INSP - Permanent occupancy | | | 8/13/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6524 issued 8-13-96 to Sweet Endings in the Parkcenter Mall.
|
Permanent Occupancy | | 7/22/1996 | 7/22/1996 | | DONE |
|
|
|
|
INSP - Final | 7/22/1996 | 7/22/1996 | 7/22/1996 | P | PASS |
Jim Storey
|
|
|
07/22/96 301 - FNL -OK FINAL perm occ.
|
Inspection Record Card- Bld | | | 7/9/1996 | | |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 7/9/1996 | | |
|
|
|
|
(F) Reprint permit | | | 7/9/1996 | | |
|
|
|
|
INSP - Final | 7/8/1996 | 7/8/1996 | 7/8/1996 | P | FAIL |
Jim Storey
|
|
|
07/08/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED B VENT TO CLOSE TO CONBUSTABL
|
90 day tracking............. | | 3/12/1996 | 6/10/1996 | | PASS |
|
|
|
|
INSP - Temporary occupancy | | | 5/28/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3219 issued 5-28-96 to Sweet Endings Deli in the Parkcenter Mall.
|
INSP - Final | 5/24/1996 | 5/24/1996 | 5/24/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - TCO -TEMP C OF O ISSUED OTH-OTHER AGENCIES NOT APPROVED for p.occ
|
INSP - Final | 5/24/1996 | 5/24/1996 | 5/24/1996 | P | FAIL |
Jim Storey
|
|
|
05/24/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OTH-OTHER AGENCIES NOT APPROVED plmb.
|
INSP - Framing/Rough-in | 5/10/1996 | 5/13/1996 | 5/13/1996 | A | PART |
Jim Storey
|
|
|
05/10/96 301 - FRAM-OK FRAMING STORAGE AN OFFICE ONLY.
|
Issue PAID IN FULL permit | | | 4/30/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/29/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 4/29/1996 | | PASS |
|
|
|
|
Plan Received by (CJW) | 4/9/1996 | | 4/29/1996 | | PASS |
Carl Westfall
|
|
|
04/29/96 11:52:31 CJW - this action updated by action script from <<>> in Case No. BLD96-0548
|
Routing - MECHANICAL | 4/25/1996 | | 4/26/1996 | | PASS |
|
|
|
|
Routing - PLUMBING | 4/22/1996 | | 4/25/1996 | | PASS |
|
|
|
|
Routing - BUILDING | 4/11/1996 | | 4/22/1996 | | PASS |
|
|
|
Approved after review of resubmittal
|
Plan resubmittals received | 4/22/1996 | | 4/17/1996 | | PASS |
|
|
|
Resubmittals approved
|
Plan Reviewer's Copy of Permit | | | 4/11/1996 | | |
|
|
|
|
Routing - FIRE | 4/11/1996 | | 4/11/1996 | | PASS |
|
|
|
|
Routing - BUILDING | 4/9/1996 | | 4/11/1996 | | FAIL |
|
|
|
Three (3) items require a response.
|
Plan resubmittals requested | 4/11/1996 | | 4/11/1996 | | |
|
|
|
Three (3) items require a response. A letter was sent to the Architect.
|
Unassigned to Plan Reviewer | 3/12/1996 | | 4/11/1996 | | PASS |
|
|
|
04/11/96 10:30:19 CJW - this action updated by action script from <<>> in Case No. BLD96-0548
|
Routing - PLUMBING | 3/28/1996 | | 4/1/1996 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 3/22/1996 | | 3/28/1996 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 3/14/1996 | | 3/22/1996 | | PASS |
|
|
|
|
Plan resubmittals received | | | 3/14/1996 | | |
|
|
|
Received the key plan and started routing.
|
Plan routing begun/TENANTS | | | 3/14/1996 | | |
|
|
|
Route to Central District Health, Public Works, Plumbing, Mechanical then back to Plan Check. After Plan Check route to Fire Department.
|
Plan resubmittals requested | | | 3/12/1996 | | PEND |
|
|
|
Plans incomplete. Requested a key plan to show location of tenant space within the building.
|
Plans taken to Plan Check | | | 3/12/1996 | | PASS |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 3/12/1996 | | |
|
|
|
|
Application received | | | 3/12/1996 | | |
|
|
|
|
Routing - BUILDING | 4/26/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 4/11/1996 | | | | PEND |
|
|
|
|
Routing - MECHANICAL | 4/1/1996 | | | | FAIL |
|
|
|
Lee Rice was talking to the plumber and mechanical contractor, therefore he gave him some infor on requirements for mechanical.
|