Permit Information
Permit NumberBLD96-01992
StatusFinaled
Name DURR MEDICAL
Site Address 300 N SAILFISH PL
Project Name 
Customer Number 
ePlanReviewNo
Description
DURR MEDICAL SUPPLY WAREHOUSE * TO CONSTRUCT A NEW 28,773 SQ.FT. TWO STORY CONCRETE TILT-UP TYPE II-NONRATED, FIRE SPRINKLERED FOR AREA INCREASE, OFFICE/WAREHOUSE BUILDING. THE SECOND FLOOR IS APPROXIMATELY 3,751 SQ.FT.,680 SQ.FT. OF THE AREA IS FINISHED OFFICE SPACE THE REMAINING AREA WILL BE FINISHED AT A FUTURE DATE. THE FIRST FLOOR IS APPROXIMATELY 25.022 SQ.FT, 20,520 IS WAREHOUSE AREA. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI STANDARDS AND THE 1994 EDITION OF THE UBC, PERMIT TO INCLUDE RELATED SITE IMPROVEMENTS. MJP (PC#401-96) DR#23-96
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  5/22/2003  
Permanent Occupancy 4/11/19974/11/1997 DONE
Details
Permanent occupancy  4/11/1997 PASS
Perm. Occ. Cert. #6832 issued 4-11-97 to Durr Medical Supply Warehouse.
Routing for occupancy4/9/19974/9/19974/9/1997 PASS
Art Yingling - insp. for final- complies w/DR-23-96.
INSP - Final3/24/19973/24/19973/24/1997 PASS
DetailsJoe Tawney
/ / 406 - FINAL REINSP OK FOR PERM OCC
Routing for occupancy3/21/19973/21/19973/21/1997 TEMP
AY insp. - Bonded for Landscaping/CC for $900. rec'd. - signed temporary
INSP - Final3/20/19973/20/19973/20/1997PNR
DetailsJoe Tawney
03/20/97 406 - 3 p.m. NOT READY FOR INSPECTION
INSP - Final3/21/19973/21/19973/19/1997PFAIL
Details
03/21/97 338 - OTH-OTHER AGENCIES NOT APPROVED fire & p/z required
INSP-Sprinkler Rough-in/Hydro3/17/19973/19/19973/19/1997PNR
DetailsJoe Tawney
03/19/97 406 - FINAL INSP NOT READY
INSP-Sprinkler Rough-in/Hydro3/17/19973/17/19973/17/1997 PART
DetailsJoe Tawney
/ / 406 - OK ON SPKLR HYDRO TEST
INSP - Conference3/13/19973/13/19973/13/1997PPASS
DetailsJoe Tawney
03/13/97 406 - DAN ###-#### PRE FINAL CONF DISCUSSED EXITS, SIGNS,HDWRE, EXTINGUISHERS. ALSO EMERG LIGHTS NOTED FDC TOO CLOSE TO WALL MTD CONTROL VLV
INSP - Conference3/12/19973/13/19973/12/1997PPASS
Details
03/13/97 338 - made ok
INSP-Supply line flush2/27/19972/28/19972/28/1997APART
DetailsJoe Tawney
02/28/97 406 - OK ON UNDERGROUND FLUSH
INSP - Framing/Rough-in2/19/19972/19/19972/19/1997PNR
Details
02/19/97 338 - rescheduled til tomorrow a.m.
INSP - Framing/ Rough-in2/19/19972/19/19972/19/1997 NR
Details
/ / 338 - str is ok but ele and plmg ae not signed off
INSP - Framing/Rough-in1/24/19971/27/19971/26/1997APASS
Details
01/27/97 338 - ROOF FRAMING FOR THE SECOND FLOORING MADE OK STILL PUD DECK CONNECTIONS
INSP - Conference1/26/19971/26/19971/26/1997 NR
Details
/ / 338 - NOT READY CALLED TO POST PONE THE INSP
INSP - Flatwork1/2/19971/3/19971/1/1997APASS
Details
01/03/97 338 - PANEL ERRECTIONS making good progress with special inspec
INSP - Masonry12/16/199612/16/199612/16/1996PPASS
Details
12/16/96 333 - CONCRETE INSP...PANELS #24 - 25 - 2I6 & 4 STRUCTURAL COLUMNS....... special insp ok
INSP - Wall cover12/11/199612/12/199612/12/1996APASS
Details
12/12/96 338 - STRUC. CONCRETE/PANEL 27,28,31,32,33,34,35, special insp
INSP - Masonry11/25/199611/25/199611/25/1996PPASS
Details
11/25/96 338 - STRUCTURAL PANEL 13 THRU 23
INSP - Flatwork11/12/199611/13/199611/13/1996APASS
Details
11/13/96 338 - WALL PANELS 1 THRU 12
90 day tracking............. 7/30/199610/28/1996
INSP - Footings10/22/199610/22/199610/22/1996PPASS
Details
10/22/96 338 - madeok r-bar placed in the first 3/4 of the footing area. special insp continuous during the pour
INSP - Footings10/18/199610/18/199610/21/1996ANR
Details
10/18/96 338 -
INSP - Conference10/14/199610/15/199610/15/1996APASS
Details
10/15/96 338 - APPROX 9AM? (BRIAN AT ###-####)
(F) Reprint permit  10/3/1996
Issue PAID IN FULL permit  10/2/1996
Plan assigned to (M_P)8/29/1996 10/1/1996 PASS
DetailsMike Phillips
10/01/96 10:20:49 KMM - this action updated by action script from <<>> in Case No. BLD96-1992
Print Occupancy Form  10/1/1996
Inspection Record Card- Bld  10/1/1996
PLANS/APPL TAKEN TO FRONT DESK  10/1/1996 PASS
Print Pending Permit.LaserJet4  10/1/1996 PASS
Plan Reviewer's activity  10/1/1996 PASS
Routing - PUBLIC WORKS9/27/1996 9/30/1996 PASS
Plan Reviewer's activity  9/27/1996 PEND
waiting for approval from public works
Routing - MECHANICAL9/24/1996 9/25/1996 PASS
PACKAGE #1 RETURNED FROM MECHANICAL
Plan resubmittals received  9/24/1996 PASS
MECH. RESUBS. RECEIVED AND SENT TO MECH. KMM
Routing - PLANNING9/12/1996 9/23/1996 PASS
X-ref: DR-23-96. Approved by MS.
Routing - MECHANICAL9/13/1996 9/20/1996 FAIL
Routing - FIRE9/13/1996 9/13/1996 PASS
Routing Off Site - A.C.H.D8/1/1996 9/13/1996 HOLD
PACKAGE #4 ON HOLD WAITING FOR SHEETS C2 AND C3 TAKEN OFF HOLD. RECEIVED SHEETS C2 AND C3 07-31-96 AFTERNOON. KMM. ACHD FEES NOT PAID.
Routing - PUBLIC WORKS9/5/1996 9/12/1996 FAIL
Routing - FIRE9/10/1996 9/10/1996 FAIL
Routing - PLUMBING9/4/1996 9/6/1996 PASS
Print Pending Permit.LaserJet4  9/3/1996 FAIL
Plan Reviewer's activity  9/3/1996 FAIL
SENT CORRECTION REPORT
Routing - PLANNING8/8/1996 8/29/1996 FAIL
PACKAGE #2 Need revised landscape plans prior to issuance of building permit. (contacted applicant w/phone call & letter) See DR-23-96. NOTE: I was holding plans in anticipation that Briggs would be forwarding plans; However, they have not, and therefore the plans should be routed to other agencies. Reviewed by MS.
Plan resubmittals received  8/27/1996 PASS
PACKAGE #1 PLUMBING RESUB. RECEIVED. PUT WITH PACKAGE #1 AND SENT TO PLUMBING. KMM PACKAGE #2 PLUMBING RESUB. RECEIVED. PUT BEHIND BOB'S DESK. WAITING FOR PACKAGE #2 TO GET BACK FROM P&Z. KMM
Routing - ELECTRICAL8/15/1996 8/19/1996 PASS
Plan resubmittals received  8/15/1996 PASS
ELECTRICAL SHEETS E-1 THRU E-5 RECEIVED
Routing - PUBLIC WORKS8/1/1996 8/8/1996 FAIL
PACKAGE #2 REQUIRES DRAINAGE PLAN 08-08-96 PACKAGE #2 WENT BACK TO P.W. ON 08-05-96
Routing - ELECTRICAL8/6/1996 8/7/1996 FAIL
PACKAGE #1 RETURN PLANS TO JIM SCHMER WHEN RECEIVE RESUBMITTALS FOR ELECTRICAL. KMM
Routing - PLUMBING8/5/1996 8/6/1996 FAIL
PACKAGE #1
Routing - MECHANICAL7/31/1996 8/5/1996 FAIL
PACKAGE #1
Received Certificate of Value7/31/1996 7/31/1996 PASS
Plan routing begun/NEW & ADDTN7/31/1996 7/31/1996 HOLD
PACKAGES #2, 3, ON HOLD. WAITING FOR SHEETS C3 AND C4 FROM WESLEY STEELE.
Plan routing begun/NEW & ADDTN  7/31/1996 PASS
PACKAGE #1 PACKAGE #2
Application received  7/30/1996
GAY'S RECEIPT FOR PARTIAL PAY  7/30/1996
Routing - PLAN CHECK9/6/1996   PEND
PACKAGE 1
Routing - PLAN CHECK8/29/1996   PEND
PACKAGE #2 SENT TO MIKE P.
Routing - PLAN CHECK9/11/1996   PEND
Routing - PLAN CHECK9/30/1996   PEND
Routing Off Site - STRUCTURAL9/24/1996   PASS
STRUCTURAL REVIEW COMPLETE AND APPROVED PER ENCLOSED LETTER FROM ATWOOD-HINZMAN-JONES
Routing Off Site - A.C.H.D9/27/1996   PASS
ACHD FEES PAID RECEIPT # 960902
Routing - PLAN CHECK9/24/1996   PEND
PACKAGE #2 TO MIKE PHILLIPS 9/24/96 DAR
Routing - PLAN CHECK9/20/1996  
Routing - BUILDING8/7/1996   PEND
PACKAGE #1
Unassigned to Plan Reviewer7/30/1996  
Routing Off Site - STRUCTURAL8/7/1996   PEND
PACKAGE #3 ON HOLD BEHIND BOB'S DESK. TAKEN OFF HOLD 8-7-96. SENT TO ATWOOD, HINZMAN, AND JONES FOR ENGINEERING VIA PDQ.
Routing - BUILDING8/19/1996   PEND