Case Summary (BLD) | | | 10/15/2003 | | |
|
|
|
|
INSP - Letter of compliance | | | 12/12/1996 | | PASS |
|
|
|
ISSUED #12375 C OF C BY MJW THIS DATE.
|
INSP - Final | 12/11/1996 | 12/11/1996 | 12/11/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - GOT RESUBMITTAL, C/N OK. OK FOR C/O...BSMT REMODEL. CARD BRO CONTRACTOR, NEED FRONT DESK SIG
|
INSP - Final | 11/15/1996 | 11/18/1996 | 11/18/1996 | A | NR |
Carl Dependahl
|
|
|
NEED ARCH'S LETTER RE DELETIONS( W BLD1055442) FOR FINAL
|
INSP - Conference | 11/18/1996 | 11/18/1996 | 11/18/1996 | | PASS |
|
|
|
W/SCOT WENDELL OF LOMBARD CONRAD ARCH'S...WILL SEND LETTER/DRAWING RE MODIFICATION OF PERMIT(S) FOR FINAL....OWNER DELETED MUCH OF WORK( PRIMARILY FROM BLD 1055442 ) WE NEED FOLLOW -UP SO PERMITS REFLECT WORK ACTUALLY DONE THROUGHOUT. BASEMENT WORK IS ESSENTIALLY COMPLETE, NEED ALL PERMITS PAID.
|
INSP - Final | 11/13/1996 | 11/13/1996 | 11/13/1996 | | PASS |
|
|
|
OK FOR PERM OCC OR CERT OF COMPLIANCE
|
INSP - Final | 11/6/1996 | 11/6/1996 | 11/6/1996 | P | FAIL |
Carl Dependahl
|
|
|
11/06/96 340 - NEED ARCH'S REVISION FOR DELETIONS. SEE C/N
|
INSP - Final | 11/5/1996 | 11/5/1996 | 11/5/1996 | | PASS |
|
|
|
OK FOR TEMP OCC CORRECTION NOTICE ISSUED
|
INSP - Temporary occupancy | 11/5/1996 | 11/5/1996 | 11/5/1996 | P | CANC |
Jim Sly
|
|
|
11/05/96 316 - Never completed and inspection at this site.....Project s Dependahl had this area..... Gave to Carl Dependahl.
|
INSP-Sprinkler Rough-in/Hydro | 11/1/1996 | 11/4/1996 | 11/5/1996 | A | FAIL |
Joe Tawney
|
|
|
LARRY SMITH - ###-#### EXT.6103 (HE WASN'T SURE EXACTLY WHAT HE NEEDED.) SPKLR HEADS OMMITTED IN 2ND FLR ELEVATOR VESTIBULE AND JANITOR RM
|
Issue PAID IN FULL permit | | | 8/19/1996 | | |
|
|
|
|
Telephone call | | | 8/16/1996 | | |
|
|
|
GORDON SAID HE WOULD BE DOWN TO PICK IT UP
|
90 day tracking............. | | 5/13/1996 | 8/11/1996 | | PASS |
|
|
|
|
Routing - BUILDING | 6/28/1996 | | 7/23/1996 | | PASS |
|
|
|
|
Plan Received by (DRS) | 6/28/1996 | | 7/23/1996 | | PASS |
Dan Stuart
|
|
|
07/23/96 10:56:20 DRS - this action updated by action script from <<>> in Case No. BLD96-1191
|
ISSUE OCCUPANCY FORM | | | 7/23/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/23/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 7/23/1996 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/19/1996 | | |
|
|
|
|
Routing - FIRE | 7/3/1996 | | 7/11/1996 | | PASS |
|
|
|
|
Meeting | | | 7/10/1996 | | |
|
|
|
Met with Scott Wendell of Lombard Conrad to review preliminary plan review correction items and discuss possible solutions to items. Scott will discuss with Extended Systems personel & resubmit plans showing corrections.
|
Plan Reviewer's Copy of Permit | | | 7/3/1996 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 7/3/1996 | | |
|
|
|
|
Unassigned to Plan Reviewer | 5/13/1996 | | 6/28/1996 | | |
|
|
|
07/03/96 15:21:14 DRS - this action updated by action script from <<>> in Case No. BLD96-1191
|
Routing - PUBLIC WORKS | 5/15/1996 | | 5/17/1996 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 5/15/1996 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Plans ACCEPTED BY PLAN CHECK | | | 5/14/1996 | | |
|
|
|
|
Plans taken to Plan Check | | | 5/13/1996 | | PASS |
|
|
|
|
Application received | | | 5/13/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 5/13/1996 | | |
|
|
|
|
Routing - BUILDING | 7/12/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 5/17/1996 | | | | |
|
|
|
|