INSP - Conference | 7/11/1996 | 7/11/1996 | 7/11/1996 | P | PASS |
|
|
|
gave resubmitted plans to Jim reviewed corridors
|
INSP - Conference | 6/17/1996 | 6/17/1996 | 6/17/1996 | P | PASS |
|
|
|
shear walls ok
|
INSP - Footings | 1/29/1996 | 1/29/1996 | 1/29/1996 | | PASS |
Bob Archibald
|
|
|
SPECIAL INSPECTION BEING PROVIDED, CENTER BASEMENT FOOTING
|
INSP - Conference | 1/22/1996 | 1/22/1996 | 1/22/1996 | | PASS |
Bob Archibald
|
|
|
on footings (inspection), and future corridor construction in basement.
|
(F) Reprint permit | | | 1/22/1996 | | |
|
|
|
|
(F) Reprint permit | | | 1/22/1996 | | |
|
|
|
|
INSP - Conference | 1/5/1996 | 1/5/1996 | 1/5/1996 | | PASS |
Bob Archibald
|
|
|
ON SPECIAL INSPECTION REQUIREMNETS.
|
Issue PAID IN FULL permit | | | 1/3/1996 | | |
|
|
|
|
Plan resubmittals received | | | 1/2/1996 | | |
|
|
|
Received resubmittal sheets S.1, S.2, S.3 and S.4.
|
Inspection Record Card- Bld | | | 1/2/1996 | | |
|
|
|
|
Unassigned to Plan Reviewer | 12/29/1995 | | 1/2/1996 | | PASS |
|
|
|
01/02/96 09:23:34 MYS - this action updated by action script from <<>> in Case No. BLD95-2280
|
Permit taken to Permit Desk | | | 1/2/1996 | | PASS |
|
|
|
|
Application received | | | 12/29/1995 | | |
|
|
|
|
Plan Received by (MYS) | 12/29/1995 | | 1/2/1995 | | PASS |
Marlene Southard
|
|
|
|