CHANGE STATUS TO (D) | | | 2/24/1997 | | |
|
|
|
|
INSP - Final | 9/13/1996 | 9/13/1996 | 9/13/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 9/10/1996 | 9/13/1996 | 9/13/1996 | A | CANC |
Wes Worcester
|
|
|
NEEDED FINAL
|
INSP - Letter of compliance | 9/13/1996 | 9/13/1996 | 9/13/1996 | A | PASS |
Wes Worcester
|
|
|
C/C # 11896
|
INSP - Framing/Rough-in | 7/15/1996 | 7/15/1996 | 7/15/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Energy code compliance | 7/15/1996 | 7/15/1996 | 7/15/1996 | P | CANC |
Jim Sly
|
|
|
07/15/96 316 - Gave to Wes.
|
INSP - Energy code compliance | 7/15/1996 | 7/15/1996 | 7/15/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 7/12/1996 | 7/12/1996 | 7/12/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Conference | 7/11/1996 | 7/11/1996 | 7/11/1996 | P | PART |
Wes Worcester
|
|
|
WENT OVER INSP PROCEDURE AGAIN
|
INSP - Framing/Rough-in | 7/11/1996 | 7/11/1996 | 7/11/1996 | P | CANC |
Wes Worcester
|
|
|
CALLED BACK TO CANCEL PM AS WAS NOT YET READY
|
INSP - Framing/Rough-in | 7/10/1996 | 7/11/1996 | 7/11/1996 | A | NR |
Wes Worcester
|
|
|
ELECT NOT DONE
|
INSP - Carpentry | 7/1/1996 | 7/1/1996 | 7/1/1996 | P | PASS |
Wes Worcester
|
|
|
shr nailing ok
|
INSP - Framing/Rough-in | 7/1/1996 | 7/1/1996 | 7/1/1996 | P | NR |
Wes Worcester
|
|
|
PARTIAL FRAME
|
INSP - Conference | 7/1/1996 | 7/1/1996 | 7/1/1996 | P | FAIL |
Wes Worcester
|
|
|
met with truss co and still need calcs for overspanned 4x4's...trusses ok and specs being faxed to ofc
|
INSP - Framing/Rough-in | 6/26/1996 | 6/27/1996 | 6/27/1996 | A | NR |
Wes Worcester
|
|
|
a.m.
|
INSP - Footings | 5/13/1996 | 5/13/1996 | 5/13/1996 | P | CANC |
|
|
|
SENT BACK TO WES
|
Inspection Record Card- Bld | | | 5/9/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/9/1996 | | |
|
|
|
|
INSP - Footings | 5/13/1996 | 5/14/1996 | 5/8/1996 | A | CANC |
Wes Worcester
|
|
|
05/13/96 342 - passed 5/13/96
|
INSP - Footings | 5/10/1996 | 5/13/1996 | 5/7/1996 | A | PASS |
Wes Worcester
|
|
|
05/13/96 342 - 5' setback noted on approved set of plans which noted 2 s
|
INSP - Footings | 5/7/1996 | 5/7/1996 | 5/7/1996 | | NR |
Wes Worcester
|
|
|
/ / 342 - still n/r and a ? on setbks
|
INSP - Foundation | 5/7/1996 | 5/7/1996 | 5/7/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
Plan Received by (DJO) | 4/24/1996 | | 5/3/1996 | | PASS |
Dan Overy
|
|
|
05/03/96 15:58:10 DJO - this action updated by action script from <<>> in Case No. BLD96-0866
|
Permit taken to Permit Desk | | | 5/3/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/3/1996 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/2/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | | | 4/24/1996 | | PASS |
|
|
|
04/24/96 13:53:47 DJO - this action updated by action script from <<>> in Case No. BLD96-0866
|
Plan resubmittals requested | | | 4/24/1996 | | PEND |
|
|
|
|
Plans taken to Plan Check | | | 4/17/1996 | | PEND |
|
|
|
|
Routing - PLANNING | 4/15/1996 | | 4/17/1996 | | PASS |
|
|
|
Approved by SB.
|
Routing - PUBLIC WORKS | 4/12/1996 | | 4/15/1996 | | PASS |
|
|
|
|
Application received | | | 4/12/1996 | | |
|
|
|
|
Routing - FRONT DESK | 4/17/1996 | | | | PEND |
|
|
|
|