Information based on query as of Saturday, July 20, 2024.
Permit Information
Permit NumberBLD96-02302
StatusFinaled
Name ST. ALPHONSUS MED. OFF.BLD.#5
Site Address 900 N LIBERTY
Project NameST ALS OFFICE #5
Customer Number 
ePlanReviewNo
Description
( ST. ALPHONSUS MEDICAL OFFICE BUILDING #5 - SHELL AND CORE ) TO CONSTRUCT A NEW 57,540 SQ. FT., FOUR STORY, STEEL FRAMED OFFICE BUILDING WITH CONCRETE FLOOR DECKS AND METAL STUD EXTERIOR WALLS WITH EXTERIOR INSULATION FINISH SYSTEM. THIS BUILDING WILL BE FULLY FIRE SPRINKLED. THIS PERMIT IS TO COMPLETE THE SHELL AND CORE ONLY. THERE WILL BE NO OCCUPANCY PERMITTED UNDER THIS PERMIT. SEPARATE TENANT IMPROVEMENT PERMITS WILL BE REQUIRED TO FINISH THIS BUILDING. THIS PERMIT WILL ALSO INCLUDE RELATED SITE IMPROVEMENTS. ALL CONSTRUTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR#97-96/CU#-51-96/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled2/7/20012/7/20012/7/2001PPASS
DetailsTom Arcoraci
Added by Inspector: 408 On 2/7/2001 4:24:02 PM
INSP - Final11/16/199811/17/199811/17/1998APASS
Details
11/17/98 338 - MADE OK L/C ISSUED # 015891
INSP - Final11/17/199811/17/199811/17/1998 PASS
Details
/ / 338 - MADE OK FOR FINAL, SIGNED THE PERM COL OF THE OCC REQ CARD A
INSP - Final11/17/199811/17/199811/17/1998 PASS
Details
/ / 338 - MADE OK FOR FINAL, SIGNED THE PERM COL OF THE OCC REQ CARD A
INSP-Final Inspection11/16/199811/16/199811/16/1998PPASS
DetailsJoe Tawney
11/16/98 406 - ###-#### cecil sched. at 1:30 REINSP OK FOR CERT OF COMPL ON SHELL
INSP-Final Inspection10/29/199810/29/199810/29/1998 FAIL
DetailsJoe Tawney
10/29/98 406 - CECIL- ###-#### FN FIRE-PER JOE WILL MEET AT 8 REINSP FAIL ALARM SYSTEM PACKAGE & NFPA 72
INSP - Occup. violation notice10/12/199810/12/199810/12/1998 FAIL
Details
/ / 338 - RECIEVED BY FRED A HOWE FOR KREISENBECK CECIL CALLED LATER T
Temporary occupancy  11/17/1997 PASS
Temp. Occ. Cert. #3504 issued 11-17-97 to St. Al's #5 for the shell and core.
INSP-Final Inspection11/5/199711/6/199711/6/1997APART
DetailsJoe Tawney
11/06/97 406 - REIN OK FOR TEMP OCC ON SHELL ALARM SUBMITTAL FRT ELEVATOR GEN TIME DELAY
INSP - Final11/6/199711/6/199711/6/1997PPART
Details
11/06/97 333 - temp ok
INSP-Final Inspection11/3/199711/4/199711/4/1997PFAIL
DetailsJoe Tawney
11/04/97 406 - FINAL NOT COMPLETED RESUME 11/5/97
Routing for occupancy11/3/1997 10/31/1997 PASS
Approved by: Carol A. Montgomery (DR-97-96).
INSP-Final Inspection10/28/199710/30/199710/30/1997ANR
DetailsJoe Tawney
10/30/97 406 - FINAL NOT READY DIG DIALER NOT INSTALLED
INSP - Framing/Rough-in10/23/199710/24/199710/24/1997PPART
Details
CEILING GRID made ok
INSP - Framing/Rough-in10/17/199710/20/199710/20/1997APART
Details
CEILING GRID AND FIRE PENETRATION verbal corrections written down on the on prelim punch lists.
INSP-Sprinkler Rough-in/Hydro10/2/199710/2/199710/2/1997PPART
DetailsJoe Tawney
10/02/97 406 - st. als/ bld #5 OK ON HYDRO TEST FOR SPKLR SYSTEM STILL NEED HYDRO TEST ON STANDPIPES
INSP - Conference9/3/19979/3/19979/3/1997 PASS
Details
/ / 338 - ok to use 2'-8" door from the first floor lobby to the north a required exit door will be market NOT AN EXIT
Plan resubmittals received  8/19/1997 PEND
RECEIVED PROPOSAL REQUEST #6 FROM KREIZENBECK CONSTRUCTORS, INC. FORWARDED TO PERRY PAINE.
INSP - Footings8/12/19978/12/19978/11/1997PPASS
Details
08/12/97 338 -
INSP-Supply line flush7/23/19977/24/19977/24/1997APART
DetailsJoe Tawney
07/24/97 406 - SUPPLY LINE FLUSH AT 11 A.M. OK ON UNDERGROUND FLUSH
INSP-Supply line flush7/17/19977/21/19977/21/1997ANR
DetailsJoe Tawney
07/21/97 406 - HE called you and set up an appt for 11 am UNDERGROUND FLUSH NOT READY
INSP - Conference7/21/19977/21/19977/21/1997 PASS
Details
/ / 338 - 2-hr shaft
INSP - Framing/Rough-in7/18/19977/21/19977/21/1997PPART
Details
07/22/97 338 - madeok partial 2-hr shaft
INSP - Framing/Rough-in7/11/19977/11/19977/14/1997PCANC
DetailsTom Arcoraci
bld #5
INSP - Framing/Rough-in7/11/19977/11/19977/11/1997 PART
Details
07/14/97 333 - 1hr at stairs ok to cover
INSP - Framing/Rough-in7/7/19977/7/19977/7/1997PFAIL
Details
07/07/97 338 - c/n misc drywall problems in the shaft wall systems they
INSP - Framing/Rough-in6/27/19976/30/19977/1/1997APASS
Details
06/30/97 338 - Nacho??? (i think)###-#### mice frame to this point ok pager
INSP - Framing/Rough-in6/20/19976/23/19976/23/1997APART
Details
06/23/97 338 - partial at the ele core and the stair cores mise perimete
INSP - Miscellaneous6/9/19976/9/19976/9/1997 PASS
Details
/ / 338 - resubmittals on the shell and main core areas
INSP - Framing/Rough-in6/9/19976/9/19976/9/1997PPASS
Details
06/09/97 338 - misc framing to this point is ok in the core area misc st
INSP - Conference5/30/19975/30/19975/30/1997 PASS
Details
/ / 338 - must follow the approved plan with the fireblocking in the w in the north srairwell no execptions
INSP - Conference5/30/19975/30/19975/30/1997 PASS
Details
/ / 338 - must follow the approved plan with the fireblocking in the w in the north srairwell no execptions
INSP - Carpentry5/30/19975/30/19975/30/1997PPASS
Details
05/30/97 338 -
INSP - Framing/Rough-in5/28/19975/29/19975/29/1997APART
Details
05/29/97 338 - partial framing north stairwell framing questions at the
INSP - Framing/Rough-in5/23/19975/27/19975/27/1997ANR
Details
05/27/97 338 - partial framing 1st floor core area not ready for cover
INSP - Carpentry5/5/19975/6/19975/6/1997APASS
Details
05/06/97 338 -
INSP - Conference5/1/19975/5/19975/5/1997APASS
Details
05/05/97 338 - ###-####
INSP - Conference3/19/19973/19/19973/18/1997PPASS
Details
03/19/97 338 - CONF ON FRAMING ok to but 1-side drywall at the bottom of fire caulk seal in the anular space will field verify.
INSP - Conference3/7/19973/10/19973/9/1997APART
Details
03/10/97 338 - on the fire proofing
INSP - Masonry2/14/19972/14/19972/14/1997PPASS
Details
02/14/97 338 - 3RD FLOOR POUR. READY TO POUR ON MONDAY WEATHER PRO IN PL INSP
INSP - Conference2/5/19972/5/19972/6/1997 PASS
Details
02/05/97 338 - made ok
INSP - Conference2/5/19972/5/19972/5/1997PPASS
Details
02/05/97 338 - made ok sp insp made ok weather pro in place
CHANGE STATUS TO (I)  2/4/1997
(F) Reprint permit  2/4/1997
INSP - Flatwork1/27/19971/28/19971/28/1997APASS
Details
01/28/97 338 - 2ND FLR.POUR made ok 2nd half
Print Occupancy Form  1/28/1997
Telephone call  1/28/1997
TOLD SECRETARY THAT PERMIT IS READY
Inspection Record Card- Bld  1/28/1997
INSP - Masonry1/24/19971/27/19971/26/1997APASS
Details
01/27/97 338 - POURING 2ND FLR DECK. (I DIDN'T KNOW WHAT TO PUT THIS UN GAVE OK TO POUR 2ND HALF OF THIS DECK WITH THE SPEC INSP BLESSING
Plan resubmittals received  1/23/1997 PASS
PLAN RESUBMITTALS RECEIVED AND APPROVED ON REQUESTED CHANGE OF CONSTRUCTION TYPE FROM TYPE II-ONE-HOUR TO TYPE I-FR.
INSP - Foundation1/16/19971/17/19971/17/1997APASS
Details
01/17/97 338 - fnd.rebar made ok wp in place
INSP - Foundation1/14/19971/15/19971/16/1997PPASS
Details
01/16/97 338 - WILL POUR IN THE AM south west at the dock
INSP - Conference1/13/19971/13/19971/13/1997 PASS
Details
/ / 338 - DETAILS C3&C4 ON A7.0 SHAFT WALL DETAILS THERE IS NO DETAIL SHAFT
Plan resubmittals requested  1/7/1997 PEND
RESUBMITTAL PLANS REQUESTED ON TYPE OF CONSTRUCTION CHANGE REQUEST.
Plan Reviewer's activity  12/18/1996 PEND
ARCHITECT SUBMITTED PLAN SHEETS REQUIRED TO CHANGE CONSTRUCTION TYPE FROM TYPE II-ONE-HOUR TO TYPE I-FR CONSTRUCTION.
INSP - Foundation12/10/199612/10/199612/10/1996 PASS
Details
/ / 338 - made ok by 316
INSP - Footings12/6/199612/9/199612/9/1996APASS
Details
12/09/96 338 - FOOTING REBAR r-bar placed weather prot ok
INSP - Foundation12/3/199612/4/199612/4/1996PPASS
Details
12/04/96 338 - REBAR r-bar placed spec insp made ok
INSP - Footings11/26/199611/27/199611/27/1996PPASS
Details
11/27/96 338 - footing rebar early pm SPEC INSP MADE OK
90 day tracking............. 8/28/199611/26/1996
INSP - Foundation11/21/199611/22/199611/22/1996APASS
Details
RE-BAR FOOTING/FOUNDATION/ placed made ok spec insp
INSP - Footings11/14/199611/18/199611/19/1996PPASS
Details
11/19/96 338 - SPECIAL INSP MADE OK
INSP - Foundation11/12/199611/13/199611/13/1996APASS
Details
11/13/96 338 - ok to pour with the special insp blessing
INSP - Conference11/5/199611/6/199611/6/1996APASS
Details
11/06/96 338 - STARTING PROJECT. LOOKS GOOD WILL SCHEDULE PRE JOB CONFERENCE WHEN THE SUBS ARE ALL HIRED
(F) Reprint permit  10/29/1996
Issue PAID IN FULL permit  10/28/1996
Plan assigned to (JCM)9/10/1996 10/25/1996 PASS
DetailsJohn Menard
Inspection Record Card- Bld  10/25/1996
Print Pending Permit.LaserJet4  10/25/1996
Print Occupancy Form  10/25/1996
PLANS/APPL TAKEN TO FRONT DESK  10/25/1996 PASS
PLANS ARE APPROVED FOR ISSUE. JCM
Telephone call  10/25/1996
LEFT MESSAGE WITH RECEPTIONIST
Plan assigned to (RGG)8/30/1996 10/25/1996 PASS
10/25/96 11:55:13 JCM - this action updated by action script from <<>> in Case No. BLD96-2302
Plan resubmittals received  10/21/1996 PASS
Plan resubmittals requested  10/18/1996 PEND
Plan resubmittals received  10/15/1996 PEND
Routing - PUBLIC WORKS10/3/1996 10/3/1996 PASS
PACKAGE #2
Routing Off Site - A.C.H.D8/30/1996 10/2/1996 PASS
PACKAGE #4 CONTACTED STEVE SIMMIONS AT ###-#### FOR ACHD PICKUP.
Routing - PUBLIC WORKS9/26/1996 10/1/1996 FAIL
PACKAGE 2
Routing - FIRE9/25/1996 9/25/1996 PASS
PACKAGE #1
Application received  9/25/1996 PEND
PACKAGE #1 TO PLANCHECKER.
Routing Off Site - STRUCTURAL8/30/1996 9/23/1996 PEND
PACKAGE #3 SENT TO CH2MHILL ATTEN. CRAIG BARRETT OR MARK BOWEN VIA PDQ. COPY OF CORRECTION LIST WAS FORWARDED TO LOMBARD-CONRAD FOR REQUESTED REVISIONS 09/25/96. JCM
Routing - PLUMBING9/19/1996 9/20/1996 PASS
PACKAGE #1
Routing - PLANNING9/9/1996 9/20/1996 PASS
PACKAGE #2 X-ref: CU-51-96 & DR-97-96. Approved by JH & MS.
Plan resubmittals requested  9/18/1996 PEND
SENT CORRECTION LIST TO ARCHITECT.
Routing - PUBLIC WORKS8/30/1996 9/9/1996 FAIL
PACKAGE #2 NEEDS DRAINAGE PLAN AND LEGAL DESCRIPTION
Routing - ELECTRICAL9/4/1996 9/5/1996 PASS
PACKAGE #1
Routing - MECHANICAL8/30/1996 9/3/1996 PASS
PACKAGE #1
Received Certificate of Value  8/30/1996 PASS
Plan routing begun/NEW & ADDTN  8/30/1996 PASS
Gay Receipt For Partial Pay  8/28/1996
Application received  8/28/1996
INSP - Footings11/7/199611/8/19961/3/1980APASS
Details
11/08/96 338 - LATE A.M. FORMS SET R-BAR PLACED OK BY SPECIAL INSP
Routing - PLAN CHECK10/1/1996   PEND
PACKAGE 2
Routing - PLAN CHECK10/3/1996   PEND
PACKAGE #4
Routing - PLAN CHECK10/3/1996   PASS
Routing - PLAN CHECK9/25/1996   PEND
Routing - PLAN CHECK9/20/1996   PEND
Routing - PLAN CHECK9/20/1996   PEND
PACKAGE #2 TO PC. 9-20-96