CHANGE STATUS TO (D) | | | 8/16/1996 | | |
|
|
|
|
90 day tracking............. | | 5/16/1996 | 8/14/1996 | | PASS |
|
|
|
|
INSP - Final | 8/12/1996 | 8/13/1996 | 8/13/1996 | P | CANC |
Alan Hauser
|
|
|
08/13/96 350 - CALL ###-#### FOR EXACT LOCATION. SOMEONE WILL BE IN THE IF YOU NEED FURTHER ASSISTANCE. DONE BY #342
|
INSP - Conference | 8/13/1996 | 8/13/1996 | 8/13/1996 | P | PASS |
Wes Worcester
|
|
|
met w/Cathy to issue L/C
|
INSP - Letter of compliance | 8/13/1996 | 8/13/1996 | 8/13/1996 | P | PASS |
Wes Worcester
|
|
|
l/c issued
|
INSP - Final | 8/13/1996 | 8/13/1996 | 8/13/1996 | P | PASS |
Wes Worcester
|
|
|
alan received this request by "accident".........
|
INSP - Letter of compliance | 8/13/1996 | 8/13/1996 | 8/13/1996 | P | PASS |
Wes Worcester
|
|
|
l/c issued
|
INSP - Framing/Rough-in | 8/8/1996 | 8/8/1996 | 8/8/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 - placed correct guardrails and handrail
|
INSP - Conference | 8/6/1996 | 8/8/1996 | 8/8/1996 | A | PASS |
Wes Worcester
|
|
|
08/08/96 342 - CONF. THURS. 9 A.M. AT PRESBYTERIAN CHURCH.
|
INSP - Conference | 8/5/1996 | 8/5/1996 | 8/5/1996 | A | PASS |
Wes Worcester
|
|
|
met w/Carl ref playground guardrails and steps
|
INSP - Conference | 8/2/1996 | 8/2/1996 | 8/2/1996 | A | PART |
Wes Worcester
|
|
|
discussed steps w/ plan ck and architect
|
INSP - Conference | 7/31/1996 | 7/31/1996 | 7/31/1996 | P | PART |
Wes Worcester
|
|
|
called architect to submit changes for stair steps, etc
|
INSP - Carpentry | 7/31/1996 | 7/31/1996 | 7/31/1996 | P | FAIL |
Wes Worcester
|
|
|
RAILINGS - PAUL HOFFMAN - 344- 8162 NEEDS A TIME TO MEET YOU...... stair steps not to plan nor code
|
INSP - Foundation | 6/24/1996 | 6/24/1996 | 6/24/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Foundation | 6/21/1996 | 6/24/1996 | 6/24/1996 | A | NR |
Wes Worcester
|
|
|
06/24/96 342 - MON. A.M.
|
INSP - Footings | 6/21/1996 | 6/21/1996 | 6/21/1996 | | NR |
Wes Worcester
|
|
|
06/21/96 342 - P.M. EARLY
|
INSP - Footings | 6/21/1996 | 6/21/1996 | 6/21/1996 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
Issue PAID IN FULL permit | | | 6/21/1996 | | |
|
|
|
|
Plan Received by (CJW) | 6/10/1996 | | 6/20/1996 | | PASS |
Carl Westfall
|
|
|
06/20/96 11:08:48 CJW - this action updated by action script from <<>> in Case No. BLD96-1228
|
Inspection Record Card- Bld | | | 6/20/1996 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 6/20/1996 | | |
|
|
|
|
Routing - BUILDING | 6/11/1996 | | 6/20/1996 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Permit taken to Permit Desk | | | 6/20/1996 | | PASS |
|
|
|
|
Plan resubmittals received | 6/20/1996 | | 6/18/1996 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Telephone call | 6/11/1996 | | 6/11/1996 | | |
|
|
|
|
Plan resubmittals requested | 6/11/1996 | | 6/11/1996 | | |
|
|
|
Three items require a response. See conditions sections.
|
Routing - BUILDING | 6/10/1996 | | 6/11/1996 | | FAIL |
|
|
|
Three items require a response. See conditions section.
|
Plan Reviewer's Copy of Permit | | | 6/11/1996 | | |
|
|
|
|
Routing - PLANNING | 5/24/1996 | | 5/27/1996 | | PASS |
|
|
|
X-ref: CU-78-94. Approved by SR.
|
Routing Off Site - A.C.H.D | 5/21/1996 | | 5/24/1996 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 5/21/1996 | | |
|
|
|
Route to Ada County Highway District, Planning then back to Plan Check.
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 5/17/1996 | | |
|
|
|
|
Plans taken to Plan Check | | | 5/16/1996 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/16/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 5/16/1996 | | |
|
|
|
|
Application received | | | 5/16/1996 | | |
|
|
|
|
Routing - FIRE | 6/11/1996 | | 6/19/1906 | | PASS |
|
|
|
|
Routing - BUILDING | 6/11/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 5/29/1996 | | | | PEND |
|
|
|
|
Unassigned to Plan Reviewer | 5/16/1996 | | | | |
|
|
|
|