Permanent Occupancy | | 12/2/1996 | 12/2/1996 | | DONE |
|
|
|
|
INSP - Permanent occupancy | | | 12/2/1996 | | PASS |
|
|
|
Perm. Occ. Cert. #6725 issued 12-2-96 to Fidelity Funding in the Emerald Corp. Park #4.
|
INSP-Conference | 11/25/1996 | 11/26/1996 | 11/27/1996 | A | CANC |
Joe Tawney
|
|
|
suite 134
|
INSP - Final | 11/26/1996 | 11/26/1996 | 11/26/1996 | A | PASS |
Joe Tawney
|
|
|
OK FOR PERM OCC
|
INSP - Final | 11/25/1996 | 11/26/1996 | 11/26/1996 | P | PASS |
|
|
|
11/26/96 338 -
|
INSP - Framing/Rough-in | 10/29/1996 | 10/30/1996 | 10/29/1996 | P | PASS |
|
|
|
10/30/96 338 - MADEOK OK TO COVER AFTER THE PLMG IS SIGNED OFF
|
Inspection Record Card- Bld | | | 10/8/1996 | | |
|
|
|
|
Print Occupancy Form | | | 10/8/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/8/1996 | | PASS |
|
|
|
|
Plan assigned to (R_H) | 9/27/1996 | | 10/8/1996 | | PASS |
|
|
|
10/08/96 10:00:35 R_H - this action updated by action script from <<>> in Case No. BLD96-2580
|
Routing - PLAN CHECK | 9/30/1996 | | 10/7/1996 | | PEND |
|
|
|
|
Routing - FIRE | 10/7/1996 | | 10/7/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/1/1996 | | PEND |
|
|
|
Started plan review
|
Routing - PUBLIC WORKS | 9/27/1996 | | 9/30/1996 | | PASS |
|
|
|
|
Issue FEE-DUE permit | | | 9/27/1996 | | |
|
|
|
|
Plan routing begun/TENANTS | | | 9/27/1996 | | |
|
|
|
Route to Public Works then back to Plan Check. After Plan Check route to Fire Department.
|
Plan Reviewer's activity | | | 9/27/1996 | | |
|
|
|
PREPARED AND ISSUED A PARTIAL PERMIT AT THE REQUEST OF THE CONTRACTOR (MARV MEYER).
|
Telephone call | | | 9/27/1996 | | |
|
|
|
CALLED AND TOLD MARV PERMIT READY
|
Application received | | | 9/26/1996 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 9/26/1996 | | PEND |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/26/1996 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 10/7/1996 | | | | PEND |
|
|
|
|