INSP - Final | 12/24/1998 | | 12/24/1998 | | PASS |
|
|
|
other agencies made ok ok for prm occd
|
INSP - Temporary occupancy | | | 6/7/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3228 issued 6-7-96 to Studio One.
|
INSP - Temporary occupancy | 5/8/1996 | 5/8/1996 | 5/8/1996 | P | FAIL |
|
|
|
05/08/96 338 - CALL LEE AT ###-#### TO MEET YOU FOR ACCESS..DIX not ready OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Energy code compliance | 5/7/1996 | 5/8/1996 | 5/8/1996 | A | NH |
Jim Sly
|
|
|
energy code not required on commercial 05/07/96 316 - A.M. No access.... left note to call for inspection.
|
(F) Reprint permit | | | 5/8/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 4/2/1996 | 4/2/1996 | 4/2/1996 | P | PASS |
|
|
|
ok to cover with mech pass
|
INSP - Framing/Rough-in | 3/29/1996 | 4/1/1996 | 4/1/1996 | A | FAIL |
|
|
|
need plmg rough, c/n issued, need mech rough, ok to drywall 1 side of the framed walls
|
INSP - Conference | 3/26/1996 | 3/26/1996 | 3/26/1996 | | PASS |
|
|
|
/ / 338 - update wp
|
Issue PAID IN FULL permit | | | 3/25/1996 | | |
|
|
|
|
Plan resubmittals received | 3/22/1996 | | 3/22/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 3/22/1996 | | PASS |
|
|
|
ALL IN ORDER----ISSUE
|
Routing - FIRE | 3/12/1996 | | 3/20/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/12/1996 | | PEND |
|
|
|
files
|
Plan Received by (PRP) | 3/4/1996 | | 3/12/1996 | | PASS |
|
|
|
STARTED REVIEW 03/12/96 10:39:29 PRP - this action updated by action script from <<>> in Case No. BLD96-0545
|
Plan Reviewer's activity | | | 3/12/1996 | | PEND |
|
|
|
received separate plans for this tenant improvment today, reviewed, ran plan-analysis, correction list, fax to arch, mark-up, input to Permit-Plan, forward to Fire.
|
Routing - PUBLIC WORKS | 2/29/1996 | | 3/4/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | 2/23/1996 | | 3/4/1996 | | PASS |
|
|
|
03/04/96 16:52:22 PRP - this action updated by action script from <<>> in Case No. BLD96-0384
|
Plan routing begun/TENANTS | | | 2/28/1996 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Plans taken to Plan Check | | | 2/23/1996 | | |
|
|
|
|
Application received | | | 2/23/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 2/23/1996 | | |
|
|
|
|
Routing - BUILDING | 3/4/1996 | | | | PEND |
|
|
|
|