CHANGE STATUS TO (D) | | | 8/16/1996 | | |
|
|
|
|
INSP - Letter of compliance | 4/22/1996 | 4/22/1996 | 4/22/1996 | A | PASS |
Wes Worcester
|
|
|
C/C ISSUED
|
INSP - Letter of compliance | 4/22/1996 | 4/22/1996 | 4/22/1996 | A | PASS |
Wes Worcester
|
|
|
C/C ISSUED
|
INSP - Final | 4/19/1996 | 4/22/1996 | 4/17/1996 | A | PASS |
Wes Worcester
|
|
|
04/22/96 342 -
|
CHANGE STATUS TO (I) | | | 2/22/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 2/20/1996 | 2/20/1996 | 2/20/1996 | P | PART |
Wes Worcester
|
|
|
trusses not braced as per eng but as per Dennis Moody. Letter of Transmittal being sent requesting stamped engineering of "as built" fix
|
Issue & PRINT FEE-DUE permit | | | 2/15/1996 | | |
|
|
|
|
INSP - Energy code compliance | 2/13/1996 | 2/14/1996 | 2/14/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 2/13/1996 | 2/14/1996 | 2/14/1996 | A | FAIL |
Wes Worcester
|
|
|
reinspection fee assessed
|
INSP - Framing/Rough-in | 2/8/1996 | 2/9/1996 | 2/9/1996 | A | FAIL |
Wes Worcester
|
|
|
c/n issued @ ref truss eng, pt lds, pony walls (wet crawl).
|
INSP - Foundation | 1/5/1996 | 1/5/1996 | 1/5/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - poured but setbks ok
|
INSP - Footings | 1/4/1996 | 1/5/1996 | 1/5/1996 | A | PASS |
Wes Worcester
|
|
|
01/04/96 342 -
|
Print Pending Permit.LaserJet4 | | | 1/2/1996 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 1/2/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/2/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 1/2/1996 | | PASS |
|
|
|
|
Plan Received by (DJO) | 12/29/1995 | | 12/29/1995 | | PASS |
Dan Overy
|
|
|
12/29/95 16:48:10 DJO - this action updated by action script from <<>> in Case No. BLD95-2258
|
Unassigned to Plan Reviewer | 12/29/1905 | | 12/29/1995 | | PASS |
|
|
|
12/29/95 16:46:44 DJO - this action updated by action script from <<>> in Case No. BLD95-2258
|
Application received | | | 12/21/1995 | | |
|
|
|
|