(F) Reprint permit | | | 2/1/2008 | | |
|
|
|
|
CHANGE STATUS TO (D) | | | 8/16/1996 | | |
|
|
|
|
INSP - Letter of compliance | 7/10/1996 | 7/10/1996 | 7/10/1996 | P | PASS |
|
|
|
LETTER #10763
|
INSP - Letter of compliance | 7/10/1996 | 7/10/1996 | 7/10/1996 | P | PASS |
|
|
|
LETTER #10763
|
INSP - Final | 7/8/1996 | 7/9/1996 | 7/9/1996 | P | PASS |
|
|
|
07/09/96 333 - TUES.PM. FNL -OK FINAL
|
INSP - Final | 7/3/1996 | 7/5/1996 | 7/5/1996 | A | CANC |
Wes Worcester
|
|
|
given to J Storey #301
|
INSP - Final | 7/5/1996 | 7/5/1996 | 7/5/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Energy code compliance | 5/22/1996 | 5/23/1996 | 5/23/1996 | P | PASS |
|
|
|
05/23/96 400 - THURS. P.M.
|
INSP - Framing/Rough-in | 5/21/1996 | 5/22/1996 | 5/22/1996 | A | PASS |
|
|
|
05/21/96 400 -
|
INSP - Footings | 4/4/1996 | 4/4/1996 | 4/4/1996 | P | PASS |
|
|
|
checked set backs-ok
|
Issue PAID IN FULL permit | | | 3/26/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/22/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | 3/13/1996 | | 3/22/1996 | | PASS |
|
|
|
03/22/96 14:03:21 DJO - this action updated by action script from <<>> in Case No. BLD96-0583
|
Plan Received by (DJO) | 3/22/1996 | | 3/22/1996 | | PASS |
Dan Overy
|
|
|
03/22/96 14:10:57 DJO - this action updated by action script from <<>> in Case No. BLD96-0583
|
Permit taken to Permit Desk | | | 3/22/1996 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/1996 | | |
|
|
|
|
Routing - PLANNING | 3/15/1996 | | 3/19/1996 | | PASS |
|
|
|
Approved by MGH.
|
Plans taken to Plan Check | | | 3/19/1996 | | PASS |
|
|
|
|
Application received | | | 3/15/1996 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/13/1996 | | 3/15/1996 | | PASS |
|
|
|
|
Routing - FRONT DESK | 3/19/1996 | | | | PEND |
|
|
|
|