Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD95-01891
StatusFinaled
Name THE PIZZA PIPELINE
Site Address 111 S BROADWAY AVE Unit: 127
Project NameBROADWAY 111
Customer Number 
ePlanReviewNo
Description
To remodel an existing 1,206 sq.ft. (OLD BOISE BOX OFFICE) tenant space to convert from office to take out pizza tenant by installation of appliances, walk-in cooler, misc partition walls, cabinets and equipment per approved plans on file and attached requirement lists. A new Certificate of Occupancy must be obtained by the tenant prior to occupying this space. A separate Plumbing, Mechanical, and Electrical Permits must be obtained for this project. Plan Check # 749-95. PRP INITIAL CERTIFICATE OF VALUE ON FILE. ELEC. 3,900 PLG. 3,500 MECH. 2,700
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 1/30/19961/30/1996 DONE
Details
INSP - Final1/29/19961/30/19961/30/1996APASS
DetailsWes Worcester
SUITE #127 OCC CARD TAKEN TO KATHY
INSP - Permanent occupancy  1/30/1996 PASS
Perm. Occ. Cert. #6281 issued 1-30-96 to the Pizza Pipeline in the Broadway 111 complex.
INSP - Temporary occupancy  1/26/1996 PASS
Temp. Occ. Cert. #3134 issued 1-126-96 to the Pizza Pipeline.
INSP - Final1/25/19961/25/19961/25/1996 PART
DetailsWes Worcester
/ / 342 - temp elec
INSP - Final1/25/19961/25/19961/25/1996 PART
DetailsWes Worcester
/ / 342 - temp elec
Issue PAID IN FULL permit  12/29/1995
Issue PAID IN FULL permit  12/29/1995
Print Pending Permit.LaserJet4  12/28/1995 PASS
FILES
Print Pending Permit.LaserJet4  12/28/1995
Plan Received by (PRP)12/12/1995 12/28/1995 PASS
Details
12/28/95 15:48:07 PRP - this action updated by action script from <<>> in Case No. BLD95-1891
Routing - FIRE12/18/1995 12/28/1995 PASS
Permit taken to Permit Desk  12/28/1995 PASS
Inspection Record Card- Bld  12/28/1995
Received Certificate of Value12/27/1995 12/27/1995
Plan resubmittals received12/27/1995 12/18/1995
Plan resubmittals received  12/18/1995 PASS
E PLANS CONVERTED TO FLOOR PLANS???? OK.
Routing - MECHANICAL12/12/1995 12/18/1995 PASS
MECHANICAL MUST REVIEW FOR HOOD CLEARIFICATION ETC.
Telephone call  12/12/1995 PEND
CALLED SEAN WHALEN AND ASKED FOR FLOOR PLAN WITH PARTITION WALL DETAIL INCLUDING BRACING, AREA USAGES, COOLER SPECS, CABINET DETAILS.
Routing - PUBLIC WORKS11/22/1995 11/27/1995 PASS
Routing Off Site - C.D.H11/9/1995 11/21/1995 PASS
CONTACTED SEAN WHALEN AT ###-#### FOR C.D.H. PICKUP.
Plan routing begun/TENANTS  11/9/1995
Route to Central District Health, Public Works, Plumbing, Mechanical then back to Plan Check. After Plan Check route to Fire Department.
(F) Reprint permit  11/7/1995
Application received  11/7/1995 MYS
INSP - Final1/25/19961/26/19961/16/1995APART
DetailsWes Worcester
UNIT #127 Temporary ok
Routing - BUILDING12/28/1995   PEND