Information based on query as of Saturday, July 20, 2024.
Permit Information
Permit NumberBLD96-02359
StatusFinaled
Name STATEWIDE CONSTRUCTION
Site Address 5556 W LAKE RIVER LN
Project Name 
Customer Number 
ePlanReviewNo
Description
TO BUILD A NEW SINGLE STORY 2279 s.f SINGLE FAMILY DWELLING WITH A 2009 S.F. ATTACHED GARAGE AND 432 S.F OF WOODEN DECK ALL PER THE APPROVED PLANS AND ATTACHED CONDITIONS." THIS LOT IS SOLAR PROTECTED" see approved setbacks ACHD # 96-0796 PR # 704 338
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (D)  2/24/1997
INSP - Letter of compliance2/19/19972/19/19972/19/1997 PASS
DetailsAlan Hauser
/ / 350 - c/c #12041
INSP - Final2/19/19972/19/19972/19/1997 PASS
DetailsAlan Hauser
/ / 350 - final
INSP - Letter of compliance2/19/19972/19/19972/19/1997 PASS
DetailsAlan Hauser
/ / 350 - c/c #12041
INSP - Final2/18/19972/18/19972/18/1997PFAIL
DetailsAlan Hauser
02/18/97 350 - still need electrical final, everything else ok
INSP - Energy code compliance12/5/199612/5/199612/5/1996 PASS
DetailsAlan Hauser
/ / 350 - insulation ok, ok to cover
INSP - Framing/Rough-in12/4/199612/5/199612/5/1996APASS
DetailsAlan Hauser
12/05/96 350 - FRAME REINSPECT frame ok
INSP - Framing/Rough-in12/2/199612/2/199612/2/1996PPART
DetailsAlan Hauser
12/02/96 350 - CORRECTIONS ON FRAME, OK TO INSULATE, WILL CHECK FRAME CO
INSP - Framing/Rough-in11/25/199611/26/199611/26/1996AFAIL
DetailsAlan Hauser
11/26/96 350 - NO ADDRESS POSTED, NO MECH. OR PBLG. APPROVED
INSP - Footings10/8/199610/9/199610/9/1996PPASS
DetailsAlan Hauser
10/09/96 350 - CHECK ENGINEERED FOOTING... TALKED WITH CONCRETE MAN HE HAS PICTURES OF THE STEEL IN PADS FOR COLUMN PADS ARE POURED BUT WHERE STILL EXPOSED
INSP - Conference10/4/199610/4/199610/4/1996 PASS
DetailsAlan Hauser
/ / 350 - PICKED UP APPROVED PLANS, WENT BY JOB SITE TO LOOK AT TWO RE GARAGE AREA. MEET BRIAN, HE SAID THEY ARE THERE, I CAN'T SEE THEM ASKED EXPOSE THEM FOR INSPECTION. HE SAID HAD MEETING AND WOULD DO IT LATER. A HIM TO CALL ME FOR
Issue PAID IN FULL permit  10/1/1996
INSP - Footings9/26/19969/27/19969/27/1996APASS
DetailsAlan Hauser
09/27/96 350 - LATE A.M. WENT BY AND TALKED TO CONCRETE PEOPLE ABOUT PAD STEEL BEAM IN GARAGE FOOTINGS OK, TWO BARS OF #4 IN FTNS
Plan resubmittals received  9/24/1996 PASS
RECIEVED THREE PAGES REVIEWED AND ACCEPTED THEM INTO THE APPROVED PLANS ON FILE
Plan assigned to (338)9/10/1996 9/19/1996 PASS
692 09/19/96 07:38:09 338 - this action updated by action script from <<>> in Case No. BLD96-2359
Telephone call  9/19/1996 PASS
CALLED SANDY THEY WILL BE IN TO PICK IT UP.
PLANS/APPL TAKEN TO FRONT DESK  9/19/1996
Print Pending Permit.LaserJet4  9/19/1996
Inspection Record Card- Bld  9/19/1996
Routing - PLAN CHECK9/18/1996 9/18/1996 PASS
Routing - FRONT DESK9/18/1996 9/18/1996 PASS
Print Pending Permit.LaserJet4  9/16/1996
Routing - PLANNING9/6/1996 9/11/1996 PASS
Approved by MGH.
Routing - PUBLIC WORKS9/5/1996 9/6/1996 PASS
Application received  9/5/1996