Permanent Occupancy | | 3/13/1997 | 3/13/1997 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/13/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6810 issued 3-13-97 to Frank-N-Buns in the Boise Research Center.
|
INSP - Final | 3/12/1997 | 3/12/1997 | 3/12/1997 | P | PASS |
Jim Sly
|
|
|
03/12/97 316 - Frank n Buns/ for perm occup. OK
|
INSP - Final | 11/26/1996 | 11/27/1996 | 11/27/1996 | P | NR |
Carl Dependahl
|
|
|
11/27/96 340 - 316 AREA, SENT IN ERROR
|
INSP-Sprinkler Rough-in/Hydro | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
Joe Tawney
|
|
|
11/25/96 406 - TONY ###-#### NOT SURE WHAT HE WANTED. OK FOR PERM OCC
|
INSP-Sprinkler Rough-in/Hydro | 11/21/1996 | 11/22/1996 | 11/22/1996 | A | FAIL |
Joe Tawney
|
|
|
11/22/96 406 - joe, this might be a final, i was confused./pat per stan normal/pat FINAL INSP FAILED ANSUL TEST DOOR HDWRE EMERG LIGHTS
|
INSP - Framing/Rough-in | 11/15/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
Jim Sly
|
|
|
11/15/96 316 - OK
|
INSP - Carpentry | 11/14/1996 | 11/14/1996 | 11/14/1996 | P | FAIL |
Jim Sly
|
|
|
11/14/96 316 - 1 HR. SHAFT C/N... Architect to re-submit details for ap
|
INSP - Carpentry | 11/12/1996 | 11/13/1996 | 11/13/1996 | A | FAIL |
Jim Sly
|
|
|
11/12/96 316 - 1 HR. SHAFT C/N....Need to build per approved plans.
|
INSP - Ceiling grid | 11/8/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Jim Sly
|
|
|
11/12/96 316 - OK
|
INSP - Carpentry | 11/8/1996 | 11/8/1996 | 11/11/1996 | P | FAIL |
Jim Sly
|
|
|
11/11/96 316 - 1 HR. SHAFT C/N.
|
INSP - Carpentry | 11/8/1996 | 11/8/1996 | 11/8/1996 | | FAIL |
Jim Sly
|
|
|
11/08/96 316 - 1 HR. SHAFT C/N.
|
INSP - Framing/Rough-in | 10/24/1996 | 10/25/1996 | 10/25/1996 | P | PART |
Jim Sly
|
|
|
10/24/96 316 - OK to cover interior walls and demising wall. Left note 2 hr hood shaft W/O inspections of each layer.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/1996 | | PASS |
|
|
|
Issue upon receipt of Fax From Architect showing second exit. ARNOLD FILLMORE BROUGHT IN A1 SHEETS SHOWING SECOND EXIT. KMM 10-15-96 I ISSUED PER DICK PIERCES REQUEST.
|
Issue PAID IN FULL permit | | | 10/15/1996 | | |
|
|
|
|
Telephone call | | | 10/15/1996 | | |
|
|
|
TOLD THEM PERMIT READY
|
Inspection Record Card- Bld | | | 10/15/1996 | | |
|
|
|
|
Print Occupancy Form | | | 10/15/1996 | | |
|
|
|
|
Plan resubmittals received | | | 10/15/1996 | | PASS |
|
|
|
2 A1 SHEETS FOR EXIT DOOR
|
Telephone call | | | 10/11/1996 | | PASS |
|
|
|
Conversation with Owner (Randell Fillmore) this AM about second exit door. He will install as requested but Architect is out of town till Monday and will not be able to Fax over to us the Resubmittal showing the door being added back into the plans. Since I will be gone for a week starting this PM I have assembled the plans with the note redlined into the approved copy and have completed the approval in Tidemark and sent to Radfords desk with instruction to assemble into plans the Fax upon arrival and forward to the Permit Desk for issuance.
|
Plan assigned to (PRP) | 9/18/1996 | | 10/11/1996 | | PASS |
|
|
|
10/11/96 10:17:31 PRP - this action updated by action script from <<>> in Case No. BLD96-2422
|
Print Pending Permit.LaserJet4 | | | 10/8/1996 | | PEND |
|
|
|
files
|
Routing - FIRE | 10/8/1996 | | 10/8/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/7/1996 | | PEND |
|
|
|
review plans, mark-up, input to Plan Analysist for review and corrections, Fax to Arch and Owner, forward to Fire.
|
Routing - PUBLIC WORKS | 9/25/1996 | | 10/4/1996 | | PASS |
|
|
|
|
Routing - MECHANICAL | 10/4/1996 | | 10/4/1996 | | PASS |
|
|
|
|
Routing - PLUMBING | 9/18/1996 | | 9/25/1996 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 9/13/1996 | | 9/18/1996 | | PASS |
|
|
|
CONTACTED RANDALL FILLMORE AT ###-#### TO TAKE PLANS TO ACHD.
|
Routing - ELECTRICAL | 9/13/1996 | | 9/13/1996 | | PASS |
|
|
|
FIELD VERIFY
|
Plan routing begun/TENANTS | | | 9/13/1996 | | |
|
|
|
This plan to route to Central District Health, Public Works, Plumbing, Mechanical then back to Plan Check. After Plan Check route to Fire Department.
|
Application received | | | 9/12/1996 | | |
|
|
|
|
Received Certificate of Value | | | 9/12/1996 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/12/1996 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 9/12/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/4/1996 | | | | PEND |
|
|
|
|
Routing - PLAN CHECK | 10/9/1996 | | | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/18/1996 | | | | PEND |
|
|
|
|