Case Summary (BLD) | | | 6/15/2005 | | |
|
|
|
|
INSP - Permanent occupancy | | | 10/11/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6626 issued 10-9-96 to Bruegger's Bagel Bakery.
|
INSP - Final | 10/9/1996 | 10/9/1996 | 10/9/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL
|
Permanent Occupancy | | 10/9/1996 | 10/9/1996 | | DONE |
|
|
|
|
INSP - Temporary occupancy | | | 10/8/1996 | | PASS |
|
|
|
Temp. Occ. Cert. #3291 issued 10-8-96 to Bruegger's Bagel Bakery by Monica.
|
INSP - Final | 10/7/1996 | 10/7/1996 | 10/7/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - TCO -TEMP C OF O ISSUED mec, health dept. 90 days.
|
INSP - Final | 10/7/1996 | 10/7/1996 | 10/7/1996 | | PASS |
|
|
|
/ / 405 - door hardware replaced
|
INSP - Final | 10/7/1996 | 10/7/1996 | 10/7/1996 | P | CANC |
|
|
|
EARLY P.M. PLEASE. done in am,
|
INSP - Final | 10/3/1996 | 10/4/1996 | 10/4/1996 | A | FAIL |
|
|
|
10/03/96 405 - CALL ODIE AT ###-#### BEFORE INSPECTING not ready....doors not changed
|
INSP - Final | 9/25/1996 | 9/26/1996 | 9/26/1996 | A | FAIL |
|
|
|
09/25/96 405 - c/n issued on exit doors, address, assembly permit
|
INSP - Ceiling grid | 9/16/1996 | 9/16/1996 | 9/16/1996 | P | PASS |
Jim Storey
|
|
|
09/16/96 301 - grid ok
|
90 day tracking............. | | 6/5/1996 | 9/3/1996 | | PEND |
|
|
|
|
INSP - Framing/Rough-in | 8/12/1996 | 8/13/1996 | 8/13/1996 | A | PASS |
Jim Storey
|
|
|
08/12/96 301 - FRAM-OK FRAMING
|
Issue PAID IN FULL permit | | | 7/17/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/11/1996 | | |
|
|
|
|
ISSUE OCCUPANCY FORM | | | 7/11/1996 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/10/1996 | | PASS |
|
|
|
reviewed plans, prepared correction list, fax to arch, mark-up plan, forward to Dave for forwarding. Received Resubs and Approve 7/8/96.
|
Permit taken to Permit Desk | | | 7/10/1996 | | PASS |
|
|
|
issue
|
Plan Received by (PRP) | 6/27/1996 | | 7/10/1996 | | PASS |
|
|
|
BRUEGGERS BEGAL--RECEIVED TWO PLANS, SPEC BOOKS, APPLICATIONS FOR REVIEW 07/10/96 16:45:20 PRP - this action updated by action script from <<>> in Case No. BLD96-1444
|
Print Pending Permit.LaserJet4 | | | 7/10/1996 | | PASS |
|
|
|
files
|
Plan resubmittals received | 7/10/1996 | | 7/8/1996 | | |
|
|
|
|
Routing - FIRE | 7/1/1996 | | 7/3/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | 6/5/1996 | | 6/27/1996 | | PASS |
|
|
|
06/27/96 09:18:36 PRP - this action updated by action script from <<>> in Case No. BLD96-1444
|
Routing - MECHANICAL | 6/25/1996 | | 6/26/1996 | | PASS |
|
|
|
|
Routing - PLUMBING | 6/21/1996 | | 6/24/1996 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/18/1996 | | 6/21/1996 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 6/7/1996 | | 6/17/1996 | | PASS |
|
|
|
CONTACTED SCOTT LUNG AT ###-#### FOR ACHD PICKUP.
|
Plan routing begun/TENANTS | | | 6/7/1996 | | |
|
|
|
Route to Central District Health, Public Works, Plumbing, Mechanical then back to Plan Check. After Plan Check route to Fire Department.
|
Plans ACCEPTED BY PLAN CHECK | | | 6/6/1996 | | |
|
|
|
|
Plans taken to Plan Check | | | 6/5/1996 | | PEND |
|
|
|
|
Application received | | | 6/5/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 6/5/1996 | | |
|
|
|
|
Routing - BUILDING | 7/3/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 6/26/1996 | | | | PEND |
|
|
|
|