CHANGE STATUS TO (D) | | | 1/24/1997 | | PASS |
|
|
|
|
INSP - Letter of compliance | 1/15/1997 | 1/15/1997 | 1/15/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #11462
|
INSP - Final | 1/14/1997 | 1/15/1997 | 1/15/1997 | P | PASS |
Alan Hauser
|
|
|
01/15/97 350 - final
|
INSP - Letter of compliance | 1/15/1997 | 1/15/1997 | 1/15/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #11462
|
INSP - Energy code compliance | 11/14/1996 | 11/15/1996 | 11/15/1996 | A | PASS |
Jim Sly
|
|
|
11/14/96 316 -
|
INSP - Framing/Rough-in | 11/15/1996 | 11/15/1996 | 11/15/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/N Removed...
|
INSP - Framing/Rough-in | 11/12/1996 | 11/13/1996 | 11/13/1996 | A | PASS |
Jim Sly
|
|
|
11/12/96 316 -
|
Issue PAID IN FULL permit | | | 10/8/1996 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/4/1996 | | PASS |
|
|
|
|
Telephone call | | | 10/4/1996 | | |
|
|
|
CALLED 12:20 PM AND LET THEM KNOW PERMIT WAS READY
|
Inspection Record Card- Bld | | | 10/4/1996 | | |
|
|
|
|
Plan resubmittals received | | | 10/4/1996 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 9/27/1996 | | 10/4/1996 | | PASS |
Dan Overy
|
|
|
10/04/96 10:39:04 DJO - this action updated by action script from <<>> in Case No. BLD96-2593
|
INSP - Footings | 10/2/1996 | 10/3/1996 | 10/3/1996 | A | PASS |
Jim Sly
|
|
|
10/02/96 316 -
|
Plan resubmittals requested | | | 10/3/1996 | | PEND |
|
|
|
NEED ADDITIONAL INFORMATION. CALLED DESIGNER AND LEFT MESSAGE.
|
Plans ACCEPTED BY PLAN CHECK | | | 10/3/1996 | | PEND |
|
|
|
|
Routing - PLANNING | 9/30/1996 | | 10/2/1996 | | PASS |
|
|
|
PASSED BY RAC
|
Routing - PUBLIC WORKS | 9/27/1996 | | 9/30/1996 | | PASS |
|
|
|
|
(F) Reprint permit | | | 9/27/1996 | | |
|
|
|
|
Application received | | | 9/27/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/2/1996 | | | | PEND |
|
|
|
|