CHANGE STATUS TO (D) | | | 2/24/1997 | | |
|
|
|
|
INSP - Letter of compliance | 11/15/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Final | 11/15/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Final | 11/14/1996 | 11/14/1996 | 11/14/1996 | P | FAIL |
Wes Worcester
|
|
|
caulk outlet boxes and install front door
|
INSP - Final | 11/12/1996 | 11/13/1996 | 11/13/1996 | P | NR |
Wes Worcester
|
|
|
still do not have eng letter
|
Inspection Record Card- Bld | | | 8/8/1996 | | |
|
|
|
|
INSP - Energy code compliance | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | PASS |
Wes Worcester
|
|
|
still need eng on East shear wall
|
INSP - Framing/Rough-in | 7/19/1996 | 7/22/1996 | 7/22/1996 | A | CANC |
Alan Hauser
|
|
|
07/22/96 350 - TO BE DONE BY #342
|
INSP - Footings | 5/21/1996 | 5/22/1996 | 5/22/1996 | A | CANC |
|
|
|
given to wes
|
INSP - Foundation | 5/24/1996 | 5/24/1996 | 5/18/1996 | P | PASS |
Wes Worcester
|
|
|
05/24/96 342 -
|
INSP - Footings | 5/18/1996 | 5/18/1996 | 5/18/1996 | | NR |
Wes Worcester
|
|
|
/ / 342 - eng for hd strap vs column to be on job site at next insp
|
INSP - Footings | 5/18/1996 | 5/18/1996 | 5/18/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - ck'd epoxy set of dowels in West 1/2 of ftg and ok....eng be attn Wes
|
INSP - Foundation | 5/18/1996 | 5/18/1996 | 5/18/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - rebar ok
|
INSP - Footings | 5/18/1996 | 5/18/1996 | 5/18/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - ck'd rebar clearances and pk
|
INSP - Footings | 5/23/1996 | 5/23/1996 | 5/17/1996 | P | FAIL |
Wes Worcester
|
|
|
05/23/96 342 - poured w/o insp... verify rebar placement....do not cover it has insufficient cover
|
Issue PAID IN FULL permit | | | 5/16/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/1996 | | |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 5/16/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/15/1996 | | PASS |
|
|
|
FILES
|
Plan resubmittals received | 5/15/1996 | | 5/15/1996 | | |
|
|
|
|
Plan Received by (PRP) | 5/6/1996 | | 5/15/1996 | | PASS |
|
|
|
RECEIVED TWO PLANS, TWO ENGINEERS FOUNDATION REPORT, NO DETACHED GARAGE PLANS, NO SOILS REPORT 05/15/96 15:32:54 PRP - this action updated by action script from <<>> in Case No. BLD96-1057
|
Permit taken to Permit Desk | | | 5/15/1996 | | PASS |
|
|
|
ISSUE
|
Plan Reviewer's activity | | | 5/15/1996 | | PASS |
|
|
|
REVIEW MARKED-UP PLANS, INPUT TO PERMIT-PLAN, CORRECTION/CONDITIONS, ISSUE
|
Unassigned to Plan Reviewer | 5/2/1996 | | 5/9/1996 | | PASS |
|
|
|
05/09/96 10:23:51 PRP - this action updated by action script from <<>> in Case No. BLD96-1057
|
Plan resubmittals requested | 5/9/1996 | | 5/9/1996 | | |
|
|
|
|
Telephone call | | | 5/9/1996 | | PEND |
|
|
|
CALLED WILSON BROS TO INFORM OF PLAN FAILURE AND FAX COPY OF ACCOMPANING LETTER.
|
Plan Reviewer's activity | | | 5/9/1996 | | FAIL |
|
|
|
REVIEW PLANS AND ENGINEERS REPORT AND FND PLANS, REJECT PLANS DUE TO 21 ITEMS NOT CORRECT ON PLANS, NO SOILS REPORT AVAILABLE.
|
Plan resubmittals received | | | 5/8/1996 | | PEND |
|
|
|
RECEIVED 8.5 X 11" PLANS FOR DETACHED GARAGE TO ATTACH TO HOUSE PLANS.
|
Routing - PLANNING | 5/2/1996 | | 5/6/1996 | | PASS |
|
|
|
Approved by MGH.
|
Plans taken to Plan Check | | | 5/6/1996 | | PASS |
|
|
|
|
Application received | | | 5/2/1996 | | |
|
|
|
|
Routing - PUBLIC WORKS | 4/30/1996 | | 5/1/1996 | | PEND |
|
|
|
BRIAN BROUGHT PAPER WORK IN AND PLAN WAS RE-ROUTED TO PUBLIC WORKS 4/30/PE
|
Routing - FRONT DESK | 4/25/1996 | | 4/30/1996 | | PASS |
|
|
|
ROUTED BACK TO PUBLIC WORKS
|
Routing - PUBLIC WORKS | 4/18/1996 | | 4/25/1996 | | FAIL |
|
|
|
FAILED PUBLIC WORKS, WAITING FOR ADDITIONAL INFO
|
Routing - FRONT DESK | 5/6/1996 | | | | PEND |
|
|
|
|