INSP - Letter of compliance | | | 12/19/1996 | | PASS |
|
|
|
ISSUED #12384 C OF C BY 301 THIS DATE.
|
INSP - Final | 12/18/1996 | 12/18/1996 | 12/18/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL
|
INSP - Final | 12/17/1996 | 12/18/1996 | 12/18/1996 | P | PASS |
|
|
|
|
INSP - Fire Dept. Request | 12/6/1996 | 12/6/1996 | 12/6/1996 | | PASS |
|
|
|
/ / 405 - sprinkler relo rough in
|
INSP - Framing/Rough-in | 11/25/1996 | 11/26/1996 | 11/26/1996 | A | NR |
Jim Storey
|
|
|
11/25/96 301 - OTH-OTHER AGENCIES NOT APPROVED ele n/r
|
(F) Reprint permit | | | 11/25/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 11/12/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Jim Storey
|
|
|
11/12/96 301 - FRAM-OK FRAMING Fweld & STRUCTURAL WELDING ok 1/4 bo plates
|
90 day tracking............. | | 7/30/1996 | 10/28/1996 | | |
|
|
|
|
INSP - Foundation | 10/21/1996 | 10/22/1996 | 10/22/1996 | A | PASS |
Jim Storey
|
|
|
10/21/96 301 - FND.REBAR. GATE 54..EARLY A.M. FDN -OK FOUNDATION
|
INSP - Footings | 10/18/1996 | 10/18/1996 | 10/18/1996 | P | PEND |
Jim Storey
|
|
|
MAKE A U-TURN BY TOWER AND YOU WILL BE THERE PENDING S.I. REPORT
|
INSP - Conference | 10/11/1996 | 10/14/1996 | 10/14/1996 | A | PASS |
Jim Storey
|
|
|
10/12/96 301 - PRE-CONSTRUCTION INSPECTION GEN -GENERAL INSPECTION WORK ON EXAVATION IN PROGESS
|
Issue PAID IN FULL permit | | | 10/7/1996 | | |
|
|
|
|
Telephone call | | | 10/4/1996 | | |
|
|
|
CALLED CUSTOMER TO LET THEM KNOW PLANS ARE READY
|
Print Occupancy Form | | | 10/4/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/4/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/1996 | | PASS |
|
|
|
|
Received Certificate of Value | | | 10/4/1996 | | |
|
|
|
|
Plan assigned to (CJW) | 8/23/1996 | | 10/4/1996 | | PASS |
Carl Westfall
|
|
|
10/04/96 15:36:50 CJW - this action updated by action script from <<>> in Case No. BLD96-2007
|
Plan Reviewer's activity | | | 10/3/1996 | | PASS |
|
|
|
Drawings approved October 3, 1996 after resubmittal was approved and modification to guardrail height provisions was approved by Tim Hogland, Building Director.
|
Plan resubmittals received | | | 9/16/1996 | | |
|
|
|
Resubmittal received. Drawings approved on October 3, 1996.
|
Routing - FIRE | 9/4/1996 | | 9/10/1996 | | PASS |
|
|
|
|
Routing - PLANNING | 9/4/1996 | | 9/3/1996 | | PASS |
|
|
|
Approved by TKW. X-ref: ZC @ 3201 Airport Way
|
Telephone call | 8/28/1996 | | 8/28/1996 | | |
|
|
|
|
Plan resubmittals requested | 8/28/1996 | | 8/28/1996 | | |
|
|
|
Sent plan chect report to the architect. See "Conditions" for items that require a response.
|
Routing - PLAN CHECK | 8/26/1996 | | 8/28/1996 | | |
|
|
|
Waiting for architect's response. Drawings approved on October 3, 1996 after modification of guardrail provisions by Tim Hogland,
|
Plans ACCEPTED BY PLAN CHECK | | | 7/31/1996 | | |
|
|
|
|
Plan routing begun/TENANTS | | | 7/31/1996 | | |
|
|
|
This plan to be reviewed by Plan Check and the Fire Department.
|
Application received | | | 7/30/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 9/10/1996 | | | | PEND |
|
|
|
|