CHANGE STATUS TO (D) | | | 3/10/1997 | | PASS |
|
|
|
|
INSP - Letter of compliance | 2/26/1997 | 2/26/1997 | 2/26/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - LC 11479
|
INSP - Final | 2/25/1997 | 2/26/1997 | 2/26/1997 | P | PASS |
Carl Dependahl
|
|
|
02/26/97 340 - OK
|
INSP - Letter of compliance | 2/26/1997 | 2/26/1997 | 2/26/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - LC 11479
|
INSP - Wall cover | 12/5/1996 | 12/5/1996 | 12/5/1996 | P | PASS |
Jim Sly
|
|
|
12/05/96 316 - NAILING int. wall cover..OK Ext. OK
|
INSP - Framing/Rough-in | 11/29/1996 | 12/2/1996 | 12/2/1996 | A | CANC |
Carl Dependahl
|
|
|
12/01/96 340 -
|
INSP - Carpentry | 12/2/1996 | 12/2/1996 | 12/2/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CHK SHEAR WALL; NEED FURTHER INSP AT INT GYP SHEAR WALL...NO EXT OK. PLACED FOIL VAPOR BARRIER AT ALL INT WALLS...OK
|
INSP - Energy code compliance | 11/12/1996 | 11/12/1996 | 11/12/1996 | | PART |
Carl Dependahl
|
|
|
11/08/96 340 - PART, NEED COMPLETE VAPOR BARRIER
|
INSP - Energy code compliance | 11/8/1996 | 11/12/1996 | 11/12/1996 | P | PART |
Carl Dependahl
|
|
|
SHOWED ON NON RESPONSE REPORT...
|
INSP - Framing/Rough-in | 11/12/1996 | 11/12/1996 | 11/12/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - C/N OK
|
INSP - Conference | 11/12/1996 | 11/12/1996 | 11/12/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - RE VAPOR BARRIER USE
|
INSP - Conference | 11/8/1996 | 11/8/1996 | 11/8/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - W/ JOHN, SUPT RE C/N OF 11-7-96
|
INSP - Framing/Rough-in | 11/7/1996 | 11/8/1996 | 11/8/1996 | A | FAIL |
Carl Dependahl
|
|
|
11/08/96 340 - C/N OK TO INS
|
INSP - Framing/Rough-in | 11/6/1996 | 11/7/1996 | 11/7/1996 | P | FAIL |
Carl Dependahl
|
|
|
11/06/96 340 - LEFT C/N, NR
|
INSP - Foundation | 10/10/1996 | 10/10/1996 | 10/11/1996 | P | PART |
Carl Dependahl
|
|
|
10/10/96 340 - POURED W/O INSP , LOOKS OK. NEED PLAN
|
INSP - Footings | 10/7/1996 | 10/8/1996 | 10/8/1996 | A | PART |
Carl Dependahl
|
|
|
10/08/96 340 - POURED W/O INSP...NO HILLSIDE REQ'S
|
Issue PAID IN FULL permit | | | 10/2/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/1996 | | PASS |
|
|
|
ISSUE
|
Print Pending Permit.LaserJet4 | | | 9/30/1996 | | PASS |
|
|
|
FILES
|
Plan Reviewer's activity | | | 9/30/1996 | | PASS |
|
|
|
REVIEW PLANS AND ATTACHMENTS, MARK-UP PLANS, INPUT TO TIDEMARK, ISSUE
|
Telephone call | | | 9/30/1996 | | |
|
|
|
TOLD THEM PERMIT IS READY
|
Inspection Record Card- Bld | | | 9/30/1996 | | |
|
|
|
|
Plan assigned to (PRP) | 9/26/1996 | | 9/30/1996 | | PASS |
|
|
|
09/30/96 14:45:33 PRP - this action updated by action script from <<>> in Case No. BLD96-2500
|
Routing - FRONT DESK | 9/26/1996 | | 9/26/1996 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 9/19/1996 | | 9/26/1996 | | PEND |
Dan Overy
|
|
|
|
Routing - PLANNING | 9/25/1996 | | 9/26/1996 | | PASS |
|
|
|
Approved by MGH.
|
Routing - PUBLIC WORKS | 9/19/1996 | | 9/25/1996 | | PASS |
|
|
|
|
Application received | | | 9/19/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 9/26/1996 | | | | |
|
|
|
|