Permanent Occupancy | | 1/17/1997 | 1/17/1997 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 1/17/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6770 issued 1-17-97 to In-System Design in the Brighton Bldg.
|
INSP - Final | 1/13/1997 | 1/14/1997 | 1/14/1997 | A | PART |
Jim Sly
|
|
|
01/14/97 316 - Temp Occ. .....needs perm for elect.
|
INSP - Final | 1/14/1997 | 1/14/1997 | 1/14/1997 | | PASS |
|
|
|
FINAL OK FOR PERM OCC
|
INSP - Final | 12/17/1996 | 12/17/1996 | 12/17/1996 | | PASS |
Joe Tawney
|
|
|
12/17/96 406 - OK FOR TEMP OCC STILL NEED TO RESOLVE EXIT DOOR SWING ISSUE
|
INSP - Final | 12/17/1996 | 12/17/1996 | 12/17/1996 | | FAIL |
Jim Sly
|
|
|
12/16/96 316 - C/N ...No framing insp completed, no approved plans on si inspecton.
|
INSP - Final | 12/16/1996 | 12/17/1996 | 12/17/1996 | P | FAIL |
Jim Sly
|
|
|
12/17/96 316 - C/N Need approved plans and framing insp.
|
90 day tracking............. | | 9/18/1996 | 12/17/1996 | | PEND |
|
|
|
|
INSP - Final | 12/3/1996 | 12/3/1996 | 12/3/1996 | P | FAIL |
Joe Tawney
|
|
|
12/03/96 406 - early pm FAILED SPKLR SYST ANNUAL INSP EXIT SIGN MOUNT FIRE EXT CHECK EXIT DOOR SWING WITH ARCH
|
INSP - Ceiling grid | 12/3/1996 | 12/3/1996 | 12/3/1996 | P | PASS |
Jim Sly
|
|
|
12/03/96 316 - OK.
|
INSP-Sprinkler Rough-in/Hydro | 12/2/1996 | 12/2/1996 | 12/2/1996 | P | PASS |
Joe Tawney
|
|
|
12/02/96 406 - RANDY - ###-#### spklr rough-in OK TO COVER
|
Issue PAID IN FULL permit | | | 10/30/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/25/1996 | | |
|
|
|
|
Print Occupancy Form | | | 10/25/1996 | | |
|
|
|
|
Telephone call | | | 10/25/1996 | | |
|
|
|
CALLED STEED..SECRETARY SAID THEY WOULD PICK UP ON THE 28TH
|
Plan Reviewer's activity | | | 10/24/1996 | | PASS |
|
|
|
reviewed resubs and approve. input to tidemark.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/1996 | | PASS |
|
|
|
ISSUE
|
Print Pending Permit.LaserJet4 | | | 10/24/1996 | | PASS |
|
|
|
ISSUE
|
Plan resubmittals received | | | 10/24/1996 | | |
|
|
|
|
Plan assigned to (PRP) | 9/19/1996 | | 10/24/1996 | | PASS |
|
|
|
10/24/96 15:17:16 PRP - this action updated by action script from <<>> in Case No. BLD96-2495
|
Plan resubmittals received | | | 10/23/1996 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/21/1996 | | PEMD |
|
|
|
reviewed plans, did Plan analysist review, correction list, fax to Arch, forward to fire Dept.
|
Plan resubmittals requested | | | 10/21/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 10/15/1996 | 10/15/1996 | 10/15/1996 | | FAIL |
Jim Sly
|
|
|
/ / 316 - C/N
|
Plan resubmittals received | | | 10/15/1996 | | |
|
|
|
|
INSP - Framing/Rough-in | 10/14/1996 | 10/14/1996 | 10/14/1996 | P | NR |
Carl Dependahl
|
|
|
10/14/96 340 - 316 AREA, NEED C/N ONSITE; WILL CALL SLY
|
Routing - FIRE | 9/30/1996 | | 10/1/1996 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 9/30/1996 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/30/1996 | | PEND |
|
|
|
PRELIMINARY REVIEW-REQUESTED INFO BEFORE REVIEW.
|
Routing - PLAN CHECK | 9/20/1996 | | 9/30/1996 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 9/19/1996 | | 9/20/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/20/1996 | | |
|
|
|
ISSUED A PARTIAL PERMIT ON 9/20/96.
|
Issue FEE-DUE permit | | | 9/20/1996 | | |
|
|
|
|
Issue FEE-DUE permit | | | 9/20/1996 | | |
|
|
|
|
Plan routing begun/TENANTS | | | 9/19/1996 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Recd Pcfee & Taken To Pln CK | | | 9/18/1996 | | PEND |
|
|
|
|
Gay Receipt For Partial Pay | | | 9/18/1996 | | PEND |
|
|
|
|
Application received | | | 9/18/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/1/1996 | | | | PEND |
|
|
|
|