Permanent Occupancy | | 7/17/1997 | 7/17/1997 | | DONE |
|
|
|
|
INSP - Final | 7/17/1997 | 7/17/1997 | 7/17/1997 | P | PASS |
Jim Storey
|
|
|
final occ ok'd
|
Permanent occupancy | | | 7/17/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6918 issued 7-17-97 to Papa Murphy's Pizza.
|
INSP-Final Inspection | 7/15/1997 | 7/16/1997 | 7/16/1997 | A | PASS |
|
|
|
|
INSP - Final | 7/15/1997 | 7/15/1997 | 7/15/1997 | P | PART |
Jim Storey
|
|
|
07/15/97 301 - FNL -OK FINAL pending fire dept. signoff.
|
Temporary occupancy | | | 5/5/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3401 issued 5-5-97 to Papa Murphy's Pizza.
|
INSP - Final | 5/1/1997 | 5/2/1997 | 5/2/1997 | A | PART |
Jim Storey
|
|
|
05/02/97 301 - TCO -TEMP C OF O ISSUED fire and bldg.struc. address visablity and resub .
|
INSP - Final | 4/30/1997 | 5/1/1997 | 5/1/1997 | A | NR |
Jim Storey
|
|
|
05/01/97 301 - LATE A.M. FIRE GOING OUT EARLY A.M. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 5/1/1997 | 5/1/1997 | 5/1/1997 | P | PART |
|
|
|
temp pending complete basement and address
|
INSP-Final Inspection | 4/30/1997 | 5/1/1997 | 5/1/1997 | A | FAIL |
|
|
|
EARLY A.M. STRUCTURAL GOING OUT LATE A.M. BASEMENT SEP AND PARTITIONS NOT PROVIDED PER PLANS BUT ACCESS FOR STORAGE WAS. STORAGE AND SHELVING PRESENT
|
INSP - Final | 4/28/1997 | 4/29/1997 | 4/29/1997 | P | FAIL |
Jim Storey
|
|
|
04/29/97 301 - FINAL FOR C/O CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OTH-OTHER AGENCIES NOT APPROVED fire and health dept.
|
INSP - Framing/Rough-in | 4/2/1997 | 4/3/1997 | 4/2/1997 | A | |
Jim Storey
|
|
|
|
INSP - Conference | 3/25/1997 | 3/25/1997 | 3/25/1997 | P | NH |
Jim Storey
|
|
|
03/25/97 301 - HE WILL CALL YOU...I THINK...
|
Print Occupancy Form | | | 3/25/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/25/1997 | | |
|
|
|
|
Print Occupancy Form | | | 3/24/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/24/1997 | | |
|
|
|
|
INSP - Framing/Rough-in | 1/24/1997 | 1/27/1997 | 1/27/1997 | A | PART |
Jim Storey
|
|
|
01/27/97 301 - FRAMING ON STAIR SOUTH OF SPACE ONLY OK
|
Issue PAID IN FULL permit | | | 8/29/1996 | | |
|
|
|
|
Telephone call | | | 8/13/1996 | | |
|
|
|
TALKED TO BILL WITH M & M SALES, HE SAID THEY WOULD BE DOWN TO PICK THE PLANS UP THIS WEEK..
|
90 day tracking............. | | 3/22/1996 | 6/20/1996 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/7/1996 | | |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 6/7/1996 | | |
|
|
|
|
Plan Received by (PRP) | 5/2/1996 | | 6/6/1996 | | PASS |
|
|
|
received two plans, applications, P&Z notes and approval, achd approval, cdh approv, PW approv, Plumbing and Mechanical approval. 06/06/96 16:47:42 PRP - this action updated by action script from <<>> in Case No. BLD96-0673
|
Plan resubmittals received | 6/6/1996 | | 6/6/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 6/6/1996 | | PASS |
|
|
|
issue
|
Routing - FIRE | 6/3/1996 | | 6/5/1996 | | PASS |
|
|
|
|
Plan resubmittals received | 5/31/1996 | | 5/31/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/31/1996 | | PASS |
|
|
|
file
|
Plan Reviewer's activity | | | 5/31/1996 | | PASS |
|
|
|
RECEIVED RESUBS, REVIEW, APPROVE WITH CONDITIONS, ASSEMBLE IN PLANS, INPUT TO PERMIT PLAN, FORWARD TO FIRE.
|
Plan resubmittals requested | 5/15/1996 | | 5/15/1996 | | |
|
|
|
|
Plan Reviewer's activity | | | 5/15/1996 | | PEND |
|
|
|
REVIEWED PLANS COMPLETE WITH SIGHT AND BASEMENT PLAN, MARK-UP, PREPARE CORRECTION NOTICE, FAX TO ARCH, HOLD TILL RESUBS RECEIVED.
|
Unassigned to Plan Reviewer | 3/22/1996 | | 5/2/1996 | | PASS |
|
|
|
05/02/96 10:48:27 PRP - this action updated by action script from <<>> in Case No. BLD96-0673
|
Routing - MECHANICAL | 4/30/1996 | | 5/1/1996 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 4/16/1996 | | 4/29/1996 | | PASS |
|
|
|
CONTACTED MATHEW REDDY AT ###-#### FOR CDH AND ACHD PICKUP. CONTACTED MATHEW REDDY AT ###-#### FOR ACHD PICKUP.4/16/96 DAR
|
Routing - PLUMBING | 4/11/1996 | | 4/16/1996 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/9/1996 | | 4/11/1996 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 3/26/1996 | | 4/2/1996 | | PASS |
|
|
|
|
Routing - PLANNING | 3/25/1996 | | 3/26/1996 | | PASS |
|
|
|
New handicap ramp shall not reduce any parking requirements. Reviewed by MS.
|
Plan routing begun/TENANTS | | | 3/25/1996 | | |
|
|
|
Route to Planning, Central District Health, Ada County Highway District, Public Works, Plumbing then back to Plan Check. After Plan Check route to Fire Department.
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 3/22/1996 | | |
|
|
|
|
Application received | | | 3/22/1996 | | |
|
|
|
|
Received Certificate of Value | | | 3/22/1996 | | PASS |
|
|
|
|
Plans taken to Plan Check | | | 3/22/1996 | | PASS |
|
|
|
|
Routing - BUILDING | 5/2/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 6/6/1996 | | | | PEND |
|
|
|
|