Permanent Occupancy | | 10/17/1997 | 10/17/1997 | | DONE |
|
|
|
|
INSP - Final | 10/16/1997 | 10/17/1997 | 10/17/1997 | A | PASS |
Bob Archibald
|
|
|
Corrections made ok.
|
Permanent occupancy | | | 10/17/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #7027 issued 10-17-97 to the Overlook Condos.
|
INSP - Final | 9/25/1997 | 9/26/1997 | 9/26/1997 | P | FAIL |
Bob Archibald
|
|
|
SAID BOB A GOING TO DO. Guardrails,handrails and glazing require correction.
|
INSP-Final Inspection | 9/24/1997 | 9/25/1997 | 9/25/1997 | P | PASS |
Rick Jackson
|
|
|
inspected by 407
|
Print Occupancy Form | | | 11/6/1996 | | |
|
|
|
|
(F) Reprint permit | | | 10/9/1996 | | |
|
|
|
|
INSP - Energy code compliance | 9/4/1996 | 9/4/1996 | 9/4/1996 | P | PASS |
|
|
|
unit 204
|
INSP - Energy code compliance | 9/4/1996 | 9/4/1996 | 9/4/1996 | P | PASS |
|
|
|
unit 205
|
INSP - Energy code compliance | 9/4/1996 | 9/4/1996 | 9/4/1996 | P | PASS |
|
|
|
unit 104
|
INSP - Energy code compliance | 9/4/1996 | 9/4/1996 | 9/4/1996 | P | PASS |
|
|
|
unit 103
|
INSP - Energy code compliance | 9/4/1996 | 9/4/1996 | 9/4/1996 | P | PASS |
|
|
|
UNIT 103-104-204-205
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PASS |
|
|
|
/ / 400 -
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PASS |
|
|
|
/ / 400 -
|
INSP - Framing/Rough-in | 8/29/1996 | 8/30/1996 | 8/30/1996 | A | PASS |
|
|
|
UNITS 103 - 104 - 204 - 205.
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PASS |
|
|
|
/ / 400 - units 103 104 204 205
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PASS |
|
|
|
/ / 400 -
|
INSP - Conference | 8/29/1996 | 8/29/1996 | 8/29/1996 | | PASS |
|
|
|
/ / 400 - confer with Krazan testing-req special insp scpoe of work ac
|
INSP - Framing/Rough-in | 9/5/1996 | 8/28/1996 | 8/28/1996 | A | FAIL |
|
|
|
G-1 #204
|
INSP - Framing/Rough-in | 9/5/1996 | 8/28/1996 | 8/28/1996 | A | FAIL |
|
|
|
G-1 unit #104
|
INSP - Framing/Rough-in | 9/5/1996 | 8/28/1996 | 8/28/1996 | A | FAIL |
|
|
|
G-1 unit #205
|
INSP - Framing/Rough-in | 9/5/1996 | 8/28/1996 | 8/28/1996 | A | FAIL |
|
|
|
G-1 unit #103
|
INSP - Energy code compliance | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | PASS |
|
|
|
07/23/96 333 - bath party wall and ceiling only FRAM-OK FRAMING INSL-OK INSULATION
|
INSP - Framing/Rough-in | 7/8/1996 | 7/8/1996 | 7/8/1996 | P | FAIL |
|
|
|
07/08/96 333 - cn placed
|
INSP - Footings | 6/28/1996 | 7/1/1996 | 7/1/1996 | A | FAIL |
|
|
|
07/01/96 333 - PUMP TRUCK AT 10:30 cn placed
|
INSP - Carpentry | 6/23/1996 | 6/23/1996 | 6/23/1996 | | PASS |
|
|
|
/ / 400 - walk thru with jim
|
INSP - Carpentry | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PASS |
|
|
|
/ / 400 - walk thru with james unit G1
|
INSP - Conference | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PASS |
|
|
|
/ / 400 - pre-job confer with super & subs
|
INSP - Carpentry | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PASS |
|
|
|
/ / 400 - walk thru with james unit G1
|
INSP - Foundation | 5/28/1996 | 5/29/1996 | 5/29/1996 | P | CANC |
Dave Lightfoot
|
|
|
05/28/96 337 - EARLY P.M.
|
INSP - Footings | 5/23/1996 | 5/24/1996 | 5/24/1996 | A | PASS |
|
|
|
05/23/96 400 - EARLY A.M. setbacks seem ok
|
(F) Reprint permit | | | 5/2/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/1/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/1/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/29/1996 | | PASS |
|
|
|
files
|
Routing - PUBLIC WORKS | 3/28/1996 | | 3/29/1996 | | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 3/29/1996 | | PASS |
|
|
|
issue
|
Received Certificate of Value | 3/29/1996 | | 3/29/1996 | | |
|
|
|
|
Plan Received by (PRP) | 12/12/1995 | | 3/29/1996 | | PASS |
|
|
|
03/29/96 16:04:32 PRP - this action updated by action script from <<>> in Case No. BLD95-1791
|
Routing - FIRE | 3/27/1996 | | 3/27/1996 | | PASS |
|
|
|
|
Routing - FIRE | 1/29/1996 | | 2/16/1996 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 1/25/1996 | | PASS |
|
|
|
received corrections
|
Routing - FIRE | 12/21/1995 | | 1/11/1996 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 12/19/1995 | | 12/21/1995 | | FAIL |
|
|
|
Needs civil stamp. Contacted Larry Tierman at ###-####.
|
Plan resubmittals requested | 12/19/1995 | | 12/19/1995 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/19/1995 | | PEND |
|
|
|
FILES
|
Waiting for Cert. of Value | 12/19/1995 | | 12/19/1995 | | |
|
|
|
|
Plan Reviewer's activity | | | 12/19/1995 | | PEND |
|
|
|
FEES COLLECTED FOR THIS PERMIT ARE TO BE CREDITED TO ALL FOUR SECTIONS OF THIS BASE PERMIT NUMBERS. SEE 5122 S. SURPRISE WAY, UNITS G.2, G.3, G.4 ALSO.
|
Plan Reviewer's activity | | | 12/18/1995 | | PEND |
|
|
|
PLAN REVIEW, MARK-UP, CORRECTION LIST, FAX AND MAIL TO LARRY TIERNAN AND ARCH OF RECORD, PERMIT PLAN INPUT, FORWARD BACK TO PW THEN TO FIRE. WAITING RESUBS.
|
Routing - MECHANICAL | 12/12/1995 | | 12/14/1995 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 11/14/1995 | | 12/13/1995 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 12/12/1995 | | 12/12/1995 | | PASS |
|
|
|
|
Routing - PLUMBING | 11/22/1995 | | 11/22/1995 | | PASS |
|
|
|
|
Routing - PLANNING | 11/15/1995 | | 11/16/1995 | | PASS |
|
|
|
|
Routing - MECHANICAL | 10/26/1995 | | 11/15/1995 | | FAIL |
|
|
|
|
Received partial PAYMENT | | | 10/27/1995 | | |
|
|
|
|
Routing - PLUMBING | 10/23/1995 | | 10/25/1995 | | FAIL |
|
|
|
|
Routing - ELECTRICAL | 10/20/1995 | | 10/23/1995 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 10/10/1995 | | 10/20/1995 | | FAIL |
|
|
|
|
(F) Reprint permit | | | | | |
|
|
|
|
Routing - BUILDING | 1/11/1996 | | | | |
|
|
|
|
Routing - BUILDING | 3/29/1996 | | | | PEND |
|
|
|
|
Application received | | | | | |
|
|
|
|