SUPER- Supervisor's review | 2/9/1999 | 2/9/1999 | 2/9/1999 | | PASS |
|
|
|
Repair of south opening completed.
|
Fee Review-notes | 7/14/1998 | | 7/14/1998 | | |
|
|
|
|
(F) Reprint permit | | | 6/1/1998 | | |
|
|
|
|
INSP - Miscellaneous | 10/15/1997 | 4/15/1998 | 4/15/1998 | A | NR |
|
|
|
04/15/98 338 - stil in progress getting monthly supports from the proper CONSTRUCTION IS NO STARTED, VOID PERMIT AS PER PERRY PAINE.MPS
|
(F) Reprint permit | | | 2/5/1998 | | |
|
|
|
|
INSP - Expired/Cancelled | 12/5/1997 | 12/9/1997 | 12/9/1997 | P | PASS |
|
|
|
12/09/97 338 - here is that inspection. I have voided the permit thanks
|
FEE REVIEW-NOTES | | | 12/5/1997 | | VOID |
|
|
|
not finishing job permit fee is based on ending job value. plan check fee and fire fee is based on org. value. 42.00 admin fee applied. lh
|
VOIDED CHANGE STATUS | | | 12/5/1997 | | |
|
|
|
|
INSP - Miscellaneous | 10/15/1997 | 10/15/1997 | 10/15/1997 | P | PART |
|
|
|
confirmation that construction has stopped..request update 180 days from this date to verify yes or no on the revocation of permit per ubc abandoned work
|
INSP - Miscellaneous | 9/15/1997 | 9/15/1997 | 9/15/1997 | | PASS |
|
|
|
c/n issued to General Contractor stating 106.4.4 expiration of permit due to project shut down work not resumed within 180 days will constitute city athourity to cancell permit.
|
INSP - Masonry | 8/8/1997 | 8/8/1997 | 8/8/1997 | P | PASS |
|
|
|
08/08/97 338 - made ok with sp insp approval
|
INSP - Footings | 7/29/1997 | 7/29/1997 | 7/29/1997 | P | PASS |
|
|
|
07/29/97 338 - MADE OKor footing 2:30 spec. inspector on site FTG -OK FOOTING INTERRIOR
|
INSP - Foundation | 7/28/1997 | 7/29/1997 | 7/28/1997 | A | PASS |
|
|
|
07/29/97 338 - POURING 2:30 SPECIAL INSPECTOR ON SITE made ok with sp in
|
INSP - Masonry | 7/24/1997 | 7/25/1997 | 7/25/1997 | A | CANC |
Tom Arcoraci
|
|
|
pouring stem walls
|
INSP - Footings | 7/24/1997 | 7/24/1997 | 7/24/1997 | P | PART |
Tom Arcoraci
|
|
|
POURING AROUND 2:30 TO 3 SPECIAL INSPECTOR ON SITE MTI
|
INSP - Footings | 7/22/1997 | 7/22/1997 | 7/22/1997 | P | part |
Tom Arcoraci
|
|
|
07/22/97 408 - special inspector on site pouring at 1 o'clock
|
INSP - Footings | 7/17/1997 | 7/17/1997 | 7/17/1997 | P | PASS |
|
|
|
07/17/97 338 - made ok with sp insp ok
|
INSP - Foundation | 7/15/1997 | 7/16/1997 | 7/16/1997 | P | PASS |
|
|
|
07/16/97 333 - pending special insp reports
|
INSP - Foundation | 7/10/1997 | 7/11/1997 | 7/11/1997 | A | PART |
Tom Arcoraci
|
|
|
STEM WALL, HAS A SPECIAL INSPECTOR ON SITE.
|
INSP - Foundation | 7/10/1997 | 7/10/1997 | 7/10/1997 | P | PASS |
|
|
|
07/10/97 338 - PUMPING GROUT made ok with sp insp approval MASN-REBAR OK
|
INSP - Footings | 7/2/1997 | 7/3/1997 | 7/3/1997 | A | PASS |
|
|
|
07/03/97 338 - READY AT 11 THEY HAVE SPECIAL INSPECTOR made ok with sp i
|
INSP - Footings | 6/27/1997 | 6/30/1997 | 6/30/1997 | A | PART |
|
|
|
06/30/97 338 - Dennis Cherry ###-#### c/n issued ok to pour with the sp
|
INSP - Conference | 6/30/1997 | 6/30/1997 | 6/30/1997 | | PASS |
|
|
|
/ / 338 - conference on the inspections to be requested for this proje concrete sp insp or not as to have a correlation of inspection requests special inspections done
|
(F) Reprint permit | | | 6/16/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/13/1997 | | |
|
|
|
|
Telephone call | | | 6/13/1997 | | PASS |
|
|
|
CALLED NEIL NELSON
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/1997 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 6/13/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/13/1997 | | |
|
|
|
|
Print Occupancy Form | | | 6/13/1997 | | |
|
|
|
|
Plan Received by (M_O) | 4/22/1996 | | 6/12/1997 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/12/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/12/1997 | | |
|
|
|
|
Routing - PLANNING | 6/11/1997 | | 6/11/1997 | | PASS |
|
|
|
Approved by: TKW
|
Routing - PUBLIC WORKS | 5/29/1997 | | 6/10/1997 | | PASS |
|
|
|
PACKAGE #2
|
Routing - FIRE | 5/23/1997 | | 6/3/1997 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/20/1997 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/25/1997 | | 5/20/1997 | | PASS |
|
|
|
PACKAGE #3 REVISED PLANS CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD, HINZMAN& JONES FOR ENGINEERING.
|
Telephone call | | | 5/13/1997 | | FAIL |
|
|
|
CALLED ARCHITECT ABOUT ADDITIONAL ITEMS NEEDED FOR RESUBMITTAL AND UPDATE STATUS OF PROJECT. MO
|
Routing - PUBLIC WORKS | 4/3/1997 | | 4/9/1997 | | FAIL |
|
|
|
REVISED PACKAGE #2 REQUIRES DRAINAGE PLAN REVISION. BM 4-9-97 REQUIRES PROOF OF LEGAL LAND DIVISION. BB 4-9-97
|
Routing - FIRE | 3/18/1997 | | 3/18/1997 | | FAIL |
|
|
|
PACKAGE #1 REVISED PLANS
|
Routing - PUBLIC WORKS | 3/5/1997 | | 3/17/1997 | | PASS |
|
|
|
PACKAGE #2 REVISED PLANS REQUIRES DRAINAGE PLAN REVISION AND PROOF OF LEGAL LAND DIVISION
|
Plan resubmittals requested | | | 3/11/1997 | | FAIL |
|
|
|
Corrections on redesign of smith's foods faxed and mailed to architect on 3-11-97. MO
|
Routing - PLANNING | 3/5/1997 | | 3/5/1997 | | FAIL |
|
|
|
PACKAGE #2 REVISED PLANS Design Review modification has not been approved. Reviewed by MS.
|
Routing - ELECTRICAL | 2/27/1997 | | 3/4/1997 | | PASS |
|
|
|
PACKAGE #1 REVISED PLANS
|
Routing Off Site - C.D.H | 2/25/1997 | | 3/4/1997 | | PASS |
|
|
|
PACKAGE #2 REVISED PLANS CONTACTED TERRY SCOLFIELD AT ###-####
|
Plans ACCEPTED BY PLAN CHECK | | | 2/25/1997 | | PASS |
|
|
|
REVISED PLANS ACCEPTED IN A 4 PACKAGE SUBMITTAL
|
Plan routing begun/NEW & ADDTN | | | 2/25/1997 | | PASS |
|
|
|
REVISED 4 PACKAGE SUBMITTAL
|
Routing - MECHANICAL | 2/25/1997 | | 2/25/1997 | | PASS |
|
|
|
PACKAGE #1 REVISED PLANS
|
Routing Off Site - A.C.H.D | 2/25/1997 | | 2/25/1997 | | PASS |
|
|
|
PACKAGE #4 REVISED PLANS CONTACTED TERRY SCOFLIED AT ###-#### TO TAKE PLANS OUT TO ACHD
|
Routing - PLUMBING | 2/25/1997 | | 2/25/1997 | | PASS |
|
|
|
PACKAGE #1 REVISED PLANS
|
Plan Reviewer's activity | | | 7/31/1996 | | PEND |
|
|
|
PROJECT IS ON HOLD FOR REDESIGN PER LETTER FROM ARCHITECT DATED 07-31-96. MO
|
Routing - PLANNING | 7/18/1996 | | 7/26/1996 | | FAIL |
|
|
|
Reviewed by Wayne Gibbs.
|
Routing - PLUMBING | 7/9/1996 | | 7/17/1996 | | PEND |
|
|
|
THIS IS A COMPLETE RESUBMITTAL NOT JUST CORRECTIONS.
|
Routing - BUILDING | 6/10/1996 | | 7/17/1996 | | PEND |
|
|
|
|
Telephone call | | | 7/17/1996 | | |
|
|
|
|
INSP - Miscellaneous | | | 7/8/1996 | | PEND |
|
|
|
The completely new sets of revised plans are be recirculated with one set of the old plans to all Depts. for final review and approval if correct. MO
|
Plan resubmittals received | | | 7/3/1996 | | PEND |
|
|
|
Revised plans received by M. OTTO.
|
Routing Off Site - A.C.H.D | 6/3/1996 | | 6/7/1996 | | FAIL |
|
|
|
ACHD FEES NOT PAID.
|
Routing Off Site - C.D.H | 5/7/1996 | | 6/3/1996 | | PASS |
|
|
|
Called Terry Schofield for transport to CDH. 5/7/96 DAR APPROVED FROM EARLIER PLANS SUBMITTED. APPROVAL DATE 3/25/96 BY BUD FULLERTON.
|
Routing - FIRE | 5/2/1996 | | 5/7/1996 | | FAIL |
|
|
|
|
Meeting | | | 5/1/1996 | | PEND |
|
|
|
Meeting with Architect and Mech. Engineer to go over plan review comments.
|
Plan Reviewer's activity | | | 4/30/1996 | | PEND |
|
|
|
Architect contacted by phone. set-up meeting 5/1 to go over correction list. Corrections mailed and faxed to architect 4/30
|
Unassigned to Plan Reviewer | 3/14/1996 | | 4/24/1996 | | PASS |
|
|
|
04/24/96 16:46:55 M_O - this action updated by action script from <<>> in Case No. BLD96-0510
|
Routing - MECHANICAL | 4/17/1996 | | 4/22/1996 | | PASS |
|
|
|
|
Routing - PLUMBING | 4/15/1996 | | 4/17/1996 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 4/9/1996 | | 4/15/1996 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/25/1996 | | 4/8/1996 | | FAIL |
|
|
|
|
Routing - PLANNING | 3/15/1996 | | 3/22/1996 | | PASS |
|
|
|
X-ref: DR-81-95. Approved by TKW.
|
Plan routing begun/NEW & ADDTN | | | 3/15/1996 | | PASS |
|
|
|
|
Plans taken to Plan Check | | | 3/14/1996 | | |
|
|
|
|
Received Certificate of Value | | | 3/14/1996 | | PASS |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 3/14/1996 | | |
|
|
|
|
Application received | | | 3/8/1996 | | |
|
|
|
|
Routing - BUILDING | 7/26/1996 | | | | PEND |
|
|
|
|