Permanent Occupancy | | 5/29/1996 | 5/29/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 5/29/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6418 issued 5-29-96 to the Stinker Station.
|
INSP - Final | 5/24/1996 | 5/24/1996 | 5/24/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL for perm. occ. card on file at cathys desk ok to sign off.
|
INSP - Final | 5/20/1996 | 5/21/1996 | 5/21/1996 | P | PASS |
Jim Storey
|
|
|
05/21/96 301 - Between 3:00 - 4:00 p.m. TCO -TEMP C OF O ISSUED occ load sign, ada protection, ref lines support
|
INSP - Framing/Rough-in | 5/2/1996 | 5/2/1996 | 5/2/1996 | P | PASS |
Jim Storey
|
|
|
05/02/96 301 - EARLY PM FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 4/26/1996 | 4/26/1996 | 4/26/1996 | P | NR |
Jim Storey
|
|
|
04/26/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED pending ele. reinsp for plumb relocate drain line to meet ada 60 in radius.
|
Permit taken to Permit Desk | | | 4/22/1996 | | PASS |
|
|
|
issue
|
Plan Reviewer's activity | | | 4/22/1996 | | PASS |
|
|
|
assembled RESUBMITTAL LETTER into plan, issue
|
Inspection Record Card- Bld | | | 4/22/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/22/1996 | | |
|
|
|
|
Plan Received by (PRP) | 4/15/1996 | | 4/22/1996 | | PASS |
|
|
|
RECEIVED TWO SETS OF PLANS. 04/22/96 11:19:43 PRP - this action updated by action script from <<>> in Case No. BLD96-0573
|
Routing - BUILDING | 4/17/1996 | | 4/17/1996 | | PEND |
|
|
|
forward to fire after plan check
|
Routing - FIRE | 4/17/1996 | | 4/17/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/16/1996 | | PEND |
|
|
|
PLAN REVIEW, MARK-UP, PLAN ANALYSIS WITH CORRECTIONS, FAX TO ARCH, FORWARD TO FIRE.
|
Print Pending Permit.LaserJet4 | | | 4/16/1996 | | PEND |
|
|
|
FILE
|
Plan resubmittals requested | 4/16/1996 | | 4/16/1996 | | |
|
|
|
|
Telephone call | | | 4/16/1996 | | PEND |
|
|
|
SPOKE TO MARK KINGHORN CONCERNING ROOF STRUCTURE EXISTING. HE ASSURED ME THE ROOF SYSTEM IS STEEL TRUSS SUPPORTED EXTERIOR WALLS ONLY, FULL SPAN DESIGN. WILL PROVIDE STATEMENT OF CONCURANCE FOR FILE. ALSO WILL SIGNIFY LOCATIONS OF EXIT SIGNS AND EXISTING DOOR HARDWARE.
|
Unassigned to Plan Reviewer | 3/14/1996 | | 4/15/1996 | | PASS |
|
|
|
04/15/96 16:13:19 PRP - this action updated by action script from <<>> in Case No. BLD96-0573
|
Routing - FIRE | 4/2/1996 | | 4/4/1996 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 3/28/1996 | | 4/4/1996 | | PEND |
|
|
|
JACK DAVIS PICKUPED FOR ACHD
|
Plan resubmittals received | | | 3/28/1996 | | PASS |
|
|
|
Fax received of copy of original letter to follow reguarding the correction list responses.
|
Routing Off Site - C.D.H | 3/18/1996 | | 3/28/1996 | | FAIL |
|
|
|
|
Plan routing begun/TENANTS | | | 3/15/1996 | | |
|
|
|
Route to Central District Health and Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 3/14/1996 | | |
|
|
|
|
Plans taken to Plan Check | | | 3/14/1996 | | |
|
|
|
|
Application received | | | 3/14/1996 | | |
|
|
|
|
Routing - BUILDING | 4/4/1996 | | | | PEND |
|
|
|
|