INSP - Permanent occupancy | | | 1/9/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6752 issued 1-9-97 to Old Chicago at Boise Towne Square.
|
INSP - Final | 1/7/1997 | 1/7/1997 | 1/7/1997 | P | PASS |
|
|
|
01/07/97 338 - madeok still need to sign the occ rec card
|
INSP - Final | 1/3/1997 | 1/6/1997 | 1/6/1997 | P | CANC |
Joe Tawney
|
|
|
01/06/97 406 - CANCEL
|
INSP - Framing/Rough-in | 12/9/1996 | 12/9/1996 | 12/10/1996 | P | PASS |
|
|
|
12/09/96 338 - WANTS TO COVER
|
INSP-Conference | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
Joe Tawney
|
|
|
12/09/96 406 - SCOTT STINSON. ###-#### (MAIN ENTRY) PRE FINAL CONF ON SPKLRS EXIT & EMERG LIGHTS & ANSUL SYST FOR COOK HOOD
|
INSP - Framing/Rough-in | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | PART |
|
|
|
12/06/96 338 - CEILING GRID,,FRAMINGpartial madeok
|
INSP - Conference | 11/26/1996 | 11/26/1996 | 11/26/1996 | | PASS |
|
|
|
/ / 338 - about the hood and shaft with dan stewart and the super
|
INSP - Footings | 11/25/1996 | 11/26/1996 | 11/26/1996 | A | PASS |
|
|
|
11/26/96 338 - re-bar
|
INSP - Foundation | 11/22/1996 | 11/25/1996 | 11/25/1996 | A | CANC |
|
|
|
11/25/96 338 - cancelledtil tomorroweady until tomorrow called to cancel
|
Plan assigned to (DRS) | 9/19/1996 | | 11/18/1996 | | PASS |
Dan Stuart
|
|
|
11/18/96 09:59:52 DRS - this action updated by action script from <<>> in Case No. BLD96-2501
|
Telephone call | | | 11/18/1996 | | |
|
|
|
CALLED JEFF LANGAN
|
Print Pending Permit.LaserJet4 | | | 11/18/1996 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/18/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/18/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/18/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/1996 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 11/18/1996 | | 11/18/1996 | | PASS |
|
|
|
plans taken out to ACHD by Jeff from Old Chicago NO IMPACT FEES DUE. MG 11-18-96 KMM
|
Routing - PLAN CHECK | 11/18/1996 | | 11/18/1996 | | PASS |
|
|
|
Reviewed for approvals by all agencies. Changed fee costs to reflect new certificate of value received Nov 14, 1996.
|
Print Pending Permit.LaserJet4 | | | 11/18/1996 | | PASS |
|
|
|
|
Routing - FIRE | 11/14/1996 | | 11/15/1996 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/14/1996 | | 11/14/1996 | | PASS |
|
|
|
Received new floor plan & engineering as required. Plan Check complete. Need to route plans to Fire Dept. to be approved from previous fail.
|
Routing - MECHANICAL | 11/7/1996 | | 11/14/1996 | | PASS |
|
|
|
FIELD REVIEW ONLY. PLANS NOT CHECKED. DAR (PER PERMISSION FROM DAVID HATTRICK)
|
Print Pending Permit.LaserJet4 | | | 11/14/1996 | | PASS |
|
|
|
|
Telephone call | | | 11/14/1996 | | |
|
|
|
Called Jeff Langdon, CSDI Const., to request a new Certificate of Value. Said he would have it to me today. Plans are in Fire Dept.
|
Print Pending Permit.LaserJet4 | | | 11/14/1996 | | PASS |
|
|
|
|
Received Certificate of Value | | | 11/14/1996 | | |
|
|
|
Received new certificate of value from CDSI, Jeff Langan.
|
Meeting | | | 11/13/1996 | | |
|
|
|
Jeff Langdon came in to see how plans were progressing. Plans are still in mechanical div. for re review.
|
Plan resubmittals received | | | 11/12/1996 | | PASS |
|
|
|
Received new floor plan layour for lounge area & engineering calcs stamped by licensed Idaho architect.
|
Routing - PLAN CHECK | 10/14/1996 | | 11/7/1996 | | FAIL |
|
|
|
Started plan review of submitted plans. 10/18/96 Completed preliminary plan review. Faxes & mailed copy to architect for his response. Plan need to be reviewed by P&Z because of exterior alterations & additions. 11/07/96 - Have reviewed occupant load questions with the architect and Old Chicago field project manager. Will be receiving new floor plan layout proposals per Vince Yannett. Received letter from CSDI Construction, Inc., Jeff Langdon stating that CSDI Const will provide mechanical engeineered design for the additional ducting and one hour shaft requirements after they have opened up the ceiling for preparation to install the new Type I Hood for the pizza oven, for review and approval, prior to starting any work. I accepted the letter as a condition of the permit. drs I am rerouting the plans to the Mechanical Div. for review - failed mech. review previously.
|
Telephone call | | | 11/7/1996 | | |
|
|
|
Phone discussion with Mr Sanders, architect on Old Chicago restaurant at BTS, to review the occupanct load question within the lounge area and the need for a second complying exit serving this area. Mr. Sanders has figured a different occupant load and area than I have. He will refigure his calculations and fax me a copy of some alternate seating arrangement and an explanation of how he figured the occupant load. I also asked him to send me a legible copy of the engineering design specifications for the new entry vestibule with an architects or engineers Idaho license stamp on the calculations, that I can use to verify the design information shown. I also reviewed withhim the difference between the structural floor joist as called out on the plan to be 8 inch deep, 20 gage as versus the submitted design manufactures specs that show 6 inch 20 or 18 gage as being all right. The difference is that the 8 inch, 20 gage joist requires web stiffeners per the manufacture do to web thickness to height ratio. A heavier gage 8" joist is needed, or a web stiffener detail or the approved 6" 20 or 18 gage. I also asked him to provide a letter showing what components of the proposed special inspection bid appraisal copy,sent to me, from Materials Testing Inc. is required by the engineer and that the proposal was accepted.
|
Plan resubmittals requested | | | 11/7/1996 | | |
|
|
|
See comments under telephone calls & meetings. New plan proposals being prepared & engineering clarifications coming from architect.
|
Meeting | | | 11/7/1996 | | |
|
|
|
Had Jeff Langdon, CSDI Construction project manager for the Old Chicago tenant improvment at Boise Towne Square. He was accompanied by Vince Yannett, project manager for Rock Bottom Restaurants, Inc. owner of Old Chicago. We reviewed outstanding questions concerning the proposed Old Chicago Restaurant project. (1)The lack of appropriate exits from the lounge area. Suggestions: A tunnelled corridor exit system in front of the kitchen area to the exterior West wall from the lounge; A new exit corridor from the lounge to a exit corridor through other tenant spaces. To reduce the area of the lounge by alternate lower use occupancies such that an assembly occupancy would not be greated. Provide a letter from comany officials and signed by them that they would post the area with a sign limiting the occupant load to 49 or less and they would accept responsibility for policing the area and enforcing the occupant load - I would present this request to my superviser for consideration/approval. Mr. Yannett said he would get with the restaurant officials to consider the options and may even suggest a floor layout redesign, opening up the lounge area to interconnected with the dining room #1 area and exits. Mr. Yannett called back to say that he had talked to the restaurant layout person for Old Chicago and she would prepare some preliminary drawings showing the proposed changes for approval prior to having the architect redesign.
|
Telephone call | | | 11/6/1996 | | |
|
|
|
Tried to return call to Chuck Sanders, architect for Old Chicago project at BTS. Mr. Sanders was not in.
|
Plan Reviewer's activity | | | 10/30/1996 | | |
|
|
|
Issued a demolition permit, BLD96-2937, for the future Old Chicago site to CSDI Construction, Inc., Jeff Langdon, pending the issuance of a building permit for the tenant improvement.
|
Plan resubmittals received | | | 10/29/1996 | | |
|
|
|
Preliminary plan review comments have not been sufficiently addressed. Pursuing clarifications from the architect and CSDI Const.
|
Telephone call | | | 10/24/1996 | | |
|
|
|
Phone call to Chuck Sanders, architect, concerning the preliminary plans review. We reviewed each comment and I directed him to the code section in question and he said he would provide me with the neede information details, engineering and plan submittals. I ask him to check the bi-fold doors that open into the rear exit way from Dining Areas #1 & #2 so that the doors do not obstruct exiting. He said he would check out and address change on resubmittals if change is needed.
|
Routing - PLANNING | 10/17/1996 | | 10/22/1996 | | PASS |
|
|
|
X-ref: DR-69-96. Approved by TKW.
|
Routing - FIRE | 10/22/1996 | | 10/22/1996 | | FAIL |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/18/1996 | | |
|
|
|
|
Plan resubmittals requested | | | 10/18/1996 | | |
|
|
|
Completed preliminary review. FAXED and mailed copy to the architect for response.
|
Meeting | | | 10/16/1996 | | |
|
|
|
Met with David Ward, CSDI Construction. He was checking on progress of plans and asked if a demo permit could be issued. I told him he would need a description of the work to be done and a certificate of value for the demo and we could issue a permit.
|
Plan resubmittals received | | | 10/11/1996 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/4/1996 | | 10/7/1996 | | PASS |
|
|
|
|
Routing - MECHANICAL | 10/4/1996 | | 10/4/1996 | | FAIL |
|
|
|
DRYER EXHAUST DUCT DRAWINGS OR DETAILS PER UMC
|
Routing - PUBLIC WORKS | 9/27/1996 | | 10/4/1996 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 9/20/1996 | | 9/27/1996 | | PASS |
|
|
|
CONTACTED CHUCK SANDERS AT ###-#### TO TAKE PLANS OUT TO CDH
|
Plan routing begun/TENANTS | | | 9/20/1996 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 9/19/1996 | | |
|
|
|
Route to Central District Health, Public Works, Plumbing, Mechanical then back to Plan Check. After Plan Check route to Fire Department.
|
Gay Receipt For Partial Pay | | | 9/19/1996 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/19/1996 | | PEND |
|
|
|
|
Application received | | | 9/19/1996 | | |
|
|
|
|
INSP - Energy code compliance | 9/6/1996 | 9/6/1996 | 9/6/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - INSULATION OK, OK TO COVER POSTED
|
INSP - Final | 1/7/1997 | 1/7/1997 | 1/7/1996 | P | PASS |
Joe Tawney
|
|
|
OK FOR PERM OCC
|
Permanent Occupancy | | 1/9/1987 | 1/9/1987 | | DONE |
|
|
|
|