Case Summary (BLD) | | | 8/15/2001 | | |
|
|
|
|
INSP - Conference | 10/1/1997 | 10/1/1997 | 10/2/1997 | P | FAIL |
|
|
|
letter of trans
|
INSP - Final | 1/6/1997 | 1/6/1997 | 1/6/1997 | P | PASS |
|
|
|
card signed for temp other signatures needed
|
INSP - Temporary occupancy | | | 1/6/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3338 issued 1-6-97 to the Downtown Child Development Center.
|
INSP - Final | 12/27/1996 | 12/30/1996 | 12/30/1996 | A | FAIL |
|
|
|
12/30/96 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Final | 12/26/1996 | 12/30/1996 | 12/30/1996 | P | PASS |
|
|
|
12/30/96 405 - duct detectors added, smokes and manual pulls throughout, raised outlets, evac maps ok, system maintenance agreement in place.
|
INSP - Framing/Rough-in | 12/19/1996 | 12/19/1996 | 12/19/1996 | P | PART |
|
|
|
12/19/96 333 - ramp ok
|
90 day tracking............. | | 9/13/1996 | 12/12/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 11/15/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
|
|
|
11/15/96 333 - FRAM-OK FRAMING
|
INSP - Conference | 11/13/1996 | 11/13/1996 | 11/13/1996 | P | PASS |
|
|
|
explained cn
|
INSP - Framing/Rough-in | 11/12/1996 | 11/12/1996 | 11/12/1996 | A | FAIL |
|
|
|
11/12/96 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 11/8/1996 | 11/12/1996 | 11/12/1996 | A | CANC |
Alan Hauser
|
|
|
11/12/96 350 - TO BE DONE BY KIM M.
|
Issue PAID IN FULL permit | | | 11/1/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/31/1996 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/31/1996 | | |
|
|
|
|
Telephone call | | | 10/31/1996 | | |
|
|
|
LEFT MESSAGE FOR DAN STOUT
|
Inspection Record Card- Bld | | | 10/31/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/30/1996 | | 10/31/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/1996 | | PASS |
|
|
|
|
Routing - FIRE | 10/25/1996 | | 10/30/1996 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/22/1996 | | 10/25/1996 | | |
|
|
|
|
Routing - MECHANICAL | 10/14/1996 | | 10/21/1996 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/11/1996 | | 10/14/1996 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/4/1996 | | 10/11/1996 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/10/1996 | | PEND |
|
|
|
|
Routing - PLANNING | 10/3/1996 | | 10/4/1996 | | PASS |
|
|
|
X-ref: CU-153-90. Approved by RAC.
|
Plan assigned to (RGG) | 9/27/1996 | | 10/3/1996 | | PASS |
|
|
|
see pc#507-96
|
Routing - PLAN CHECK | 9/26/1996 | | 10/3/1996 | | PEND |
|
|
|
|
Routing Off Site - A.C.H.D | 9/18/1996 | | 9/26/1996 | | PASS |
|
|
|
CONTACTED DAN STOUT AT ###-#### TO TAKE PLANS OUT TO ACHD
|
Plan routing begun/TENANTS | | | 9/18/1996 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 9/18/1996 | | 9/18/1996 | | PASS |
|
|
|
FIELD VERIVY
|
Received Certificate of Value | | | 9/18/1996 | | PASS |
|
|
|
|
Application received | | | 9/13/1996 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 9/13/1996 | | |
|
|
|
|