, advised on need for nfpa placards for hazardous materials....work in progress.
|
Issue PAID IN FULL permit | | | 11/15/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 11/9/1995 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 11/9/1995 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/8/1995 | | PASS |
|
|
|
|
Received Certificate of Value | | | 11/4/1995 | | PASS |
|
|
|
|
Waiting for Cert. of Value | | | 10/4/1995 | | PEND |
|
|
|
|
Routing - BUILDING | 9/28/1995 | | 10/4/1995 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/20/1995 | | 9/22/1995 | | PASS |
|
|
|
|
Application received | | | 9/19/1995 | | PEND |
|
|
|
|