Permit Information
Permit NumberBLD96-00514
StatusFinaled
Name NEW OFFICE/DETAIL SHOP
Site Address 2715 W IDAHO ST
Project NameCAR WASH
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A 4,800 SQ. FT. V-N AUTOMOTIVE DETAIL SHOP WITH MASONRY EXTERIOR WALLS AND WOOD TRUSS ROOF. PERMIT INCLUDES ALL RELATED SITE WORK AND TRASH ENCLOSURE PER APPROVED PLANS AND ATTACHMENTS. OPERATIONS OF BUSINESS TO CONSIST OF BASIC CAR WASH AND DETAIL SERVICES - NO PAINTING OR AUTO PARTS CHANGING OR OTHER VEHICLE MAINTENANCE. PC# 116-96 DR# 112-95.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  6/24/1997 PASS
Perm. Occ. Cert. #6898 issued to Detail Plus.
INSP - Final6/23/19976/23/19976/23/1997APASS
DetailsTom Arcoraci
occ ok
Permanent Occupancy 6/23/19976/23/1997 DONE
Details
INSP - Final6/19/19976/20/19976/20/1997PNR
DetailsTom Arcoraci
automotive detail shop - "Work Groups" need to chk at off
Routing for occupancy6/18/19976/18/19976/18/1997 PASS
Inspected for Final by Art Yingling-meets compliance
INSP - Final11/29/199611/29/199611/29/1996PPART
DetailsGeorge Slane
INSP - Final11/29/199611/29/199611/29/1996PCANC
DetailsWes Worcester
George was going to do
INSP - Temporary occupancy11/29/199611/29/199611/29/1996PPART
DetailsGeorge Slane
G Slane issued
INSP - Temporary occupancy  11/29/1996 PASS
Temp. Occ. Cert. #3320 issued 11-29-96 to Detail Plus.
INSP - Temporary occupancy11/21/199611/25/199611/27/1996 PASS
Sched. insp. for Temp. Occ. (AY - 11:00 a.m.) Will need to bond for landscaping, curbing, approx 50% of asphalt wrk. striping and ADA Sign (Talked to Jeff Hon-have cost estimates in hand.) **Surety Bond (#5870367) for $18,500.00 posted on 11/27/96/Temp Signed
INSP - Final11/25/199611/26/199611/26/1996PNR
DetailsWes Worcester
no one there, no plans, or scope of work, 2711 locked, not done!!
INSP - Final11/26/199611/26/199611/26/1996 PASS
Details
/ / 405 - all items complete
INSP - Final11/20/199611/20/199611/20/1996 FAIL
Details
/ / 405 - C/N ISSUED GAS METER PROT NEEDED, RAIN CAPS ON OIL SEP VENT, HARDWARE WRONG (THUMBTURNS)
INSP - Framing/Rough-in10/15/199610/16/199610/16/1996PPASS
DetailsWes Worcester
10/16/96 342 - 1:30 PM ck on mech r/i otherwise ok
INSP - Masonry9/20/19969/23/19969/23/1996APASS
Details
09/23/96 333 - EARLY MON.A.M. - 8:30 APPT. MASN-REBAR OK
INSP - Masonry9/19/19969/20/19969/20/1996APASS
DetailsBob Archibald
8:30 A.M. North and south walls to approx. 17'.
INSP - Wall cover9/17/19969/18/19969/18/1996PPART
DetailsWes Worcester
CMU- BLOCK WALLS/ INSPECTOR TO BE THERE BEFORE 2:00 PER BOB ARCHIBALD/ PLANS PER 342 CORRECTION NOTICE ON BOB'S DESK North and south walls to 13'-6" only. Engineering received from prior cn.
INSP - Masonry9/12/19969/13/19969/13/1996AFAIL
DetailsWes Worcester
not ready yesterday....missing bar at corners...left with them placing dbl bar and tying in place....today they missed 4 corners. asked general to verify plan w/designer and clarify for subs. 1/A-5 repeated three times on plan w/3 different details...
INSP - Masonry9/11/19969/11/19969/11/1996PFAIL
DetailsWes Worcester
SCHEDULED TO POUR AT 2:00 needed to place another upright at openings and tie off bar JEFF HON-PAGER-###-####
INSP - Masonry9/11/19969/11/19969/11/1996PPASS
DetailsWes Worcester
first lift ok. c/n removed
INSP - Foundation8/5/19968/5/19968/5/1996PPASS
DetailsWes Worcester
late p.m.
INSP - Footings8/1/19968/2/19968/2/1996APASS
DetailsWes Worcester
8:30 A.M.
INSP - Footings8/1/19968/1/19968/1/1996PCANC
Details
08/01/96 333 - LATE PM OR EARLY A.M. FRIDAY given to wes
Routing Off Site - A.C.H.D7/26/1996 7/27/1996 PASS
Print Pending Permit.LaserJet4  7/26/1996 PASS
Issue PAID IN FULL permit  7/26/1996
ISSUE OCCUPANCY FORM  7/26/1996
Permit taken to Permit Desk  7/26/1996 PASS
plans given to DAR for fowarding to Front Desk
Received Certificate of Value  7/26/1996 PASS
final certificate of value for permit.
Inspection Record Card- Bld  7/26/1996
Plan Reviewer's Copy of Permit  7/12/1996 PASS
Waiting for Cert. of Value  6/14/1996 PASS
NEED FINAL CERTIFICATE OF VALUE TO COMPLETE PERMIT ACHD FEES HAVE NOT BEEN PAID TO DATE: MO
Plan Received by (M_O)5/9/1996 6/14/1996 PASS
Routing - PUBLIC WORKS6/10/1996 6/12/1996 PASS
Plan resubmittals received  6/3/1996 PEND
Routing - PUBLIC WORKS5/31/1996 6/3/1996 FAIL
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY.
Routing - PLANNING5/30/1996 5/30/1996 PASS
X-ref: DR-112-96. Approved by MS.
Meeting  5/29/1996 PEND
MET WITH AMBER VAN OCKER OF LEATHAM AND KROHN WENT OVER ADDITIONAL CORRECTIONS ON RESUBMITTAL.
INSP - Miscellaneous  5/28/1996 PEND
RECEIVED REVISED PLANS AND RESPONSE TO CORRECTIONS FROM LEATHAM - KROHN
Routing - FIRE5/13/1996 5/15/1996 PASS
Plan Reviewer's activity  5/13/1996 PEND
correction list faxed and mailed to architect 5-13-96.
Unassigned to Plan Reviewer3/8/1996 5/9/1996 PEND
05/09/96 13:13:39 M_O - this action updated by action script from <<>> in Case No. BLD96-0514
Routing Off Site - A.C.H.D3/29/1996 5/8/1996 FAIL
Called Scott Van Oaken ###-#### to take plans to ACHD. ACHD fees not paid. 5/8/96 DAR
Routing - MECHANICAL3/28/1996 3/29/1996 PASS
Routing - ELECTRICAL3/28/1996 3/28/1996 PASS
NO PLAN REVIEW.WILL FIELD VERIFY. 3/28/96 DAR
Routing - PLUMBING3/27/1996 3/28/1996 PASS
Routing - PUBLIC WORKS3/20/1996 3/27/1996 FAIL
Routing - PLANNING3/12/1996 3/20/1996 FAIL
Plans not revised to comply with conditions of approval. Review by MS.
Plan routing begun/NEW & ADDTN  3/12/1996 PASS
Received Certificate of Value  3/8/1996 PASS
GAY'S RECEIPT FOR PARTIAL PAY  3/8/1996
Application received  3/8/1996
Routing - BUILDING6/12/1996   PEND
Routing - BUILDING6/4/1996   PEND
Routing - BUILDING5/9/1996   PEND
PLANS GIVEN TO MIKE OTTO FOR REVIEW. 5/9/96 DAR
Routing - BUILDING5/15/1996   PEND