Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD96-02049
StatusFinaled
Name OROWHEAT FOODS OF BOISE
Site Address 2903 W IDAHO ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To remodel an existing 7,140 sq.ft. building for wholesale bakery per approved plans on file. Work to include demolition of interior partition walls in the restroom/dressing room area and removal of plumbing fixtures then installing a new door, infilling wall openings and installing new plumbing fixtures to create a new accessible rest room, build a new handicap ramp to the 29th Street door, upgrading the entrance door, landing, and glazing to CABO/ANSI REQUIREMENTS. (P.C.#425-96). A NEW CERTIFICATE OF OCCUPANCY IS REQUIRED PRIOR TO THIS TENANT OCCUPYING THIS BUILDING. PRP
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 10/31/199710/31/1997 DONE
Details
Permanent occupancy  10/31/1997 PASS
Perm. Occ. Cert. #7040 issued 10-31-97 to the Alpicella Bakery.
INSP - Final2/18/19972/19/19972/18/1997APASS
Details
02/19/97 333 - signed for perm
90 day tracking............. 8/2/199610/31/1996
INSP - Final10/18/199610/18/199610/18/1996PPART
DetailsWes Worcester
FINAL REINSPECT Temp ok, working on handrail
INSP - Framing/Rough-in10/14/199610/15/199610/15/1996APASS
DetailsWes Worcester
10/15/96 342 -
INSP - Final10/10/199610/11/199610/11/1996AFAIL
Details
10/11/96 333 - OTH-OTHER AGENCIES NOT APPROVED
Plan assigned to (PRP)9/11/1996 9/17/1996 PASS
Details
RECEIVED TWO PLANS, OROWHEAT BAKERY, FOR REVIEW 09/17/96 08:52:24 PRP - this action updated by action script from <<>> in Case No. BLD96-2049
Plan assigned to (PRP)8/5/1996 9/17/1996 PASS
Details
09/17/96 08:52:24 PRP - this action updated by action script from <<>> in Case No. BLD96-2049
PLANS/APPL TAKEN TO FRONT DESK  9/17/1996 PASS
issue
Inspection Record Card- Bld  9/17/1996
Print Occupancy Form  9/17/1996
Issue PAID IN FULL permit  9/17/1996
Plan resubmittals received9/17/1996 9/17/1996
Received Certificate of Value9/17/1996 9/17/1996
Routing - FIRE9/11/1996 9/16/1996 PASS
Waiting for Cert. of Value9/11/1996 9/11/1996
Plan resubmittals requested9/11/1996 9/11/1996
Print Pending Permit.LaserJet4  9/11/1996 PEND
files
Plan Reviewer's activity  9/11/1996 PEND
review plans, prepare corrections, review history, fax corrections to Arch, talk with owner about corrections, forward to Fire.
Routing - MECHANICAL8/15/1996 9/3/1996 PASS
Routing - PUBLIC WORKS8/9/1916 8/15/1996 PASS
Routing Off Site - C.D.H8/6/1996 8/9/1996 PASS
CONTACTED DAN PERATA AT ###-#### FOR CDH PICKUP.
Plan routing begun/TENANTS  8/5/1996
Route to Central District Health, Public Works, and Mechanical then back to Plan Check. After Plan Check route to Fire Department.
Plans ACCEPTED BY PLAN CHECK  8/5/1996 PASS
Plans taken to Plan Check  8/2/1996
Application received  8/2/1996
GAY'S RECEIPT FOR PARTIAL PAY  8/2/1996
Routing - PLAN CHECK9/3/1996   PEND
Routing - PLAN CHECK9/16/1996   PEND
Unassigned to Plan Reviewer8/2/1996