INSP - Permanent occupancy | | | 9/6/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6567 issued 9-6-96 to H. J. Heinz in the Lakepointe Center building.
|
Permanent Occupancy | | 8/26/1996 | 8/26/1996 | | DONE |
|
|
|
|
90 day tracking............. | | 5/17/1996 | 8/15/1996 | | |
|
|
|
|
INSP - Final | 7/31/1996 | 8/1/1996 | 8/1/1996 | A | NR |
Jim Sly
|
|
|
07/31/96 316 - Called and said..Not Ready.
|
INSP - Fire Dept. Request | 7/27/1996 | 7/29/1996 | 7/29/1996 | | PASS |
|
|
|
smoke seals not installed on corridor door, door wont close tightly. Had building maintenance remove wire rope holding rear main exit doors closed. Reinspect scheduled for 7/30, PM....will call. Door completed 7/31, reinspected, card signed
|
INSP - Final | 7/12/1996 | 7/12/1996 | 7/12/1996 | P | PASS |
Jim Sly
|
|
|
07/12/96 316 - C/N removed.
|
(F) Reprint permit | | | 7/12/1996 | | |
|
|
|
|
INSP - Final | 7/10/1996 | 7/11/1996 | 7/11/1996 | A | NR |
Jim Sly
|
|
|
07/10/96 316 - Need electrical and Fire Dept. sign off.
|
INSP - Framing/Rough-in | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - All framing OK to cover....need to look at new door installa in Corridor.
|
INSP - Framing/Rough-in | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - OK to cover filled in doorways only...call insp.of corridor door remodel.
|
INSP - Footings | 6/13/1996 | 6/14/1996 | 6/14/1996 | A | CANC |
Carl Dependahl
|
|
|
06/13/96 340 - a.m. early. I THINK YOU HAD THIS YESTERDAY...IN CASE YOU IT, HE RECALLED IT FOR FRI. A.M. 400 AREA, CANCEL PER MOLLY...WRONG PERMIT NO.?
|
Permit taken to Permit Desk | | | 6/14/1996 | | PASS |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 6/14/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/1996 | | |
|
|
|
|
Plan Received by (PRP) | 6/8/1996 | | 6/14/1996 | | PASS |
|
|
|
H J HEINZ--RECEIVED TWO PLANS AND APPLICATIONS, MARLENE'S PREREVIEW NOTES, AND TWO MIS96 PERMITS FOR ADDITIONAL TWO TENANTS INCLUDED IN THIS REMODEL. 06/14/96 08:07:52 KMM - this action updated by action script from <<>> in Case No. BLD96-1240
|
Issue PAID IN FULL permit | | | 6/14/1996 | | |
|
|
|
|
INSP - Footings | 6/13/1996 | 6/13/1996 | 6/13/1996 | P | CANC |
Carl Dependahl
|
|
|
06/13/96 340 - 400 AREA?...SENT TO STOREY PER BOB A.
|
Routing - FIRE | 6/10/1996 | | 6/10/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/8/1996 | | PASS |
|
|
|
FILES
|
Plan Reviewer's activity | | | 6/8/1996 | | PEND |
|
|
|
REVIEWED PLANS, MARK-UP, PERMIT PLAN INPUT, ASSEMBLE TO FILE AND PLANS, FORWARD TO FIRE.
|
Unassigned to Plan Reviewer | 5/17/1996 | | 6/8/1996 | | PASS |
|
|
|
06/08/96 09:36:00 PRP - this action updated by action script from <<>> in Case No. BLD96-1240
|
Plan routing begun/TENANTS | | | 5/21/1996 | | |
|
|
|
This plan to be reviewed by Plan Check then sent to the Fire Department.
|
Plans ACCEPTED BY PLAN CHECK | | | 5/17/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 5/17/1996 | | |
|
|
|
|
Application received | | | 5/17/1996 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Routing - BUILDING | 6/11/1996 | | | | PEND |
|
|
|
|