CHANGE STATUS TO (D) | | | 3/17/1997 | | PASS |
|
|
|
|
INSP - Letter of compliance | 3/7/1997 | 3/7/1997 | 3/7/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c#12066
|
INSP - Letter of compliance | 3/7/1997 | 3/7/1997 | 3/7/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c#12066
|
INSP - Final | 3/6/1997 | 3/7/1997 | 3/7/1997 | A | PASS |
Alan Hauser
|
|
|
03/07/97 350 - FINAL REINSPECT final, stairway guardrail/handrail approved as per bob archibald
|
INSP - Final | 3/6/1997 | 3/6/1997 | 3/5/1997 | P | FAIL |
|
|
|
03/06/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 12/11/1996 | 12/11/1996 | 12/11/1996 | P | NR |
Wes Worcester
|
|
|
no response from Truss co stamped and signed
|
INSP - Conference | 12/11/1996 | 12/10/1996 | 12/11/1996 | P | PART |
Wes Worcester
|
|
|
Routed engineering response to Bob Garrison for action
|
INSP - Conference | 12/10/1996 | 12/10/1996 | 12/10/1996 | P | PART |
Wes Worcester
|
|
|
Discussed engineering w/Bob Garrison
|
INSP - Framing/Rough-in | 12/9/1996 | 12/10/1996 | 12/10/1996 | A | PART |
Wes Worcester
|
|
|
ROCKERS TO GO AHEAD...REFERRING ENGINEERING FOR TRUSS BRACING TO PLAN CHECK
|
INSP - Carpentry | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | FAIL |
Wes Worcester
|
|
|
trusses not braced as per Idaho truss detail and eng letter of acceptance of variation not received to date
|
INSP - Energy code compliance | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 12/3/1996 | 12/5/1996 | 12/5/1996 | A | PART |
Wes Worcester
|
|
|
doing minor truss bracing
|
Issue PAID IN FULL permit | | | 10/16/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/1996 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/8/1996 | | |
|
|
|
|
Telephone call | | | 10/8/1996 | | |
|
|
|
CALLED AND TOLD THEM PERMIT READY
|
Print Pending Permit.LaserJet4 | | | 10/8/1996 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 9/23/1996 | | 10/8/1996 | | PASS |
Dan Overy
|
|
|
10/08/96 08:40:39 DJO - this action updated by action script from <<>> in Case No. BLD96-2533
|
INSP - Footings | 10/7/1996 | 10/7/1996 | 10/7/1996 | P | PASS |
|
|
|
setbacks seem okay
|
INSP - Footings | 10/7/1996 | 10/7/1996 | 10/7/1996 | | PASS |
|
|
|
/ / 400 - setbacks seem okay
|
Plan resubmittals received | | | 10/7/1996 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 10/4/1996 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 10/4/1996 | | PEND |
|
|
|
|
Routing - PLANNING | 9/24/1996 | | 10/3/1996 | | PASS |
|
|
|
Approved by SR.
|
Routing - PUBLIC WORKS | 9/23/1996 | | 9/24/1996 | | PASS |
|
|
|
|
Application received | | | 9/23/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/23/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/3/1996 | | | | PEND |
|
|
|
|
Routing - FRONT DESK | 10/3/1996 | | | | PEND |
|
|
|
|