Permit Information
Permit NumberBLD96-01506
StatusFinaled
Name NAPA AUTO PARTS STORE
Site Address 3344 W STATE ST
Project NameNAPA AUTO PARTS
Customer Number 
ePlanReviewNo
Description
NAPA AUTO PARTS STORE * TO CONSTRUCT A NEW SINGLE STORY, RETAIL STORE, MANFACTURE METAL BUILDING WITH CONCRETE BLOCK EXTERIOR WALLS, TYPE V-NONRATED CONSTRUCTION. THE PERMIT TO INCLUDE INTERIOR FINISHES AND SITE WORK. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI STANDARDS AND THE 1994 EDITION OF THE UBC. MJP (P.C.#292-96) DR#146-95
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 8/13/19978/13/1997 DONE
Details
Routing for occupancy3/13/19973/13/19978/13/1997 PASS
Art Yingling Insp - Bond for landscaping; sprklr. system; door on dumpster screen; screen A/C/...temp. ($14,811.00). NO FINAL (RELEASE OF BOND) UNTIL GRADING APPROVED BY P.W. CONTACT TERRY RECORDS. 8/97 - All complete - Checked w/ Terry Records - OK/Signed Final
Permanent occupancy  8/13/1997 PASS
Perm. Occ. Cert. #6937 issued 8-13-97 to NAPA Auto Parts.
INSP-Final Inspection4/10/19974/11/19974/11/1997ANR
DetailsJoe Tawney
04/11/97 406 - REINSP FOR FINAL NOT READY
Temporary occupancy  3/14/1997 PASS
Temp. Occ. Cert. #3386 issued 3-14-97 to Napa Auto Parts.
INSP - Final3/11/19973/12/19973/12/1997PPART
DetailsJoe Tawney
03/12/97 406 - OK FOR TEMP OCC EMERG LIGHTS HANDICAP RAMP FRONT EXIT SIGNAGE OVER FRONT DOOR
INSP - Final3/11/19973/12/19973/11/1997PFAIL
Details
03/12/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in2/5/19972/6/19972/6/1997APASS
Details
02/06/97 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in2/3/19972/4/19972/4/1997AFAIL
Details
02/04/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in2/3/19972/3/19972/3/1997PNR
Details
02/03/97 333 - aproved plan not on site
INSP - Masonry12/13/199612/13/199612/13/1996AFAIL
DetailsWes Worcester
NO SPECIAL INSPECTOR ON SITE AND MASON WAS GROUTING CELLS WITH REBAR NOT CENTERED....NO VERIFICATION OF REBAR TIED IN PLACE. NO REPOERTS ON SITE. NO LOG ON SITE. POSTED C/N
INSP - Masonry12/13/199612/13/199612/13/1996AFAIL
DetailsWes Worcester
NO SPECIAL INSPECTION LETTER OR REPORTS..RESPOND W/IN 5 DAYS
INSP - Conference12/13/199612/13/199612/13/1996AFAIL
DetailsWes Worcester
DISCUSSED SPECIAL INSP REQUIREMENT W/MASON AND 5 DAY NOTICE.....GENERAL IN SALT LAKE & WILL BE BACK TUESDAY.
(F) Reprint permit  11/6/1996
INSP - Foundation11/5/199611/5/199611/5/1996PPART
DetailsWes Worcester
11/05/96 342 - placing chairs for cover
INSP - Foundation11/5/199611/5/199611/5/1996 PASS
DetailsWes Worcester
/ / 342 -
Issue PAID IN FULL permit  11/5/1996
INSP - Footings10/31/199610/31/199610/31/1996PPASS
DetailsWes Worcester
10/31/96 342 -
Telephone call  10/24/1996
CALLED MARK GAVE HIM DOLLAR AMOUNT AND TOLD HIM PLANS ARE READY TO BE PICKED UP
Print Pending Permit.LaserJet4  10/24/1996 PASS
Print Occupancy Form  10/24/1996
PLANS/APPL TAKEN TO FRONT DESK  10/24/1996 PASS
Plan Reviewer's activity  10/24/1996 PASS
READY TO ISSUE PERMIT
Inspection Record Card- Bld  10/24/1996
Plan Received by (M_P)8/19/1996 10/24/1996 PASS
DetailsMike Phillips
10/24/96 15:07:39 LMH - this action updated by action script from <<>> in Case No. BLD96-1506
Telephone call  10/23/1996 PEND
TOLD MARK KNOWLES I NEEDED PACKAGE #4. FEES MUST BE PAID AT ACHD PRIOR TO PERMIT ISSUANCE.
Routing - PLUMBING10/22/1996 10/22/1996 PASS
Plan Reviewer's activity  10/22/1996 FAIL
WAITING FOR ADDITIONAL INFORMATION FROM ENGINEER ABOUT BOLTS WHICH ANCHOR CMU WALLS TO COLUMNS.
Routing - FIRE10/22/1996 10/22/1996 PASS
PACKAGE #1
Plan Reviewer's activity  10/22/1996 PEND
RECEIVED REQUESTED INFORMATION FROM ENGINEER ABOUT BOLTING OF CMU WALLS TO COLUMNS. WAITING FOR PLANS TO RETURN FROM PLUMBING.
Routing - BUILDING8/12/1996 10/22/1996 PEND
ROUTING PLANS TO OTHER DEPARTMENTS FOR RESUBMITTAL REVIEW.
90 day tracking............. 6/11/19969/9/1996
Meeting  9/3/1996 PEND
HAD MEETING WITH MARK KNOWLES ABOUT HAZARDOUS MATERIAL LIST
Routing - FIRE8/22/1996 8/26/1996 FAIL
PACKAGE #1
Routing Off Site - STRUCTURAL8/2/1996 8/22/1996 PEND
PACKAGE #3 SENT TO CH2MHILL FOR ENGINEERING VIA PDQ
Plan Reviewer's Copy of Permit  8/21/1996 FAIL
WAITING FOR ENGINEERING REVIEW TO RETURN.
Plan Reviewer's activity  8/21/1996 PEND
WAITING FOR OUTSIDE ENGINEERING REVIEW TO RETURN PRIOR TO ISSUING MY CORRECTION NOTICE.
Unassigned to Plan Reviewer  8/19/1996 PASS
08/19/96 09:31:21 M_P - this action updated by action script from <<>> in Case No. BLD96-1506
Routing - PUBLIC WORKS8/12/1996 8/12/1996 PASS
Routing - PLUMBING7/31/1996 8/2/1996 FAIL
PACKAGE #1 REQUIRES PLUMBING PLAN 8-2-96
Routing - PUBLIC WORKS7/25/1996 7/31/1996 FAIL
PACKAGE #2 NEEDS DRAINAGE PLANS, BRIAN MURPHY.
Routing - PUBLIC WORKS7/31/1996 7/31/1996 FAIL
PACKAGE #2
Routing - ELECTRICAL7/30/1996 7/30/1996 PASS
PACKAGE #1 ELECTRICAL FAILED. RESUBMITTALS REQUIRED. RESUBMITTALS WILL BE FIELD VERIFIED. PER 324. DAR 7/30/96.
Routing - MECHANICAL7/24/1996 7/29/1996 PASS
PACKAGE #1 MECHANICAL NO REVIEW WILL FIELD VERIFY.
Routing - PLANNING7/24/1996 7/25/1996 PASS
PACKAGE #2 X-ref: DR-146-95. Approved by TKW.
Plan routing begun/NEW & ADDTN  7/24/1996 PASS
Received Certificate of Value7/24/1996 7/24/1996
Application received  6/11/1996
Plans taken to Plan Check  6/11/1996
GAY'S RECEIPT FOR PARTIAL PAY  6/11/1996
Routing Off Site - A.C.H.D10/23/1996   PASS
RECEIVED ACHD FEE RECEIPT
Routing - PLAN CHECK10/22/1996   PEND
Routing - PLAN CHECK10/23/1996   PEND
Routing Off Site - STRUCTURAL10/22/1996   PASS
WILL NOT BE ROUTING PLANS BACK FOR OUTSIDE ENGINEERING APPROVAL.
Routing - PLAN CHECK8/27/1996   PEND
Routing - BUILDING7/24/1996   PEND
PACKAGE #3 BEHIND BOB'S DESK
Routing Off Site - A.C.H.D7/24/1996   PEND
contacted mark knowles for achd pickup