Permanent occupancy | | | 8/1/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6935 issued 8-1-97 to Columbia Village Elementary School.
|
INSP - Final | 7/30/1997 | 7/30/1997 | 7/30/1997 | P | PASS |
Bob Archibald
|
|
|
cn made ok
|
Permanent Occupancy | | 7/30/1997 | 7/30/1997 | | DONE |
|
|
|
|
INSP - Final | 7/24/1997 | 7/25/1997 | 7/25/1997 | A | FAIL |
Jim Storey
|
|
|
07/25/97 301 - c/n pending for occ. doors in gym
|
INSP-Final Inspection | 7/7/1997 | 7/10/1997 | 7/10/1997 | A | FAIL |
|
|
|
alarms still not zoned , air pressure monitor not wired correctly
|
INSP - Conference | 7/8/1997 | 7/8/1997 | 7/8/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - dead bolts on exit doors of restrooms approved by state of i and as per architect drawings in spec. book submitted.
|
INSP-Sprinkler Rough-in/Hydro | 7/1/1997 | 7/2/1997 | 7/2/1997 | A | PASS |
Joe Tawney
|
|
|
07/01/97 406 - AT 9 A.M. WITNESTED TRIP TESTS OF 2 DP SYSTEMS AFTER SPLIT OF 1 SYST EACH SYST NOW LESS THAN 750 GAL. ALSO PICKED UP REVISED PLANS AND REV CA
|
INSP-Final Inspection | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | FAIL |
|
|
|
TIME GOT WORSE, 1:30 TO 2:00.....ALARMS STILL NOT COMPLETE
|
INSP-Final Inspection | 6/13/1997 | 6/13/1997 | 6/13/1997 | P | FAIL |
|
|
|
sprinklers failed 60 sec test (75). alll signals are alarm, low air not set, need as builts for docs
|
INSP - Conference | 6/10/1997 | 6/10/1997 | 6/10/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - NWP -GENERAL INSPECTION - NO WORK IN PROGRESS
|
INSP-Sprinkler Rough-in/Hydro | 6/6/1997 | 6/6/1997 | 6/6/1997 | P | PASS |
|
|
|
HYDRO on above ground
|
INSP-Conference | 4/15/1997 | 4/15/1997 | 4/15/1997 | A | PASS |
|
|
|
meet w/ power plus, TED, DISCUSSED DUCT DETECTOR LOCATIONS, TOLD REMOTE INDICATORS WILL BE REQUIRED, TOLD TO MOVE SMOKE DETECTORS TO WITHIN 5 FT OF DOORS ON HOLD OPENS. LOOKED AT PLANS, TOLD WILL NEED AS BUILTS WITH ALL CALCULATIONS FOR FINAL
|
INSP-Sprinkler Rough-in/Hydro | 4/2/1997 | 4/3/1997 | 4/3/1997 | A | PART |
|
|
|
underground hydro ok
|
INSP-Supply line flush | 4/2/1997 | 4/3/1997 | 4/3/1997 | A | PASS |
|
|
|
8:30 am, FEW ROCKS, FAIRLY CLEAN, GOOD FLOW
|
INSP-Sprinkler Rough-in/Hydro | 3/27/1997 | 3/27/1997 | 3/27/1997 | A | PART |
|
|
|
hallway coverage, overbuilds along halls completed, media center complete, only place lacking is overbuilds at each corner of meia center away from gym
|
INSP-Conference | 3/21/1997 | 3/21/1997 | 3/21/1997 | A | PART |
|
|
|
phone conf w/ gus, CM. Mel Fletcher wants ceiling space above halls sprinkled since actual gap is 8" instead of 6" in many places. Will discuss w/ Fetcher. Plans called for 6" but sprinkler main and ML beams forced to 8".
|
INSP - Ceiling grid | 3/18/1997 | 3/19/1997 | 3/19/1997 | A | PART |
Jim Storey
|
|
|
03/19/97 301 - SCLG-OK SUSPENDED CEILING
|
INSP-Sprinkler Rough-in/Hydro | 3/19/1997 | 3/18/1997 | 3/18/1997 | P | PASS |
|
|
|
approved plan to sprinkle exposed comb const above media center w/ heads along walls only
|
INSP-Sprinkler Rough-in/Hydro | 3/17/1997 | 3/17/1997 | 3/17/1997 | A | PASS |
|
|
|
check media center exposed combustible construction, concealed space, need to extend foil wrap or sprinkle. hall lid ok using 96 nfpa 13 w/ new exceptions
|
INSP - Ceiling grid | 3/10/1997 | 3/11/1997 | 3/11/1997 | A | PART |
Jim Storey
|
|
|
03/11/97 301 - SCLG-OK SUSPENDED CEILING south wing
|
INSP-Sprinkler Rough-in/Hydro | 2/19/1997 | 2/20/1997 | 2/20/1997 | A | PART |
|
|
|
issued c/n on MECHANICAL SPACE ABOVE KITCHEN. and RISER Access issues
|
INSP-Conference | 2/14/1997 | 2/14/1997 | 2/14/1997 | P | PART |
|
|
|
CONF ON RISER LOCATION OPTIONS
|
INSP-Sprinkler Rough-in/Hydro | 2/12/1997 | 2/13/1997 | 2/13/1997 | A | PART |
|
|
|
ROUGH IN CAFETERIA AND GYM, PROBLEM WITH RISER ROOM LOCATION
|
INSP - Framing/Rough-in | 1/29/1997 | 1/30/1997 | 1/30/1997 | A | PASS |
Jim Storey
|
|
|
01/30/97 301 - FRAM-OK FRAMING OCC SEPECTION
|
INSP-Sprinkler Rough-in/Hydro | 1/24/1997 | 1/28/1997 | 1/29/1997 | P | PART |
|
|
|
AREAS E & F ok to cover 1st floor w/ conditions for access to areas not complete...c/n with condition noted
|
INSP - Framing/Rough-in | 1/17/1997 | 1/21/1997 | 1/21/1997 | A | PASS |
Jim Storey
|
|
|
01/21/97 301 - C WING OK
|
INSP - Wall cover | 1/15/1997 | 1/15/1997 | 1/15/1997 | P | PASS |
Jim Storey
|
|
|
01/15/97 301 - roof nailling at gym roof and fire rated ply in place as
|
INSP - Framing/Rough-in | 1/8/1997 | 1/9/1997 | 1/9/1997 | A | PART |
Jim Storey
|
|
|
01/09/97 301 - conf. re insp. for 1/10/97
|
INSP - Roof | 1/2/1997 | 1/3/1997 | 1/3/1997 | A | PART |
Wes Worcester
|
|
|
will finish this pm
|
INSP - Roof | 12/31/1996 | 12/31/1996 | 12/31/1996 | A | PART |
Wes Worcester
|
|
|
East and Northeast roof sections ok
|
INSP - Roof | 12/30/1996 | 12/30/1996 | 12/30/1996 | P | NR |
Wes Worcester
|
|
|
still putting on roof....will walk Tues am
|
INSP - Roof | 12/27/1996 | 12/30/1996 | 12/30/1996 | A | NR |
Wes Worcester
|
|
|
ROOF NAILING said he called for pm....will reschedule
|
INSP - Conference | 11/22/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
Wes Worcester
|
|
|
picked up address and permit #
|
INSP - Conference | 11/21/1996 | 11/21/1900 | 11/21/1996 | | FAIL |
|
|
|
conference w/Bob & George @ earlier conversation w/Gus
|
INSP - Conference | 11/14/1996 | 11/14/1996 | 11/14/1996 | | FAIL |
|
|
|
super had stated that he would call in w/approximate time and place for next lift and a conference for coordination
|
INSP - Conference | 11/12/1996 | 11/12/1996 | 11/12/1996 | | PART |
|
|
|
stopped in again to get on scheduled lifts and so we could make computer entries to coincide w/progress
|
INSP - Masonry | 11/6/1996 | 11/6/1996 | 11/6/1996 | | NR |
|
|
|
stopped by to look at project, not plaving grout at that time, asked super to call in for conference.
|
INSP - Flatwork | 10/28/1996 | 10/28/1996 | 10/28/1996 | | FAIL |
|
|
|
notified super that mesh was not being imbedded in concrete. Special insp was reg'd according to super as pour was 3000 + concrete
|
INSP - Conference | 10/15/1996 | 10/15/1996 | 10/15/1996 | | PASS |
|
|
|
/ / 405 - issued letter on requirements
|
INSP - Conference | 10/14/1996 | 10/14/1996 | 10/14/1996 | | PASS |
|
|
|
/ / 405 - discussed alarm and sprinkler requirements for project
|
Meeting | | | 8/28/1996 | | PASS |
|
|
|
In a meeting with Bob Garrison, it was discussed that this plan was reviewed by Ken Hartell, DLIS, State of Idaho. As agreed on with the Director on many occasions, School Building projects reviewed by the State of Idaho would be constructed as per the approved plans.
|
(F) Reprint permit | | | 8/28/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/27/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/1996 | | |
|
|
|
|
Print Occupancy Form | | | 8/23/1996 | | |
|
|
|
|
Inspector's copy Bld permit | | | 8/23/1996 | | |
|
|
|
|
Application received | | | 8/23/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 8/23/1996 | | NA |
|
|
|
THE BUILDING AS DESIGNED IS IN VIOLATION OF THE BUILDING CODE FOR ALLOWED AREA, SEE SHEET AO.1 OF THE PLANS. THIS PROJECT AS SUBMITTED HAS BEEN ACCEPTED BY THE CITY BUILDING DEPARTMENT PER DAVID HATTRICK ON THIS DATE 08/23/96.
|
INSP-Final Inspection | 7/24/1997 | 7/24/1997 | 7/24/1996 | A | PASS |
|
|
|
alarms completed-main bldg
|
Unassigned to Plan Reviewer | | | | | |
|
|
|
|