Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD96-00537
StatusFinaled
Name FEDERAL WAY BUSINESS CENTER
Site Address 2513 S FEDERAL WAY
Project NameFEDERAL WAY BUSINESS
Customer Number 
ePlanReviewNo
Description
RETAIL AND WAREHOUSE BUSINESS * (VANILA FINISH ONLY) TO CONSTRUCT A NEW SINGLE STORY, APPROXIMATELY 8774 SQ.FT. MULTI TENANT, RETAIL AND WAREHOUSE BUILDING. THE CONSTRUCTION TO BE CONCRETE MASONRY WALLS TYPE V-NONRATED STRUCTURE. A ONE-HOUR OCCUPANCY SEPARATION IS BEING CONSTRUCTED AT GRID LINE #7. THE ENTIRE CEILING IS REQUIRED TO BE ONE-HOUR PER SECTION 709.4.1,EXC.#5 AND 302.2. THIS PERMIT DOES NOT ALLOW A CERTIFICATE OF OCCUPANCY TO BE ISSUED. SEPARATE PERMITS WILL BE REQUIRED TO FINISH EACH TENANT SPACE AND TO ISSUE A CERTIFICATE OF OCCUPANCY. MJP (PC#119-96) DR#120-95
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (D)  3/20/1997 PASS
CHANGE STATUS TO (D)  3/14/1997 PASS
INSP - Letter of compliance3/10/19973/10/19973/10/1997 PASS
DetailsJim Storey
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 13735#
INSP - Final3/10/19973/10/19973/10/1997PPASS
DetailsJim Storey
03/10/97 301 - FNL -OK FINAL
INSP - Letter of compliance3/10/19973/10/19973/10/1997 PASS
DetailsJim Storey
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 13735#
INSP - Wall cover11/18/199611/18/199611/18/1996PPASS
DetailsJim Storey
11/18/96 301 - 1 HR SHAFT ASSEMBLY FRAM-OK FRAMING FRWL-RATED WALL CONST. OK
INSP - Final11/7/199611/7/199611/7/1996 PASS
Details
SHELL AND CORE
INSP - Occupancy Sign-off11/14/199611/6/199611/6/1996 F
Insp. by Scott Brown - Complies w/ Cond. of DR-120-95/MOD Signed Final Occ. 11/06/96
INSP - Final11/6/199611/6/199611/6/1996PPART
DetailsJim Storey
11/06/96 301 - T/O TCO -TEMP C OF O ISSUED C/N FOR RATED ACESS FRAMES TO BE ATCHED PER LIST PUBLICWORKS INSP.
INSP - Final11/4/199611/4/199611/4/1996 NR
DetailsJim Storey
11/01/96 301 - LATE PM CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Final11/1/199611/1/199611/4/1996PNR
DetailsJim Storey
11/04/96 301 - LATE PM UGA -UNABLE TO GAIN ACCESS-LEFT NOTC
INSP - Framing/Rough-in10/9/199610/10/199610/10/1996PFAIL
DetailsJim Storey
10/10/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in10/8/199610/9/199610/9/1996PCANC
DetailsJim Storey
10/09/96 301 -
INSP - Ceiling grid9/13/19969/13/19969/12/1996PPASS
Details
09/13/96 338 - late p.m. made ok 1st 1/2 of shafts ok
INSP - Framing/Rough-in9/6/19969/9/19969/9/1996PFAIL
DetailsJim Storey
09/09/96 301 - LATE P.M. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Flatwork8/8/19968/8/19968/8/1996PPASS
DetailsJim Sly
08/08/96 316 - SLAB FLR OK. ì
INSP - Foundation7/26/19967/26/19967/26/1996 PASS
Details
/ / 333 - FDN -OK FOUNDATION
INSP - Foundation7/26/19967/26/19967/26/1996PPART
DetailsJim Storey
07/26/96 301 - trans to kim m.
INSP - Footings7/24/19967/25/19967/25/1996APASS
DetailsWes Worcester
9 A.M. THURSDAY
INSP - Footings7/25/19967/25/19967/25/1996ANR
DetailsWes Worcester
INSP - Foundation7/25/19967/25/19967/25/1996APASS
DetailsWes Worcester
INSP - Conference7/25/19967/25/19967/25/1996APASS
DetailsWes Worcester
getting cover and placing second mat per top and bottom notation on plans.. Shop is upset w/shop drawings and insp request for double mat as per plan
INSP - Foundation7/24/19967/24/19967/24/1996ANR
DetailsWes Worcester
still trying to get cover requirements
INSP - Footings7/24/19967/24/19967/24/1996AFAIL
DetailsWes Worcester
calls for dbl mat
INSP - Footings7/24/19967/24/19967/24/1996ANR
DetailsWes Worcester
still trying to get cover
INSP - Footings7/23/19967/24/19967/24/1996ANR
DetailsJim Storey
07/24/96 301 - transphered to wes w.
INSP - Conference7/24/19967/24/19967/24/1996APART
DetailsWes Worcester
dbl mat requirements
INSP - Foundation7/19/19967/19/19967/19/1996PPASS
DetailsJim Sly
07/19/96 316 - stem wall - spec.inspector will be there at 12:30. OK T Jim Sly.
INSP - Footings7/17/19967/18/19967/18/1996APASS
DetailsJim Storey
07/18/96 301 - J SLY PERFORMED INSP. BEFORE I ARIVED
INSP - Footings7/18/19967/18/19967/18/1996 PART
DetailsJim Sly
/ / 316 - Inspection of Footings ...S. and W. sides (F1-F2). OK
ISSUE OCCUPANCY FORM  7/11/1996
Inspection Record Card- Bld  7/11/1996
Issue PAID IN FULL permit  7/11/1996
Issue PAID IN FULL permit  7/11/1996
Permit taken to Permit Desk  7/10/1996 PASS
Inspection Record Card- Bld  7/10/1996
Plan Reviewer's activity  7/10/1996 PASS
received verification of fire flow (2500 gpm) for this location.
Plan Received by (M_P)5/6/1996 7/10/1996 PASS
DetailsMike Phillips
PLANS GIVEN TO ME 4/30 FINISHED OTHER WORK PRIOR TO STARTING PLAN REVIEW. 07/10/96 15:22:33 DAR - this action updated by action script from <<>> in Case No. BLD96-0537
Print Pending Permit.LaserJet4  7/10/1996 PASS
Routing - PUBLIC WORKS7/3/1996 7/9/1996 PEND
Routing Off Site - A.C.H.D7/2/1996 7/3/1996 PEND
FEES MUST BE PAID PRIOR TO PERMIT ISSUANCE fees not paid as of 07-03-96
Routing - PUBLIC WORKS6/26/1996 7/1/1996 FAIL
REQUIRES DRAINAGE PLAN. REQUIRES STREET LIGHT PLAN . NEEDS OK FROM ACHD.
Plan Reviewer's activity  6/26/1996 PEND
WAITING FOR PUBLIC WORKS AND ACHD APPROVAL. NEED TO RECEIVE CERTIFICATE OF VALUE.
Waiting for Cert. of Value  6/26/1996 PEND
NEED TO RECEIVE CERTIFICATE OF VALUE.
Routing Off Site - A.C.H.D6/6/1996 6/12/1996 FAIL
CONTACTED RICHARD FOR PICK-UP TO ACHD. DAR
90 day tracking............. 3/11/19966/9/1996 PASS
Plan Reviewer's activity  6/6/1996 FAIL
second correction notice sent
Routing - FIRE5/9/1996 5/14/1996 HOLD
ON HOLD UNTIL FIRE HYDRANT INFORMATION IS PROVIDED.
Plan Reviewer's Copy of Permit  5/9/1996 FAIL
Plan Reviewer's activity  5/9/1996 FAIL
Unassigned to Plan Reviewer3/11/1996 5/9/1996 PASS
05/09/96 11:36:54 M_P - this action updated by action script from <<>> in Case No. BLD96-0537
Routing Off Site - A.C.H.D4/4/1996 4/30/1996 FAIL
CONTACTED GREGG BUSH FOR ACHD PICKUP AT ###-####
Routing - PUBLIC WORKS3/28/1996 4/3/1996 FAIL
Routing - MECHANICAL3/22/1996 3/28/1996 PASS
Routing - ELECTRICAL3/22/1996 3/22/1996 PASS
Not reviewed. Will field verify. DAR 3/22/96.
Routing - PLUMBING3/15/1996 3/21/1996 PASS
Routing - PLANNING3/12/1996 3/14/1996 PASS
Approved by MS. X-ref: DR-120-95
Plan routing begun/NEW & ADDTN  3/12/1996 PASS
GAY'S RECEIPT FOR PARTIAL PAY  3/11/1996
Received Certificate of Value  3/11/1996 PASS
(F) Reprint permit  3/11/1996
Application received  3/11/1996
Plans taken to Plan Check  3/11/1996 PASS
Routing - BUILDING7/3/1996   PEND
Routing - BUILDING4/30/1996   PEND
Routing - BUILDING6/12/1996   PEND