INSP - Energy code compliance | 11/15/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
Alan Hauser
|
|
|
11/15/96 350 - INSULATION OK, OK TO COVER
|
INSP - Framing/Rough-in | 11/12/1996 | 11/12/1996 | 11/12/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - CORRECTIONS ON FRAME CORRECTED, OK TO INSULATE
|
INSP - Framing/Rough-in | 11/7/1996 | 11/7/1996 | 11/7/1996 | P | FAIL |
Alan Hauser
|
|
|
11/07/96 350 - NO FRAME, CORRECTIONS TO BE FIXED BEFORE INSULATION
|
INSP - Conference | 5/6/1996 | 5/6/1996 | 5/6/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - Conference on framing.
|
INSP - Footings | 3/20/1996 | 3/20/1996 | 3/20/1996 | P | PART |
Jim Sly
|
|
|
03/20/96 316 - Footings and stem walls poured about 6-8 months prior to inspection....has been backfilled...from what I can see and in talking with the owner, the footing seems to be marginal and minimum
|
Issue PAID IN FULL permit | | | 12/14/1995 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/21/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 11/21/1995 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/21/1995 | | |
|
|
|
|
Dwelling recd. by Plan Check | | | 11/18/1995 | | |
|
|
|
|
Application received | | | 11/7/1995 | | |
|
|
|
|