Case Summary (BLD) | | | 10/9/2013 | | DONE |
|
|
|
|
INSP - Framing/Rough-in | 2/19/1997 | 2/19/1997 | 2/19/1997 | P | PASS |
Alan Hauser
|
|
|
02/19/97 350 - FRAME REINSPECT frame ok, ok to cover
|
INSP - Framing/Rough-in | 2/18/1997 | 2/18/1997 | 2/18/1997 | P | FAIL |
Alan Hauser
|
|
|
02/18/97 350 - corrections on frame
|
INSP - Framing/Rough-in | 2/12/1997 | 2/13/1997 | 2/13/1997 | P | NR |
Alan Hauser
|
|
|
02/13/97 350 - mech. not approved for cover yet.
|
INSP - Footings | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Foundation | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Foundation | 11/12/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Wes Worcester
|
|
|
EARLY PM.
|
INSP - Footings | 11/7/1996 | 11/7/1996 | 11/7/1996 | P | PASS |
Wes Worcester
|
|
|
11/07/96 342 - EARLY PM
|
Inspection Record Card- Bld | | | 9/10/1996 | | |
|
|
|
|
Application received | | | 9/10/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/10/1996 | | |
|
|
|
|