CHANGE STATUS TO (D) | | | 2/24/1997 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 10/31/1996 | | |
|
|
|
|
INSP - Final | 9/11/1996 | 9/11/1996 | 9/11/1996 | P | PASS |
Jim Sly
|
|
|
09/11/96 316 - RE-INSPECTION C/N Removed..C/C # 11262
|
INSP - Letter of compliance | 9/11/1996 | 9/11/1996 | 9/11/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 11262
|
INSP - Letter of compliance | 9/11/1996 | 9/11/1996 | 9/11/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 11262
|
INSP - Final | 9/9/1996 | 9/10/1996 | 9/10/1996 | P | FAIL |
Jim Sly
|
|
|
09/10/96 316 - C/N ...misc
|
INSP - Framing/Rough-in | 7/29/1996 | 7/29/1996 | 7/29/1996 | P | FAIL |
Jim Storey
|
|
|
07/29/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETEDFRAME REINSPECT
|
Issue & PRINT FEE-DUE permit | | | 7/29/1996 | | |
|
|
|
|
INSP - Energy code compliance | 7/19/1996 | 7/19/1996 | 7/19/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - INS NOT COMPLETE, CORR'S NOT MADE
|
INSP - Framing/Rough-in | 7/19/1996 | 7/19/1996 | 7/19/1996 | P | FAIL |
Carl Dependahl
|
|
|
07/19/96 340 - framing reinspect KEEP C/N, CORR'S NOT DONE. 42.00 REINSP
|
INSP - Framing/Rough-in | 7/17/1996 | 7/17/1996 | 7/17/1996 | P | FAIL |
|
|
|
07/17/96 338 - EARLY PM c/n issued ok to insulate
|
INSP - Foundation | 6/3/1996 | 6/3/1996 | 6/3/1996 | P | PART |
Carl Dependahl
|
|
|
06/03/96 340 - POURED W/O INSP
|
INSP - Footings | 6/3/1996 | 6/3/1996 | 6/3/1996 | P | PART |
Carl Dependahl
|
|
|
06/03/96 340 - POURED W/O INSP
|
Issue PAID IN FULL permit | | | 5/29/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/23/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | 5/8/1996 | | 5/23/1996 | | PASS |
|
|
|
05/23/96 14:36:26 DJO - this action updated by action script from <<>> in Case No. BLD96-1158
|
Plan Received by (DJO) | 5/23/1996 | | 5/23/1996 | | PASS |
Dan Overy
|
|
|
05/23/96 14:36:41 DJO - this action updated by action script from <<>> in Case No. BLD96-1158
|
Permit taken to Permit Desk | | | 5/23/1996 | | PASS |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 5/15/1996 | | |
|
|
|
|
Routing - PLANNING | 5/10/1996 | | 5/13/1996 | | PASS |
|
|
|
Approved by GRH.
|
Plans taken to Plan Check | | | 5/13/1996 | | PEND |
|
|
|
|
Application received | | | 5/10/1996 | | |
|
|
|
|
Routing - PUBLIC WORKS | 5/8/1996 | | 5/9/1996 | | PASS |
|
|
|
|
Routing - FRONT DESK | 5/13/1996 | | | | PEND |
|
|
|
|