INSP - Final | 10/15/1996 | 10/16/1996 | 10/16/1996 | A | PASS |
Carl Dependahl
|
|
|
10/15/96 340 - KEY TO RIGHT OF DOOR cn ok
|
INSP - Final | 10/11/1996 | 10/11/1996 | 10/11/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - SENT TO 301 IN ERROR, REQUESTED FOR AM C/N, VAPOR BARRIER, SEAL HVAC BOOTS
|
INSP - Final | 10/10/1996 | 10/11/1996 | 10/11/1996 | A | NR |
Jim Storey
|
|
|
10/10/96 301 - TRANSPHERED TO CARL D.
|
INSP - Energy code compliance | 8/6/1996 | 8/6/1996 | 8/6/1996 | P | PASS |
Jim Storey
|
|
|
08/06/96 301 - INSL-OK INSULATION-ENERGY CODE FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 8/2/1996 | 8/5/1996 | 8/5/1996 | A | PART |
Jim Storey
|
|
|
08/02/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 8/1/1996 | 8/1/1996 | 8/1/1996 | P | NR |
Jim Storey
|
|
|
08/01/96 301 - OTH-OTHER AGENCIES NOT APPROVED ELE NO STICKER NO STOP.
|
INSP - Framing/Rough-in | 7/31/1996 | 7/31/1996 | 8/1/1996 | P | NR |
Jim Storey
|
|
|
07/31/96 301 - OTH-OTHER AGENCIES NOT APPROVED ELE NO STICKER NO STOP.
|
INSP - Framing/Rough-in | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | FAIL |
Carl Dependahl
|
|
|
07/23/96 340 - FRAME REINSPECT need elec r/i, left c/n
|
INSP - Framing/Rough-in | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | CANC |
Carl Dependahl
|
|
|
07/23/96 340 - sent twice
|
INSP - Footings | 6/18/1996 | 6/18/1996 | 6/18/1996 | P | NR |
Carl Dependahl
|
|
|
06/18/96 340 - nr, gave to 338
|
INSP - Footings | 6/18/1996 | 6/18/1996 | 6/18/1996 | | PASS |
|
|
|
/ / 338 - FDN -OK FOUNDATION
|
INSP - Footings | 6/18/1996 | 6/18/1996 | 6/18/1996 | | PASS |
|
|
|
/ / 338 - FTG -OK FOOTING poured fore insp setrbacks appear ok
|
INSP - Footings | 6/18/1996 | 6/18/1996 | 6/18/1996 | | PASS |
|
|
|
/ / 338 - FTG -OK FOOTING poured fore insp setrbacks appear ok
|
INSP - Footings | 6/18/1996 | 6/18/1996 | 6/18/1996 | | PASS |
|
|
|
/ / 338 - FDN -OK FOUNDATION
|
Issue PAID IN FULL permit | | | 6/11/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/18/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/15/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | 3/7/1996 | | 3/15/1996 | | PASS |
|
|
|
03/15/96 15:28:16 DJO - this action updated by action script from <<>> in Case No. BLD96-0529
|
Permit taken to Permit Desk | | | 3/15/1996 | | PASS |
|
|
|
|
Plan Received by (DJO) | 3/15/1996 | | 3/15/1996 | | PASS |
Dan Overy
|
|
|
03/15/96 15:55:23 DJO - this action updated by action script from <<>> in Case No. BLD96-0529
|
Routing - PLANNING | 3/11/1996 | | 3/14/1996 | | PASS |
|
|
|
Approved by GRH.
|
Plans taken to Plan Check | | | 3/14/1996 | | |
|
|
|
|
Application received | | | 3/11/1996 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/7/1996 | | 3/8/1996 | | PASS |
|
|
|
|
Routing - FRONT DESK | 3/14/1996 | | | | PEND |
|
|
|
|