BOISE HIGH SCHOOL REMOTE FIELDS AT FORT BOISE * TO CONSTRUCT A NEW 256 SQ.FT. SERVICE BUILDING WITH RESTROOMS AND RELATED PARKING LOT. RECONSTRUCT EXISTING BALLFIELDS AND RELOCATE EXISTING LIGHT POLES AND FIXTURES. PER APPROVED PLANS ON FILE WHICH WERE REVIEWED AND APPROVED BY THE IDAHO DEPARTMENT OF LABOR AND INDUSTRIAL SERVICES. DAR PC #295-96
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval  7/27/1998 DONE
Drainage project found complete 07/27/98. M.Strasser
Permanent Occupancy 10/17/199610/17/1996 DONE
Details
INSP - Permanent occupancy  10/17/1996 PASS
Perm. Occ. Cert. #6639 issued 10-17-96 to the Boise Independent School District for a service bldg.
INSP - Final10/14/199610/15/199610/15/1996ANR
DetailsWes Worcester
10/15/96 342 -
INSP - Final10/14/199610/14/199610/14/1996PPASS
Details
10/14/96 333 - CALL JEFF AT ###-#### FNL -OK FINAL
INSP - Final9/19/19969/19/19969/19/1996PPASS
Details
09/19/96 405 - perm occ approved
INSP - Final9/19/19969/19/19969/19/1996 NR
Details
/ / 405 - not ready
INSP - Framing/Rough-in8/14/19968/16/19968/16/1996PPART
DetailsWes Worcester
ROOF FRAMING. PREFERS 2PM....placing top chord bracing
INSP - Conference8/16/19968/16/19968/16/1996PPASS
DetailsWes Worcester
discussed truss installation and engineering
INSP - Carpentry8/16/19968/16/19968/16/1996PPASS
DetailsWes Worcester
trusses installed correctly...roof ok
INSP - Masonry7/31/19967/31/19967/31/1996PPASS
DetailsWes Worcester
INSP - Footings7/30/19967/30/19967/30/1996PPASS
DetailsWes Worcester
INSP - Conference7/30/19967/30/19967/30/1996PPASS
DetailsWes Worcester
discussed bar placement
INSP - Footings7/30/19967/30/19967/30/1996PNR
DetailsWes Worcester
INSP - Site Preparation7/30/19967/30/19967/30/1996PPASS
DetailsWes Worcester
placing spacers, hanging rebar.. cleaning out loose soil
Plan Received by (M_P)7/15/1996 7/25/1996 PASS
DetailsMike Phillips
07/25/96 07:45:17 DAR - this action updated by action script from <<>> in Case No. BLD96-1568
Print Pending Permit.LaserJet4  7/25/1996 PASS
Permit taken to Permit Desk  7/25/1996 PASS
ISSUE OCCUPANCY FORM  7/25/1996
Issue PAID IN FULL permit  7/25/1996
ISSUE OCCUPANCY FORM  7/25/1996
Inspection Record Card- Bld  7/25/1996
Received Certificate of Value  7/24/1996 PASS
RECEIVED REVISED CERTIFICATE OF VALUE FROM CONTRACTOR (CSDI)
INSP - Miscellaneous  7/23/1996 PEND
TO STATE LABOR INDUSTRIAL SERVICES FOR STAMP.
Routing - ELECTRICAL7/18/1996 7/23/1996 PASS
Routing - BUILDING7/18/1996 7/18/1996 PEND
Routing - FIRE7/16/1996 7/18/1996 PASS
Plan Reviewer's activity  7/15/1996 PEND
Plan Reviewer's Copy of Permit  7/15/1996 PEND
Routing - PUBLIC WORKS7/11/1996 7/12/1996 PASS
Routing - PLANNING7/9/1996 7/11/1996 PASS
Approved by SRS.
Routing - MECHANICAL7/8/1996 7/8/1996 PASS
Routing - MECHANICAL7/8/1996 7/8/1996 PASS
Routing - PUBLIC WORKS7/1/1996 7/5/1996 FAIL
REQUIRES DRAINAGE PLAN KMM
Routing - PLUMBING6/26/1996 7/1/1996 PASS
Routing - PUBLIC WORKS6/20/1996 6/26/1996 FAIL
REQUIRES DRAINAGE PLAN
Routing - PLANNING6/18/1996 6/20/1996 FAIL
A revised site plan is required showing a continuous landscape strip along Robbins Road--between parking lot and street. Reviewed by MH.
Plan routing begun/NEW & ADDTN  6/18/1996 PASS
Received Certificate of Value  6/18/1996 PASS
Routing Off Site - A.C.H.D6/17/1996 6/17/1996 PASS
Application received  6/13/1996
Routing - BUILDING7/8/1996   PEND
Routing - BUILDING7/12/1996   PEND
Plan Received by (DAR)7/22/1996   PASS
PLAN REASSIGNED TO DAR. PLANS WERE APPROVED BY STATE OF IDAHO DEPARTMENT OF LABOR.