Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD96-02403
StatusFinaled
Name ED ZIMMER
Site Address 833 W DIAMOND ST
Project NameECCO ELECTRONIC
Customer Number 
ePlanReviewNo
Description
TO BUILD A NEW 49,565 SQ.FT., TWO STORY, OFFICE AND MANUFACTURING BUILDING CONSTRUCTED OF MASONRY AND STEEL EXTERIOR WALLS, BUTLER MANUFACTURING CO. STEEL BUILDING FRAME, ROOF JOISTS AND METAL ROOF DECK, CONCRETE SLAB FIRST FLOOR, TJI FLOOR JOIST AND PLYWOOD SECOND FLOOR AND WOOD AND STEEL INTERIOR WALLS. THIS BUILDING IS FULLY FIRE SPRINKLED AND USED FOR ALLOWABLE AREA INCREASES. THE SECOND FLOOR IS UNFINISHED SPACE AND WILL REQUIRE A TENANT IMPROVEMENT PERMIT TO FINISH AND OCCUPY. THIS PERMIT ALSO INCLUDES ALL RELATED SITE IMPROVEMENTS. ( FIRST FLOOR 40,335 SQ. FT., SECOND FLOOR 9230 SQ. FT.) DR#65-96/PC#496-96/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  1/11/2016  
Case Summary (BLD)  11/20/2008  
Permanent occupancy  9/5/1997 DONE
Perm. Occ. Cert. #6968 issued 9-5-97 to Ecco Electronics.
Permanent Occupancy 8/29/19978/29/1997 DONE
Details
INSP-Final Inspection8/29/19978/29/19978/29/1997PPASS
DetailsRick Jackson
INSP - Final8/29/19978/29/19978/29/1997 PASS
DetailsJim Storey
/ / 301 - FNL -OK FINAL
INSP - Final8/26/19978/27/19978/27/1997PNR
DetailsJim Storey
08/27/97 301 - i gave floyd his for 8/26/97 all other trades finaled. ca CORR-CORREC-CALL FOR REINSP WHEN COMPLETED HI JIM.....I FAILED THEM TUESDAY PM, ALARM ZONES STILL NOT RIGHT
INSP-Final Inspection8/26/19978/26/19978/26/1997PFAIL
Details
cathy has card to sign off. ALARM RESPONCE STILL WRONG ( 5/23 CORRECTION LIST) FD CALLED FOR EVERYTHING... TO CORRECT ASAP
Routing for occupancy5/29/19975/29/19975/29/1997 PASS
Art Y. inspected for final - meets compliance with DR-65-96/Signed Final.
INSP - Final5/29/19975/29/19975/29/1997 PASS
DetailsJim Storey
/ / 301 - TCO -TEMP C OF O ISSUED CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
Temporary occupancy  5/29/1997 PASS
Temp. Occ. Cert. #3411 issued 5-29-97 to Ecco Electronic.
INSP - Final5/23/19975/27/19975/27/1997PNR
DetailsJim Storey
05/27/97 301 -
INSP-Final Inspection5/23/19975/23/19975/23/1997PPART
Details
supervisorys still tranmit as alarms, need nfpa 72
INSP-Final Inspection5/21/19975/21/19975/21/1997PFAIL
Details
address not visible, piv not monitored, all signals transmit as fire alarms, panel troubles do not transmit, 1 head too close to unit heater for temp rating
INSP-Final Inspection5/12/19975/12/19975/12/1997PFAIL
Details
c/n issued, lots of details to wrap up, advised egress control devices must have auto, manual, fire alarm and power out release
INSP - Framing/Rough-in5/9/19975/9/19975/9/1997PPASS
DetailsJim Storey
05/09/97 301 - FRAM-OK FRAMING Resubmital wall
INSP - Framing/Rough-in4/24/19974/25/19974/25/1997APASS
DetailsJim Storey
04/25/97 301 - ceiling wall SCLG-OK SUSPENDED CEILING and draft stop ok
INSP-Sprinkler Rough-in/Hydro4/24/19974/25/19974/25/1997APASS
Details
hydro test, todd will call when pressurized replaced test orifice w/ correct size
INSP-Sprinkler Rough-in/Hydro4/24/19974/24/19974/24/1997APART
Details
correction list given to herb on missing sprinklers. also gave notice that approved plans do not allow storage over 12 ft. sprinklers designed for 16 ft, no racks over 8 ft since no seismic was provided
INSP-Sprinkler Rough-in/Hydro4/23/19974/23/19974/23/1997PPART
Details
herb dock area not complete, need to check 2nd floor storage
INSP - Conference4/21/19974/21/19974/21/1997 PART
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Carpentry4/3/19974/2/19974/3/1997 PASS
DetailsJim Storey
sheer nailling on walls
INSP - Framing/Rough-in4/1/19974/1/19974/1/1997PPASS
DetailsJim Storey
sheer nailling ok mezanine fr ok
INSP - Framing/Rough-in3/25/19973/25/19973/25/1997PPART
DetailsJim Storey
03/25/97 301 - INTER STUD WALLS ALL BUT SHEER OK
INSP - Footings3/11/19973/12/19973/12/1997PPASS
DetailsJim Storey
03/12/97 301 - covered by si. recieved eifs submital and approved system
INSP - Foundation12/12/199612/13/199612/13/1996APASS
DetailsJim Storey
12/13/96 301 - CALLED IN A FLOOR POUR FDN -OK FOUNDATION hair pins
90 day tracking............. 9/10/199612/9/1996
Plan resubmittals received  12/5/1996 PASS
A RESUBMITTAL WAS RECEIVED FOR BRS ARCHITECTS THAT CONTAINED REVISIONS TO THE PROPOSED HAZARDOUS MATERIALS MANAGEMENT PLAN, THE QUANTITIES OF HAZARDOUS MATERIALS TO BE STORED AND USED AND THE LOCATION OF THE STORED MATERIALS, INCLUDING THE DELETION OF THE PROPOSED EXTERIOR ATTACHED STORAGE ROOMS. THE PROPOSAL ALSO INCLUDED A CHANGE IN THE EXTERIOR FINISH MATERIALS FOR THE ECCO BUILDING. THE EXTERIOR FINISH CHANGES WOULD HAVE REQUIRED A MODIFICATION TO THE DESIGN REVIEW AND SO THAT REVISION WAS WITHDRAWN. THE HAZARDOUS MATERIALS USED AND THE STORAGE LOCATION CHANGES WERE REVIEWED BY JOHN MENARD AND DAVE MILLER AND APPROVED PER THE INFORMATION SUBMITTED FOR THE PROPOSED REVISION. THE PROPOSED CHANGES WERE SUBMITTED FOR APPROVAL AFTER THE ISSUANCE OF THE BUILDING PERMIT AND CONSTRUCTION HAS CONTINUED DURING THIS REVIEW.
INSP - Footings11/26/199611/27/199611/27/1996PPASS
DetailsJim Storey
/ / 301 - READY AT 1PM PLEASE. FRMS-OK FORMS-REBAR special insp on site
INSP - Footings11/26/199611/26/199611/26/1996PPART
DetailsJim Storey
11/26/96 301 - WIP -WORK IN PROGRESS special insp. on site pending repor
INSP - Footings11/25/199611/25/199611/25/1996PNR
DetailsWes Worcester
still placing dobbies and getting side clearance...spec insp to be on site
INSP - Foundation11/25/199611/25/199611/25/1996PPART
DetailsWes Worcester
poured with special insp on site...pending report as some dowels had less than 1" cover between them at jambs
INSP - Foundation11/21/199611/21/199611/21/1996PPART
DetailsWes Worcester
special insp on site
INSP - Footings11/19/199611/19/199611/19/1996PPASS
DetailsWes Worcester
APPT. 3 P.M.
INSP - Footings11/19/199611/19/199611/19/1996ANR
DetailsWes Worcester
INSP - Site Preparation11/19/199611/19/199611/19/1996APART
DetailsWes Worcester
cleaning out mud and having soils tested
INSP - Conference11/19/199611/19/199611/19/1996APASS
DetailsWes Worcester
ck on lean concrete fill - going to pour at 3pm w/sp insp
INSP - Footings11/14/199611/15/199611/15/1996AFAIL
DetailsWes Worcester
inadequate cover, special inspectors report rejected, eng of record and special inspector to meet on site. several 100'poured
(F) Reprint permit  11/14/1996
Routing - PLAN CHECK11/12/1996 11/13/1996 PASS
Issue PAID IN FULL permit  11/13/1996
PLANS/APPL TAKEN TO FRONT DESK  11/13/1996 PASS
Issue PAID IN FULL permit  11/13/1996
Print Occupancy Form  11/13/1996
Telephone call  11/13/1996
LEFT MESSAGE WITH SECRETARY
Inspection Record Card- Bld  11/13/1996
Plan assigned to (JCM)9/19/1996 11/13/1996 PASS
DetailsJohn Menard
Routing - FIRE11/5/1996 11/12/1996 PASS
PACKAGE #1
Routing Off Site - A.C.H.D11/12/1996 11/12/1996 PASS
No impact fees were required for this project. See letter on file from A.C.H.D..
Routing - PLANNING11/5/1996 11/6/1996 PASS
PACKAGE #2 X-ref: DR-65-96. Approved by TKW.
Routing Off Site - A.C.H.D9/11/1996 11/5/1996 PEND
PACKAGE #4 CONTACTED CLINTON YAKA AT ###-#### TO TAKE PLANS TO ACHD ACHD FEES NOT PAID.
Routing - PLAN CHECK10/30/1996 11/5/1996 PASS
Plan resubmittals received  10/31/1996 PASS
Routing - FIRE10/24/1996 10/30/1996 FAIL
PACKAGE 1
Routing - PUBLIC WORKS10/18/1996 10/21/1996 PASS
Application received  10/18/1996
Routing Off Site - STRUCTURAL9/12/1996 10/10/1996 PEND
PCKAGE#3 CONTACTED PDQ TO TAKE PLANS TO CH2MHILL ATTEN. CRAIG BARRETT OR MARK BOWEN FOR OUTSIDE ENGINEERING. KMM 9-12-96 RETURN 10-10-96 BACK AT JOHN DESK. COPY OF STRUCTURAL CORRECTION COMMENTS FAXED TO CLINTON YAKA AT BRS FOR REQUIRED REVISIONS. 10/11/96 JCM
Plan resubmittals requested  10/8/1996 PEND
ADDITIONAL RESUBMITTALS REQUESTED OF THE ARCHITECT.
Routing - FIRE10/1/1996 10/4/1996 FAIL
PACKAGE #1
Plan resubmittals received  10/3/1996 PEND
Routing - MECHANICAL9/25/1996 10/1/1996 PASS
PACKAGE #1
Routing - PLANNING9/20/1996 9/25/1996 FAIL
PACKAGE #2 X-ref: DR-65-96. Modification pending. Reviewed by TKW.
Plan resubmittals requested  9/24/1996 PEND
PRELIMINARY PLAN REVIEW COMMENTS SENT TO CLINTON YAKA, BRS ARCHITECTS FOR REQUIRED REVISIONS.
Routing - PUBLIC WORKS9/11/1996 9/20/1996 FAIL
PACKAGE #2 REQUIRES DRAINAGE PLAN REVISION
Routing - PLUMBING9/13/1996 9/18/1996 PASS
PACKAGE#1
Routing - ELECTRICAL9/11/1996 9/13/1996 PASS
PACKAGE#1
CHANGE STATUS TO (P)  9/12/1996 PEND
Plan routing begun/NEW & ADDTN  9/11/1996 PASS
Gay Receipt For Partial Pay  9/11/1996 PEND
Application received  9/10/1996
Received Certificate of Value  9/10/1996 PASS
Routing - PLAN CHECK9/19/1996   PEND
PACKAGE #1
Routing - PLAN CHECK10/4/1996   PEND
PACKAGE #1
Routing - PLAN CHECK10/21/1996   PEND
PACKAGE #2
Routing - PLAN CHECK11/12/1996  
Routing - PLAN CHECK11/7/1996  
PACKAGE #2
Routing - PLAN CHECK9/25/1996   PEND
PACKAGE #2