Permanent Occupancy | | 9/25/1996 | 9/25/1996 | | DONE |
|
|
|
|
INSP - Final | 9/25/1996 | 9/25/1996 | 9/25/1996 | P | PASS |
|
|
|
09/25/96 333 - card signed for final perm
|
INSP - Permanent occupancy | | | 9/25/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6594 issued 9-25-96 to Murie Graphics in the Tower Plaza.
|
INSP - Final | 9/24/1996 | 9/24/1996 | 9/24/1996 | P | FAIL |
|
|
|
09/24/96 333 - not ready
|
INSP - Final | 9/23/1996 | 9/23/1996 | 9/23/1996 | P | FAIL |
|
|
|
09/23/96 333 - #401 CORR-CORREC-CALL FOR REINSP WHEN COMPLETED old corrections not made
|
INSP - Temporary occupancy | | | 9/23/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3280 issued 9-23-96 to Murie Graphics.
|
INSP - Final | 9/18/1996 | 9/19/1996 | 9/19/1996 | P | FAIL |
|
|
|
Firecaulking still required in corridor penetrations.
|
INSP - Final | 9/16/1996 | 9/17/1996 | 9/17/1996 | P | PART |
|
|
|
LATE AFTERNOON. CN issued ok for temp. occ.. Routed to Cathy.
|
INSP - Final | 9/13/1996 | 9/16/1996 | 9/17/1996 | A | PASS |
|
|
|
all items complete 9/25/96 09/16/96 405 - SUITE 400 - MIKE MURIE - ###-#### alarm test and final temp occ isssued...smoke seals missing on doors
|
INSP - Final | 9/16/1996 | 9/16/1996 | 9/16/1996 | | NR |
|
|
|
/ / 405 - not ready...alarms not working
|
INSP - Final | 8/28/1996 | 8/28/1996 | 8/28/1996 | | FAIL |
|
|
|
/ / 405 - b occ in multi-use high rise advised cont he will need alarm plans. also needs f/s damper on penetration of wall to adjacent suite w fresh air duct. noted on plans but arch said not required.
|
INSP - Framing/Rough-in | 8/26/1996 | 8/27/1996 | 8/27/1996 | A | PASS |
|
|
|
08/27/96 333 - corridor walls ok
|
90 day tracking............. | | 4/4/1996 | 7/3/1996 | | PASS |
|
|
|
|
INSP - Framing/Rough-in | 6/19/1996 | 6/19/1996 | 6/19/1996 | P | PASS |
|
|
|
|
INSP - Conference | 6/5/1996 | 6/5/1996 | 6/5/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - LEFT CORRECTION NOTICE TELLING H.V.A.C. CONTRACTOR TO SUBMIT DRAWINGS TO THE CITY FOR REVIEW AND APPROVAL BEFORE ANY INSPECTIONS CAN DONE.
|
Issue PAID IN FULL permit | | | 6/5/1996 | | |
|
|
|
|
Telephone call | 5/30/1996 | | 5/30/1996 | | |
|
|
|
Called Neil Hosford. We talked about the incorrect fire stopping systems that were called out on the resubmitted drawings. He was told that this time I (Carl J. Westfall) would "red line" the drawings with an example of an acceptable fire stopping system. In the future we want accurate systems for the application.
|
Permit taken to Permit Desk | | | 5/30/1996 | | PASS |
|
|
|
|
Routing - BUILDING | 5/14/1996 | | 5/30/1996 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/30/1996 | | |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 5/30/1996 | | |
|
|
|
|
Plan Received by (CJW) | 5/9/1996 | | 5/30/1996 | | PASS |
Carl Westfall
|
|
|
05/30/96 11:05:28 CJW - this action updated by action script from <<>> in Case No. BLD96-0777
|
Plan resubmittals received | 5/30/1996 | | 5/29/1996 | | PASS |
|
|
|
|
Routing - FIRE | 5/10/1996 | | 5/14/1996 | | PASS |
|
|
|
|
Plan resubmittals requested | 5/10/1996 | | 5/10/1996 | | |
|
|
|
Six (6) items require a response.
|
Routing - BUILDING | 5/9/1996 | | 5/10/1996 | | FAIL |
|
|
|
Six (6) items require a response.
|
Plan Reviewer's Copy of Permit | | | 5/10/1996 | | |
|
|
|
|
Routing - PUBLIC WORKS | 4/4/1996 | | 4/11/1996 | | PASS |
|
|
|
|
INSP - Framing/Rough-in | 4/8/1996 | 4/8/1996 | 4/8/1996 | P | CANC |
Wes Worcester
|
|
|
wrong permit number entered
|
Plans taken to Plan Check | | | 4/4/1996 | | PASS |
|
|
|
|
Application received | | | 4/4/1996 | | |
|
|
|
|
Plan routing begun/TENANTS | | | 4/4/1996 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 4/4/1996 | | |
|
|
|
|
Routing - BUILDING | 4/11/1996 | | | | PEND |
|
|
|
|
Unassigned to Plan Reviewer | 4/4/1996 | | | | |
|
|
|
|
Routing - BUILDING | 5/14/1996 | | | | PEND |
|
|
|
|