Permit Information
Permit NumberBLD95-02024
StatusFinaled
Name THE COURT HOUSE INC
Site Address 7211 W COLONIAL DR
Project Name 
Customer Number 
ePlanReviewNo
Description
To upgrade the existing COURTHOUSE INC. exercise facility based on a Code Review Analysis of existing fire & life safety deficiencies and the outstanding correction notices from past projects. All per approved plans, Code Review Analysis specifying corrections required and time frame for project completion as outlined by Pat McKeegan, architect, and modified by Tim Hogland, Building Department Director. Separate electrical and mechanical permits are required. PC210-94 drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  10/15/2008  
CHANGE STATUS TO (D)  8/16/1996
INSP - Permanent occupancy7/31/19967/31/19967/16/1996
DetailsMarv Burrus
PERM OCC. CERT #6503 ISSUED TO COURTHOUSE INC.
INSP - Final7/16/19967/16/19967/16/1996 PASS
Details
/ / 338 - OCC REC CARD SIGNED BY 325 OK BY ME OTHER AGENCIES ARE APPRO
Permanent Occupancy 7/15/19967/15/1996 DONE
Details
INSP - Conference7/5/19967/8/19967/8/1996ACANC
DetailsWes Worcester
CONF/W MECHANICAL CONTRACTOR AND THE MECH. INSPECTOR AT JOB SITE. TIME TO BE DETERMINED. Stuart handled w/Perry and I wasn't needed
INSP - Final7/1/19967/2/19967/2/1996PPART
Details
07/03/96 338 - CALL DWIGHT BUTLIN - ###-####. EARLY P.M. HE CALLED & SA OTH-OTHER AGENCIES NOT APPROVED WILL BRING PROPER PAPERWORK DOWN TO BUIL DEPT FOR SIGNOFFS.
INSP - Wall cover4/2/19964/2/19964/2/1996PPART
Details
SHEETROCK NAILING 2 hour walla in the concealed area between ceilings and floors above corridors.
INSP - Wall cover4/1/19963/29/19964/1/1996APART
Details
2 hour wall repair in the attic
INSP - Framing/Rough-in3/28/19963/28/19963/28/1996PNR
Details
03/28/96 338 - RESCHEDULAD TIL TOMORROW
INSP - Framing/Rough-in3/26/19963/26/19963/26/1996PPASS
Details
03/26/96 338 - CALL DWIGHT ###-####... partial ok to cover
INSP - Framing/Rough-in3/20/19963/21/19963/21/1996APART
Details
03/21/96 338 - drywall ok at the stair enclosures only
Issue PAID IN FULL permit  2/12/1996
Inspection Record Card- Bld  12/20/1995
Routing - FIRE12/12/1995 12/19/1995 PASS
Permit taken to Permit Desk  12/19/1995 PASS
Plan Reviewer's Copy of Permit  12/13/1995
Plan resubmittals received  12/8/1995
Received updated sets of plans from Pat.
Meeting  12/4/1995
Met with Pat to have one set of plans stamped by him as the architect and to receive on additional set for review. It was discovered by plan comparison that the set of plans I had was not the latest set. Pat will provide an additional set that shows all revisions dated 7-12-95.
Additional plans submitted  12/4/1995
Received a stamped set of plans from Pat McKeegan in response to my request that he had only submitted one set of plans. The set of plans I have also need stamped by Pat. In comparison of plans Pat had brought to submitt with plans previously received, they were found to be different. Plan changes had been made but the City had not been included in receiving new updated plans. I requested another updated set of plans from Pat before I could continue circulating the plans to the Fire dept. for review.
Meeting  12/4/1995
Meeting with Pat McKeegan on Courthouse plans to compare what I had with what he thought I had and to stamp by the architect some plans submitted without the stamp.
Plan Reviewer's Copy of Permit  11/29/1995
Received Certificate of Value  11/27/1995
Waiting for Cert. of Value  11/22/1995
Meeting  7/5/1995
Meeting with Pat McKeegan, Tim hogland & Dan Stuart to finalize acceptable procedures for final submittals of plans, details & time frame per a request from Mayor Coles after his meeting with Mr Balukoff & Mr Mateff, that Tim become involved with thw approval process. Tm Hogland had previously met with Pat mcKeegan on June 1, 1995 and arrived at certain conclusions of which I was notified By letter from Pat. This meeting was being held because of two major concerns that I felt had not been adequately addressed - The full construction of a rated corridor exit system by separating the corridor from the nonrated mezzanine & exercise rooms and the question on direction of door swing within the corridor. Since it had been concluded in the meeting between Tim & Pat that the doors would not be changed do to extensive costs & structural changes that would be involved, it was concluded that an early warning smoke detection alarm system be installed within the corridor system. An enclosure was accomplished of opening within the corridor and plans indicating all approved actions, approvals & method of compliance are to be submitted for review.
Meeting  4/20/1995
Meeting with Pete Mulvihill, Fire dept. plan reviewer and Wes Wooster structural division to check on their progress of reviewing Code Review, deficiency corrections and proposed time frame of completion we had received from Pat McKeegan on March 28, 1995.
Application received  4/19/1995
Plan resubmittals received  3/28/1995
Received plans & code review analysis from Pat McKeegan. Copies given to Pete Mulvihill, Fire dept & Wes Wooster, Structural Inspector for their review and comments as regards outstanding correction notices that have been issued by their Departments.
Plan resubmittals requested  1/19/1995
Was informed by Pat McKeegan, by phone, that he had been retained by Mr Balukoff as the Architect to do a code review of the building as previously requested of Mr. Kohn. He has collected the outstanding correction notices, letters from the fire dept. & building department to the Court House. I reviewed with him my concerns and information to be presented on plans etc. Deadline of Jan 31, 1995 established by Fire & Building Dept. notice to Mr. Balukoff will not be enforced as long as a positive action is ongoing to provide compliance with Building & Fire Dept. notices per Pete milvihill & Wes Wooster.
Meeting  10/20/1994
Meeting with Balukoff, Krohn, Crossland, other Court House employee & D. Stuart on code review information being supplied by Mr. Krohn. The review of the existing building has been minimul, plans are copies of original with hand written notes but no update to reflect as-built, no correction details or proposals and no time frame. Unsatisfactory attempt by the architect to respond to requirements. Owner wants to meet with previous owner to review why some things were not done per plans and who is going to pay for compliance corrections - then they will get back to me.
Plan resubmittals requested  10/20/1994
Expressed inadequacy of information on plans received from Mr. Krohn in response to the 6/15/94 meeting. Mr Krohn to review letter on requested information as part of code review and resubmitt requested information, plans & details.
Plan resubmittals received  8/4/1994
Received plan submittal from Mr. Krohn as requested in 6/15/94 meeting. Plans and notes very inadequate to determine deficiencies found, as-built construction & use of present building, correction procedure to be used and proposed time frame. Plans rejected by letter to Mr. Krohn on 8/11/94.
Plan resubmittals requested  6/15/1994
Mr Krohn to submitt as-built plans of existing building layout and room use with dimensiuons, areas, etc. & to include details for corrective procedures for noted deficiencies found by his code review of building.
Meeting  6/15/1994
Meeting with Kent Krohn, Architect; A.J. Balukoff, New Owner; Brad Crossland, General Manager of Court House, Inc. & Dan Stuart, Plan Reviewer. Lined out questions to be answered buy code review of existing building by the architect. Review to include outstanding correction notices, as-built compared to original plan review, updated plans to show existing conditions & proposals for method of correction of deficiencies and time frame for completion. Meeting is a result of plans submitted for construction of a new pool equipment storage room, new ownership requiring Occupancy certificate, on-site review with Paul Fortin of Fire Dept. and on site visit with Brad Crossland in late April, 1994.
Application received  4/15/1994
Routing - BUILDING11/29/1995  
Routing - BUILDING12/19/1995   PEND