CHANGE STATUS TO (D) | | | 2/24/1997 | | |
|
|
|
|
INSP - Final | 10/24/1996 | 10/25/1996 | 10/29/1996 | A | PASS |
Wes Worcester
|
|
|
/ / 342 - 9:30 am apt
|
INSP - Final | 10/23/1996 | 10/24/1996 | 10/24/1996 | A | CANC |
Wes Worcester
|
|
|
cancelled by builder
|
INSP - Framing/Rough-in | 9/27/1996 | 9/30/1996 | 9/30/1996 | A | FAIL |
Wes Worcester
|
|
|
APPT. AT 9:00 AM MONDAY M0RNING
|
INSP - Framing/Rough-in | 9/26/1996 | 9/27/1996 | 9/27/1996 | P | CANC |
Wes Worcester
|
|
|
cancelled until Mon at 9am as per Mark (super)
|
INSP - Conference | 9/26/1996 | 9/26/1996 | 9/26/1996 | A | FAIL |
Wes Worcester
|
|
|
attempted to discuss insp procedure w/super
|
INSP - Foundation | 9/26/1996 | 9/26/1996 | 9/26/1996 | A | FAIL |
Wes Worcester
|
|
|
poured w/o insp
|
INSP - Footings | 9/26/1996 | 9/26/1996 | 9/26/1996 | A | FAIL |
Wes Worcester
|
|
|
poured w/o insp and does have rebar according to super
|
INSP - Footings | 9/17/1996 | 9/17/1996 | 9/17/1996 | P | |
Wes Worcester
|
|
|
|
Application received | | | 8/28/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/28/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/28/1996 | | |
|
|
|
|
Plan assigned to (DJO) | 8/28/1996 | | 6/28/1996 | | PASS |
Dan Overy
|
|
|
|