Permanent Occupancy | | 7/22/1997 | 7/22/1997 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/22/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6926 issued 7-22-97 to First Health.
|
INSP - Final | 1/8/1997 | 1/9/1997 | 1/9/1997 | A | PASS |
Jim Sly
|
|
|
01/08/97 316 - FINAL FOR C/O OK Perm Occ.
|
INSP - Final | 12/17/1996 | 12/17/1996 | 12/17/1996 | | CANC |
Jim Sly
|
|
|
12/16/96 316 - Cancel by contractor
|
INSP - Final | 12/13/1996 | 12/16/1996 | 12/16/1996 | A | CANC |
Joe Tawney
|
|
|
12/16/96 406 - INSP WAS PERFORMED ON 12/13/96 AND ENTERED AS AN ADD ON
|
INSP - Final | 12/13/1996 | 12/16/1996 | 12/16/1996 | A | CANC |
Jim Sly
|
|
|
12/16/96 316 - Cancel by contractor
|
INSP - Final | 12/13/1996 | 12/13/1996 | 12/13/1996 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC
|
INSP - Final | 12/6/1996 | 12/6/1996 | 12/9/1996 | P | FAIL |
Joe Tawney
|
|
|
12/06/96 406 - Scott - ###-#### FAILED DOOR HDWRE EXIT SIGNS BLDG ADDRESS OCC SIGNS
|
90 day tracking............. | | 8/30/1996 | 11/28/1996 | | PEND |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 11/4/1996 | 11/6/1996 | 11/6/1996 | A | PASS |
Joe Tawney
|
|
|
RANDY - ###-#### #C - RESCH FOR 11/06/96 SPKLR ROUGH IN OK HYDRO TEST TO FOLLOW
|
INSP - Ceiling grid | 11/4/1996 | 11/5/1996 | 11/5/1996 | A | PASS |
Jim Sly
|
|
|
11/04/96 316 - Grid..OK
|
INSP - Framing/Rough-in | 10/16/1996 | 10/16/1996 | 10/16/1996 | P | PASS |
Jim Sly
|
|
|
10/16/96 316 - Ext and interior walls OK.
|
INSP - Framing/Rough-in | 10/11/1996 | 10/14/1996 | 10/14/1996 | A | CANC |
Jim Sly
|
|
|
10/11/96 316 - WILL CALL AND SEE IF YOU CAN DO IT 10/11 PM Did on 10/11/96.
|
INSP - Framing/Rough-in | 10/11/1996 | 10/11/1996 | 10/11/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - OK to cover Ext. walls only.....except (2) wood framed openi type 2 N construction......C/N for that.
|
Issue PAID IN FULL permit | | | 9/26/1996 | | |
|
|
|
|
Plan assigned to (R_H) | 9/4/1996 | | 9/24/1996 | | PASS |
|
|
|
09/24/96 08:42:50 R_H - this action updated by action script from <<>> in Case No. BLD96-2326
|
Print Pending Permit.LaserJet4 | | | 9/24/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/24/1996 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/24/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/24/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/24/1996 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/1996 | | PASS |
|
|
|
|
Routing - FIRE | 9/19/1996 | | 9/23/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/20/1996 | | |
|
|
|
ISSUED A PARTIAL PERMIT ON 9/20/96.
|
Issue FEE-DUE permit | | | 9/20/1996 | | |
|
|
|
|
Plan resubmittals requested | | | 9/19/1996 | | PEND |
|
|
|
Requested change to exiting requirments from A-3 occupancy.
|
Routing - PUBLIC WORKS | 9/4/1996 | | 9/18/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/18/1996 | | PEND |
|
|
|
Started plan review
|
Plan routing begun/TENANTS | | | 9/4/1996 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 8/30/1996 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 8/30/1996 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/30/1996 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/23/1996 | | | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/18/1996 | | | | PEND |
|
|
|
|