Permanent Occupancy | | 8/27/1998 | 8/27/1998 | | DONE |
|
|
|
|
INSP - Final | 8/25/1998 | 8/27/1998 | 8/27/1998 | A | PASS |
Wes Worcester
|
|
|
08/27/98 342 - dominic ###-####
|
Permanent occupancy | | | 8/27/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7381 issued 8-27-98 to Peterson Dental Offices.
|
INSP - Final | 8/26/1998 | 8/26/1998 | 8/26/1998 | P | NR |
Carl Dependahl
|
|
|
will recall
|
INSP - Final | 8/25/1998 | | 8/25/1998 | | NR |
|
|
|
notified dominic, need to call for final
|
Temporary occupancy | | | 8/19/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #7-8-98 to Peterson Dental Ofc.
|
INSP - Final | 8/6/1998 | 8/6/1998 | 8/6/1998 | P | NR |
Carl Dependahl
|
|
|
conf w/ Brian M. of pub wks...signed card, need final walk-thru
|
INSP - Final | 8/5/1998 | 8/5/1998 | 8/5/1998 | A | NR |
Carl Dependahl
|
|
|
need verify pub wks ok for perm. occ.
|
PubWorks Occupancy Approval | | | 7/31/1998 | | DONE |
|
|
|
Drainage project found complete 7/31/98, no inspections. R.Rokovitz
|
Code Occupancy Approval | | | 7/6/1998 | | PASS |
|
|
|
Final Occupancy approved per plans. BOD ok to release.
|
INSP - Final | 5/6/1998 | 5/7/1998 | 5/7/1998 | A | FAIL |
Wes Worcester
|
|
|
05/06/98 342 - need p/w and code enforcement w/bond released.. ###-#### around 9:00
|
INSP - Final | 5/6/1998 | 5/6/1998 | 5/6/1998 | P | NR |
Carl Dependahl
|
|
|
no insp, conf. w/ bldr re c/n...keep cc/n
|
INSP - Final | 5/5/1998 | 5/5/1998 | 5/5/1998 | P | NR |
Carl Dependahl
|
|
|
DOMINIC/###-#### - FINAL. INSP. INCLUDING CONCRETE LANDING. nr, not at site, unable to contact
|
INSP-Final Inspection | 5/5/1998 | 5/5/1998 | 5/5/1998 | P | PASS |
Joe Tawney
|
|
|
05/05/98 406 - DOMINIC/###-#### - RE-INSP ON FINAL FIRE INSP. OK FOR PERM OCC
|
Code Occupancy Approval | | | 5/4/1998 | | TEMP |
|
|
|
Bond posted for the landscape, sprinkler, and plants. $11,660.
|
INSP - Final | 4/30/1998 | 5/1/1998 | 5/1/1998 | A | PART |
Wes Worcester
|
|
|
05/01/98 342 - DOMINIC/###-#### - FINAL.
|
INSP-Final Inspection | 4/30/1998 | 5/1/1998 | 5/1/1998 | A | PART |
Joe Tawney
|
|
|
05/01/98 406 - DOMINIC/###-#### - RE-INSPECTION. REINSP OK FOR TEMP OCC LANDING HAND RAIL
|
Temporary occupancy | | | 5/1/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3601 issued 5-1-98 to Peterson Dental Offices.
|
INSP-Final Inspection | 4/29/1998 | 4/30/1998 | 4/30/1998 | A | FAIL |
Joe Tawney
|
|
|
04/30/98 406 - dominic ###-#### FINAL FAIL DOOR HDWRE, EMERG LIGHTS, ADDRESS, PAINT CURBS, MED GAS REPOR
|
Code Occupancy Approval | | | 4/29/1998 | | PEND |
|
|
|
Requested by: Dominic.
|
INSP-Final Inspection | 4/28/1998 | 4/28/1998 | 4/28/1998 | P | PART |
Joe Tawney
|
|
|
04/28/98 406 - bill simons ###-#### CONF ON MED GAS ROOM AND TESTS FOR SYSTEM
|
INSP - Framing/Rough-in | 3/27/1998 | 3/26/1998 | 3/26/1998 | P | PART |
Carl Dependahl
|
|
|
not insp, conf...need to insp completed draft stop prior to final
|
INSP - Framing/Rough-in | 3/23/1998 | 3/24/1998 | 3/24/1998 | A | PASS |
Wes Worcester
|
|
|
03/24/98 342 - CEILING GRID REINSPECTION DOMINIC ###-####
|
INSP - Framing/Rough-in | 3/19/1998 | 3/19/1998 | 3/19/1998 | A | NR |
Carl Dependahl
|
|
|
unable to chk draft stop, need to remove insul & membrane to observe
|
INSP - Framing/Rough-in | 3/16/1998 | 3/17/1998 | 3/17/1998 | A | PART |
Wes Worcester
|
|
|
03/17/98 342 - ceiling grid-dominic ###-####
|
INSP - Framing/Rough-in | 3/12/1998 | 3/12/1998 | 3/12/1998 | A | NR |
Carl Dependahl
|
|
|
draft stop
|
INSP - Framing/Rough-in | 2/9/1998 | 2/10/1998 | 2/10/1998 | A | PART |
Carl Dependahl
|
|
|
dominic ###-#### fire wall reinspect...dom not onsite, w.i.p.
|
INSP - Carpentry | 2/6/1998 | 2/6/1998 | 2/6/1998 | P | PART |
Carl Dependahl
|
|
|
w/ dom...REC'D ENG'S LETTER RE SHEARWALLS (AND RECOMMENDATION TO LAG MAIN INT WALL TO CRIPPLE WALL...NOT DONE YET) REQ'S STAMP ARCH'S LETTER FOR ROOF CHANGE FROM TILE TO COMP...NEED TO COMPLETE DRAFT STOP, RECOMMEND CONTACT ARCH. FOR DESIGN HELP
|
INSP - Carpentry | 2/5/1998 | 2/5/1998 | 2/5/1998 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [3434445]. w/ dominic Cancelled by Hello! (Last update by [HLO]). Contact: [3434445]. rec'd arch's letter, private stair ok.... fireblocks part ok. ok to continue
|
INSP - Wall cover | 2/5/1998 | 2/5/1998 | 2/5/1998 | | PASS |
Tom Arcoraci
|
|
|
/ / 408 -
|
INSP - Energy code compliance | 2/5/1998 | 2/5/1998 | 2/5/1998 | A | NR |
Carl Dependahl
|
|
|
prearranged dominic ###-####...done by 408, not complete...ok to insulate per Tom
|
INSP - Conference | 2/5/1998 | 2/5/1998 | 2/5/1998 | A | PASS |
Carl Dependahl
|
|
|
w/ wes & supt. re c/n's
|
INSP - Framing/Rough-in | 2/3/1998 | 2/4/1998 | 2/4/1998 | P | FAIL |
Carl Dependahl
|
|
|
peterson dental ###-####...c/n, complete fireblocks; arch to clarify stair use, public or private??...need eng to approve int shear wall install...
|
INSP - Conference | 2/3/1998 | 2/3/1998 | 2/3/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ DOMINIC OF TRADEWINDS RE INSP REQUEST...NEED ARCH. TO ADDRESS SHEAR WALL ISSUES AT INT. FTGS
|
INSP - Framing/Rough-in | 2/2/1998 | 2/3/1998 | 2/3/1998 | A | FAIL |
Wes Worcester
|
|
|
02/03/98 342 - dominic ###-####
|
INSP - Carpentry | 2/2/1998 | 2/2/1998 | 2/2/1998 | A | NR |
Carl Dependahl
|
|
|
NEED ENG'S OK FOR SHEAR WALL INSTALL?...WILL TALK TO BLDR.
|
INSP - Conference | 2/2/1998 | 1/30/1998 | 1/30/1998 | P | PASS |
Carl Dependahl
|
|
|
W/ DOMINIC RE INT FTG/SHEAR WALLS
|
INSP-Sprinkler Rough-in/Hydro | 1/27/1998 | 1/28/1998 | 1/28/1998 | A | PASS |
Joe Tawney
|
|
|
01/28/98 406 - PETERSON DENTAL---DOMINIC AT ###-#### ROUGH IN OF MEDICAL GAS ROOM OK SO FAR
|
INSP-Conference | 1/8/1998 | 1/8/1998 | 1/8/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF ON MEDICAL GAS ROOM VENTILATION
|
INSP - Wall cover | 11/5/1997 | 11/6/1997 | 11/6/1997 | A | PASS |
Wes Worcester
|
|
|
11/06/97 342 -
|
INSP - Foundation | 11/6/1997 | 11/6/1997 | 11/6/1997 | P | PART |
Carl Dependahl
|
|
|
need to verify h-d's, chk underfloor shear walls when ready
|
INSP - Conference | 11/5/1997 | 11/5/1997 | 11/5/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ MIKE OTTO RE PLAN ENG'G.
|
INSP - Conference | 11/5/1997 | 11/5/1997 | 11/5/1997 | A | PASS |
Carl Dependahl
|
|
|
CALLED TED MARTINEZ TO SUGGEST HE DBL CHK HOLD DOWN LOCATIONS AND GET INSP OF INT FTG/SHEARED PONY WALLS.
|
INSP - Footings | 11/5/1997 | 11/5/1997 | 11/5/1997 | P | PART |
Carl Dependahl
|
|
|
DENTAL CLINIC...EXT WALL FTGS. DISCUSSED HOLDOWN LOCATIONS W/ CONC.CONTRACTOR; CALLED TED MARTINEZ.
|
INSP - Footings | 11/4/1997 | 11/5/1997 | 11/5/1997 | A | CANC |
|
|
|
11/05/97 333 - given to carl
|
INSP - Footings | 11/4/1997 | 11/4/1997 | 11/4/1997 | P | PART |
Carl Dependahl
|
|
|
HAS ENG'S SOILS REPORT ONSITE, IN LIEU OF 4" FILL...part, told contractor to check plan, has hold downs & shear walls at found, including cripple walls( h-d's in ftg, shear panels, nailing, etc.) below floor.
|
INSP - Footings | 10/31/1997 | 11/3/1997 | 11/3/1997 | A | NR |
Wes Worcester
|
|
|
11/03/97 342 - no rebar, 4" of compacted base not in, approved plan, eng on site, on fill and organic matter
|
INSP - Conference | 10/17/1997 | 10/17/1997 | 10/17/1997 | P | PASS |
Carl Dependahl
|
|
|
START FUNDING ON THE LOAN-WILL START WORK SOON. UPDATED PERMIT
|
(F) Reprint permit | | | 1/16/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/15/1997 | | |
|
|
|
|
Telephone call | | | 1/6/1997 | | |
|
|
|
TED MARTINEZ CALLED AND SAID PERMIT WOULD BE PICKED UP ON OR BEFORE JAN. 15TH
|
Telephone call | | | 1/6/1997 | | |
|
|
|
TALKED TO TED AT TRADEWINDS, TOLD HIM 180 DAYS FROM SUBMITAL UP, MUST BE PICKED UP RIGHT AWAY OR WILL BE VOIDED AND HAVE TO BE RESUBMITED
|
Telephone call | | | 1/3/1997 | | |
|
|
|
left message on machine, plan must be picked up by end of january of it may be voided, tradewinds
|
(F) Reprint permit | | | 12/13/1996 | | |
|
|
|
|
Telephone call | | | 12/2/1996 | | |
|
|
|
CALLED TRADEWINDS/ REMINDED DOMINIQUE PERMIT READY
|
Telephone call | | | 10/30/1996 | | |
|
|
|
TALKED TO SECRETARY..ASK HER TO HACE TED CALL ME..
|
Print Occupancy Form | | | 10/14/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/14/1996 | | |
|
|
|
|
Telephone call | | | 10/14/1996 | | |
|
|
|
TALKED TO TED..PERMIT READY
|
Print Pending Permit.LaserJet4 | | | 10/11/1996 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/1996 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 7/1/1996 | | 10/11/1996 | | PASS |
|
|
|
CONTACTED JOHN PRICE FOR ACHD PICKUP AT ###-#### PACKAGE #4
|
Plan Received by (M_O) | 7/29/1996 | | 10/11/1996 | | PASS |
|
|
|
corrections mailed and faxed to architect 7-31-96 MO PLANS FROM ACHD RECEIVED 10-11-96.
|
Routing - PLANNING | 10/3/1996 | | 10/7/1996 | | PASS |
|
|
|
PACKAGE #2 X-ref: DR-42-96. Approved by TKW.
|
90 day tracking............. | | 6/28/1996 | 9/26/1996 | | |
|
|
|
|
Routing - FIRE | 8/1/1996 | | 8/2/1996 | | PASS |
|
|
|
PACKAGE #1
|
Plan resubmittals requested | | | 7/31/1996 | | FAIL |
|
|
|
Corrections faxed and sent to architect. MO
|
Unassigned to Plan Reviewer | 6/28/1996 | | 7/29/1996 | | PEND |
|
|
|
PROCESS IMPROVEMENT TEST PROJECT PLANS RECEIVED FOR REVIEW 7-29-96 MO.
|
Routing Off Site - STRUCTURAL | 7/1/1996 | | 7/25/1996 | | FAIL |
|
|
|
PACKAGE #3 SENT TO CH2MHILL ATTENTION CRAIG BARRETT OR MARK BOWEN VIA PDQ. CORRECTIONS RECEIVED 7-26-96 BY HOWIE HENRIKSON P.E. CH2M HILL.
|
Routing - PUBLIC WORKS | 7/19/1996 | | 7/24/1996 | | PASS |
|
|
|
|
Routing - MECHANICAL | 7/9/1996 | | 7/16/1996 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLANNING | 7/8/1996 | | 7/16/1996 | | FAIL |
|
|
|
PACKAGE #2 X-ref: DR-42-96. Need revised plans & forestry approval. Reviewed by TKW.
|
Routing - PLUMBING | 7/1/1996 | | 7/8/1996 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PUBLIC WORKS | 7/1/1996 | | 7/8/1996 | | FAIL |
|
|
|
PACKAGE #2 SITE PLAN SHOULD SHOW SEWER CONNECTION. 7-8-96
|
Routing - ELECTRICAL | 6/28/1996 | | 7/1/1996 | | PASS |
|
|
|
|
Plans taken to Plan Check | | | 6/28/1996 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 6/28/1996 | | PASS |
|
|
|
|
Application received | | | 6/28/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 6/28/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/7/1996 | | | | PEND |
|
|
|
PACKAGE 2 TO PC.
|
Routing - PLAN CHECK | 10/11/1996 | | | | PEND |
|
|
|
PACKAGE #4
|
Routing - BUILDING | 7/16/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 8/5/1996 | | | | PEND |
|
|
|
|