CHANGE STATUS TO (D) | | | 8/16/1996 | | |
|
|
|
|
INSP - Final | 7/3/1996 | 7/3/1996 | 7/2/1996 | P | PASS |
|
|
|
07/03/96 338 - FNL -OK FINAL LCI-LETTER OF COMPLIANCE ISSUED # 10850
|
INSP - Letter of compliance | 7/2/1996 | 7/2/1996 | 7/2/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED 10850
|
INSP - Letter of compliance | 7/2/1996 | 7/2/1996 | 7/2/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED 10850
|
INSP - Framing/Rough-in | 5/14/1996 | 5/14/1996 | 5/14/1996 | P | PART |
Carl Dependahl
|
|
|
05/14/96 340 - PART, INSTALLED DBL MICRO LAM AT PT. LOAD AT ENTRY
|
INSP - Framing/Rough-in | 5/9/1996 | 5/10/1996 | 5/10/1996 | A | PART |
Carl Dependahl
|
|
|
05/09/96 340 - provided partial eng'g, need to dbl m.l. beam at entry, s at 16' gar opening brg floor & roof load. Adding vent fan & sump pump at as ground water is present
|
INSP - Energy code compliance | 5/6/1996 | 5/7/1996 | 5/7/1996 | A | PART |
Carl Dependahl
|
|
|
05/06/96 340 - 2nd C/N: NEED ENG'G FOR OFFSET BRG CONDITION AT GAR LID/2 CRAWL SPACE, MAY NEED PUMP/MECH VENT...HIGH WATER TABLE? OK TO COVER AS KEEP C/N
|
INSP - Framing/Rough-in | 5/7/1996 | 5/7/1996 | 5/7/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 - 2ND C/N...SEE NOTE W/ ENERGY INSP, SAME DATE. KEEP C/N, OK T
|
INSP - Conference | 5/3/1996 | 5/3/1996 | 5/3/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - DISCUSSED C/N W/ SUPT....NEED ENG'G AS REQUESTED PER C/N. KE
|
INSP - Conference | 5/2/1996 | 5/2/1996 | 5/2/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/Rough-in | 5/1/1996 | 5/2/1996 | 5/2/1996 | P | NR |
Carl Dependahl
|
|
|
05/02/96 340 - PM THURS. nr for reframe
|
INSP - Framing/Rough-in | 4/30/1996 | 5/1/1996 | 5/2/1996 | P | CANC |
Jim Sly
|
|
|
04/30/96 316 - WED PM Sent to me by mistake.
|
INSP - Conference | 4/25/1996 | 4/26/1996 | 4/26/1996 | A | PASS |
Carl Dependahl
|
|
|
04/25/96 340 - STAIRS, MAY NEED ENG'G FOR OFFSET BRG AT GAR, 2ND FL
|
INSP - Foundation | 4/2/1996 | 4/2/1996 | 4/2/1996 | P | PART |
Carl Dependahl
|
|
|
04/02/96 340 - HOUSE FLIPPED ON LOT
|
INSP - Footings | 3/29/1996 | 4/1/1996 | 4/1/1996 | A | PART |
Carl Dependahl
|
|
|
03/29/96 340 - part.no plot plan, looks ok
|
Plan resubmittals received | | | 3/27/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/27/1996 | | PASS |
|
|
|
|
Permit taken to Permit Desk | | | 3/27/1996 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/27/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/27/1996 | | |
|
|
|
|
Plan Received by (DJO) | 3/19/1996 | | 3/27/1996 | | PEND |
Dan Overy
|
|
|
|
Unassigned to Plan Reviewer | 3/8/1996 | | 3/27/1996 | | PASS |
|
|
|
03/27/96 09:13:36 DJO - this action updated by action script from <<>> in Case No. BLD96-0536
|
Plan resubmittals requested | | | 3/19/1996 | | PEND |
|
|
|
|
Plans taken to Plan Check | | | 3/12/1996 | | PASS |
|
|
|
|
Routing - PLANNING | 3/11/1996 | | 3/12/1996 | | PASS |
|
|
|
Approved by GRH.
|
Application received | | | 3/11/1996 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/8/1996 | | 3/11/1996 | | PASS |
|
|
|
|
Routing - FRONT DESK | 3/12/1996 | | | | PEND |
|
|
|
|