CHANGE STATUS TO (D) | | | 8/16/1996 | | |
|
|
|
|
INSP - Letter of compliance | 8/12/1996 | 8/12/1996 | 8/12/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C#11299
|
INSP - Final | 8/12/1996 | 8/12/1996 | 8/12/1996 | P | PASS |
Alan Hauser
|
|
|
08/12/96 350 - FRONT DOOR IS OPEN FINAL
|
INSP - Letter of compliance | 8/12/1996 | 8/12/1996 | 8/12/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C#11299
|
INSP - Final | 8/7/1996 | 8/8/1996 | 8/8/1996 | A | NH |
Alan Hauser
|
|
|
08/08/96 350 - ACCESS THROUGH SIDE DOOR OF GARAGE HOUSE LOCKED LEFT NOTICE
|
INSP - Energy code compliance | 6/12/1996 | 6/12/1996 | 6/13/1996 | P | PASS |
Alan Hauser
|
|
|
06/12/96 350 - ok to cover
|
INSP - Framing/Rough-in | 6/10/1996 | 6/11/1996 | 6/11/1996 | A | NR |
Alan Hauser
|
|
|
06/10/96 350 - not ready didn't have electrical done, did partial inspec
|
INSP - Framing/Rough-in | 6/11/1996 | 6/11/1996 | 6/11/1996 | P | PASS |
Alan Hauser
|
|
|
06/11/96 350 - REINSPECT ON THE FRAME SEE CORRECTION NOTE ON THE JOBSITE corrections made ok to insulate
|
INSP - Footings | 5/20/1996 | 5/20/1996 | 5/20/1996 | P | CANC |
Jim Sly
|
|
|
05/20/96 316 - done by 350
|
Issue PAID IN FULL permit | | | 5/10/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/23/1996 | | |
|
|
|
|
Plan Reviewer's activity | | | 4/22/1996 | | PASS |
|
|
|
REVIEWED PLAN, MARK-UP, INPUT TO PERMIT PLAN, CORRECTIONS, ASSEMBLE, ISSUE
|
Plan Received by (PRP) | 4/22/1996 | | 4/22/1996 | | PASS |
|
|
|
received two plans and specs, beam calcs, energy path 04/22/96 17:40:11 PRP - this action updated by action script from <<>> in Case No. BLD96-0860
|
Permit taken to Permit Desk | | | 4/22/1996 | | PASS |
|
|
|
ISSUE
|
Unassigned to Plan Reviewer | | | 4/22/1996 | | PASS |
|
|
|
04/22/96 17:16:50 PRP - this action updated by action script from <<>> in Case No. BLD96-0860
|
Print Pending Permit.LaserJet4 | | | 4/22/1996 | | PASS |
|
|
|
FILES
|
Plans taken to Plan Check | | | 4/17/1996 | | PEND |
|
|
|
|
Routing - PLANNING | 4/15/1996 | | 4/17/1996 | | PASS |
|
|
|
Approved by SB.
|
Routing - PUBLIC WORKS | 4/11/1996 | | 4/12/1996 | | PASS |
|
|
|
|
Application received | | | 4/11/1996 | | |
|
|
|
|
Routing - FRONT DESK | 4/17/1996 | | | | PEND |
|
|
|
|