Case Summary (BLD) | | | 8/21/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/24/2001 | | |
|
|
|
|
INSP - Final | 12/4/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
Jim Storey
|
|
|
12/04/96 301 - FNL -OK FINAL
|
INSP - Letter of compliance | | | 12/4/1996 | | PASS |
|
|
|
ISSUED #12368 C OF C BY MJW THIS DATE.
|
INSP - Final | 12/2/1996 | 12/3/1996 | 12/3/1996 | P | FAIL |
Jim Storey
|
|
|
12/03/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED doors to close and latch.
|
INSP-Sprinkler Rough-in/Hydro | 12/2/1996 | 12/3/1996 | 12/3/1996 | A | PASS |
|
|
|
12/03/96 405 - MATT - ###-#### exit door hardware note passed on to storey
|
INSP - Final | 12/3/1996 | 12/3/1996 | 12/3/1996 | | PASS |
|
|
|
/ / 405 - exit door has thumbturn
|
INSP - Final | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | CANC |
Jim Storey
|
|
|
11/25/96 301 - cancled by contractor.
|
INSP - Framing/Rough-in | 10/15/1996 | 10/15/1996 | 10/15/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
Meeting | | | 10/15/1996 | | PASS |
|
|
|
MEETING WITH THE CONTRACTORS:::: WE HAVE CHANGED THE STATUS OF THIS BUILDING TO A TYPE III-1hr WITH FIRE SPRINKLER SUBSTITUTION.
|
Inspector's copy Bld permit | | | 10/15/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 10/10/1996 | 10/10/1996 | 10/10/1996 | P | FAIL |
Jim Storey
|
|
|
10/10/96 301 - FIRE CORRIDORS CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
90 day tracking............. | | 7/12/1996 | 10/10/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 9/26/1996 | 9/27/1996 | 9/27/1996 | A | PASS |
Jim Storey
|
|
|
09/26/96 301 - FRAM-OK FRAMING vestabul only.
|
INSP - Footings | 9/17/1996 | 9/17/1996 | 9/17/1996 | P | PASS |
Jim Storey
|
|
|
09/17/96 301 - FRMS-OK FORMS-REBAR
|
INSP - Foundation | 9/17/1996 | 9/17/1996 | 9/17/1996 | P | PASS |
Jim Storey
|
|
|
09/17/96 301 - FDN -OK FOUNDATION
|
Issue PAID IN FULL permit | | | 9/3/1996 | | |
|
|
|
|
Received Certificate of Value | | | 8/30/1996 | | PASS |
|
|
|
|
Print Occupancy Form | | | 8/30/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/30/1996 | | PASS |
|
|
|
|
Plan Received by (RGG) | 8/20/1996 | | 8/27/1996 | | PASS |
|
|
|
SEE PC #360-96 Note! This building is fully fire sprinklered and is a type III-1hr. building, three story with basement. Built in 1979.
|
Unassigned to Plan Reviewer | 7/12/1996 | | 8/20/1996 | | PASS |
|
|
|
08/20/96 13:39:04 RGG - this action updated by action script from <<>> in Case No. BLD96-1859
|
Routing - PUBLIC WORKS | 7/16/1996 | | 7/18/1996 | | PASS |
|
|
|
|
Routing - PLANNING | 7/15/1996 | | 7/15/1996 | | PASS |
|
|
|
Approved by SRS.
|
Plan routing begun/NEW & ADDTN | | | 7/15/1996 | | PASS |
|
|
|
|
Received Certificate of Value | | | 7/15/1996 | | PASS |
|
|
|
|
Application received | | | 7/12/1996 | | |
|
|
|
|
Plans taken to Plan Check | | | 7/12/1996 | | |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 7/12/1996 | | |
|
|
|
|
Routing - BUILDING | 7/18/1996 | | | | PEND |
|
|
|
|